a
| 
Project A | 
 | 
| 
Year | 
Cash flow stream | 
Cumulative cash flow | 
| 
0 | 
-20000 | 
-20000 | 
| 
1 | 
12000 | 
-8000 | 
| 
2 | 
8000 | 
0 | 
| 
3 | 
6000 | 
6000 | 
| 
Payback period is the time by which undiscounted cashflow cover the
intial investment outlay | 
| 
this is happening at the end of year 2 | 
| 
therefore payback period is: | 
| 
2 Years | 
| 
Project B | 
 | 
| 
Year | 
Cash flow stream | 
Cumulative cash flow | 
| 
0 | 
-20000 | 
-20000 | 
| 
1 | 
10000 | 
-10000 | 
| 
2 | 
6000 | 
-4000 | 
| 
3 | 
16000 | 
12000 | 
| 
Payback period is the time by which undiscounted cashflow cover the
intial investment outlay | 
| 
this is happening between year 2 and 3 | 
| 
therefore by interpolation payback period = 2 +
(0-(-4000))/(12000-(-4000)) | 
| 
2.25 Years | 
Select Project A as it has smaller payback period
b
| 
Project A | 
 | 
Discount rate= | 
15.00% | 
 | 
| 
Year | 
Cash flow stream | 
Cumulative cash flow | 
Discounting factor | 
Discounted cash flows project | 
Cumulative discounted CF | 
| 
0 | 
-20000 | 
-20000 | 
1 | 
-20000 | 
-20000.00 | 
| 
1 | 
12000 | 
-8000 | 
1.15 | 
10434.78261 | 
-9565.22 | 
| 
2 | 
8000 | 
0 | 
1.3225 | 
6049.149338 | 
-3516.07 | 
| 
3 | 
6000 | 
6000 | 
1.520875 | 
3945.097395 | 
429.03 | 
| 
Discounted payback period is the time by which discounted cashflow
cover the intial investment outlay | 
| 
this is happening between year 2 and 3 | 
| 
therefore by interpolation payback period = 2 +
(0-(-3516.07))/(429.03-(-3516.07)) | 
| 
2.89 Years | 
| 
 | 
| 
Where | 
| 
Discounting factor =(1 + discount rate)^(corresponding year) | 
| 
Discounted Cashflow=Cash flow stream/discounting factor | 
| 
Project B | 
 | 
Discount rate= | 
15.00% | 
 | 
| 
Year | 
Cash flow stream | 
Cumulative cash flow | 
Discounting factor | 
Discounted cash flows project | 
Cumulative discounted CF | 
| 
0 | 
-20000 | 
-20000 | 
1 | 
-20000 | 
-20000.00 | 
| 
1 | 
10000 | 
-10000 | 
1.15 | 
8695.652174 | 
-11304.35 | 
| 
2 | 
6000 | 
-4000 | 
1.3225 | 
4536.862004 | 
-6767.49 | 
| 
3 | 
16000 | 
12000 | 
1.520875 | 
10520.25972 | 
3752.77 | 
| 
Discounted payback period is the time by which discounted cashflow
cover the intial investment outlay | 
| 
this is happening between year 2 and 3 | 
| 
therefore by interpolation payback period = 2 +
(0-(-6767.49))/(3752.77-(-6767.49)) | 
| 
2.64 Years | 
| 
 | 
| 
Where | 
| 
Discounting factor =(1 + discount rate)^(corresponding year) | 
| 
Discounted Cashflow=Cash flow stream/discounting factor | 
Select project B as it has lower discounted payback
c
| 
Project A | 
 | 
 | 
 | 
 | 
| 
Discount rate | 
15.000% | 
 | 
 | 
 | 
| 
Year | 
0 | 
1 | 
2 | 
3 | 
| 
Cash flow stream | 
-20000 | 
12000 | 
8000 | 
6000 | 
| 
Discounting factor | 
1.000 | 
1.150 | 
1.323 | 
1.521 | 
| 
Discounted cash flows project | 
-20000.000 | 
10434.783 | 
6049.149 | 
3945.097 | 
| 
NPV = Sum of discounted cash flows | 
 | 
 | 
 | 
 | 
| 
NPV Project A = | 
429.03 | 
 | 
 | 
 | 
| 
Where | 
 | 
 | 
 | 
 | 
| 
Discounting factor = | 
(1 +
discount rate)^(Corresponding period in years) | 
 | 
| 
Discounted Cashflow= | 
Cash flow
stream/discounting factor | 
 | 
 | 
| 
Project B | 
 | 
 | 
 | 
 | 
| 
Discount rate | 
15.000% | 
 | 
 | 
 | 
| 
Year | 
0 | 
1 | 
2 | 
3 | 
| 
Cash flow stream | 
-20000 | 
10000 | 
6000 | 
16000 | 
| 
Discounting factor | 
1.000 | 
1.150 | 
1.323 | 
1.521 | 
| 
Discounted cash flows project | 
-20000.000 | 
8695.652 | 
4536.862 | 
10520.260 | 
| 
NPV = Sum of discounted cash flows | 
 | 
 | 
 | 
 | 
| 
NPV Project B = | 
3752.77 | 
 | 
 | 
 | 
| 
Where | 
 | 
 | 
 | 
 | 
| 
Discounting factor = | 
(1 +
discount rate)^(Corresponding period in years) | 
 | 
| 
Discounted Cashflow= | 
Cash flow
stream/discounting factor | 
 | 
 | 
Select project B as it has higher NPV
d
| 
Project A | 
 | 
 | 
 | 
 | 
| 
IRR is the rate at which NPV =0 | 
 | 
 | 
 | 
 | 
| 
IRR | 
16.46% | 
 | 
 | 
 | 
| 
Year | 
0 | 
1 | 
2 | 
3 | 
| 
Cash flow stream | 
-20000.000 | 
12000.000 | 
8000.000 | 
6000.000 | 
| 
Discounting factor | 
1.000 | 
1.165 | 
1.356 | 
1.580 | 
| 
Discounted cash flows project | 
-20000.000 | 
10303.667 | 
5898.087 | 
3798.245 | 
| 
NPV = Sum of discounted cash flows | 
 | 
 | 
 | 
 | 
| 
NPV Project A = | 
0.000 | 
 | 
 | 
 | 
| 
Where | 
 | 
 | 
 | 
 | 
| 
Discounting factor = | 
(1 +
discount rate)^(Corresponding period in years) | 
 | 
| 
Discounted Cashflow= | 
Cash flow
stream/discounting factor | 
 | 
 | 
| 
Project B | 
 | 
 | 
 | 
 | 
| 
IRR is the rate at which NPV =0 | 
 | 
 | 
 | 
 | 
| 
IRR | 
25.10% | 
 | 
 | 
 | 
| 
Year | 
0 | 
1 | 
2 | 
3 | 
| 
Cash flow stream | 
-20000.000 | 
10000.000 | 
6000.000 | 
16000.000 | 
| 
Discounting factor | 
1.000 | 
1.251 | 
1.565 | 
1.958 | 
| 
Discounted cash flows project | 
-20000.000 | 
7993.637 | 
3833.894 | 
8172.469 | 
| 
NPV = Sum of discounted cash flows | 
 | 
 | 
 | 
 | 
| 
NPV Project B = | 
0.000 | 
 | 
 | 
 | 
| 
Where | 
 | 
 | 
 | 
 | 
| 
Discounting factor = | 
(1 +
discount rate)^(Corresponding period in years) | 
 | 
| 
Discounted Cashflow= | 
Cash flow
stream/discounting factor | 
 | 
 | 
Select project B as it has higher IRR