Roberta wants to compare productivity, as measured by the number of customers served, among three workers....

Roberta wants to compare productivity, as measured by the number of customers served, among three workers. The number of customers served by each worker is shown below.

Edward

Cathy

Brad

55

66

55

59

76

51

66

67

46

60

71

48

  1. Is there a difference in the number of customers served? The level of significance is 0.01. Show all the five steps of the hypothesis testing.

Solutions

Expert Solution

Here we have data:

Edward Cathy Brad
55 66 55
59 76 51
66 67 46
60 71 48

Here we are using excel for calculation:

Anova: Single Factor
SUMMARY
Groups Count Sum Average Variance
55 3 185 61.6667 14.3333
66 3 214 71.3333 20.3333
55 3 145 48.3333 6.3333
ANOVA
Source of Variation SS df MS F P-value F crit
Between Groups 800.2222 2 400.1111 29.2764 0.0008 10.9248
Within Groups 82 6 13.6667
Total 882.2222 8

Hypothesis:

Ho; μ1 = μ2 = μ3

Ha; At least one mean is difference from others.

Test statistics:

F = 29.2764

P-value = 0.0008

Critical value:

Fc = 10.9248

Reject the null hypothesis

Here we have sufficient evidence to reject the null hypothesis , F-observed value (29.2764) is greater than F-critical value (10.9248) and p-value (0.0008) is less than alpha value (0.01).

We can say that there is a difference in the number of customers served.


Related Solutions

The data in this file are the differences in the productivity of workers measured before and...
The data in this file are the differences in the productivity of workers measured before and after they undertake a training program. x 3.483286 0.502139 1.182506 -0.78977 -1.23055 0.050956 -0.55935 -0.44297 -0.28723 -2.20755 -1.29574 -2.37856 1.590792 -1.07265 -0.51803 0.88382 -1.20074 -0.37303 0.046192 0.178191 3.011939 0.370306 -1.16088 0.896363 0.921949 -0.79235 -0.65858 1.442165 1.291734 -1.19235 0.77025 0.130772 0.170839 0.424066 0.144973 -2.14435 0.925843 2.61098 1.358568 1.635042 -0.39504 0.493437 -0.12331 -1.35487 0.336548 -2.47492 -2.26872 -0.25936 -0.54652 1.104589 -0.39521 3.072957 1.835252 -1.30094 2.040434 2.496305 0.567188...
. A manufacturing company measured the productivity of its workers and found that: • between the...
. A manufacturing company measured the productivity of its workers and found that: • between the hours of 6am and 10am they could produce 30 pieces/hour/worker • between 10am and 2pm they could produce 40 pieces/hour/worker • between 2pm and 6pm they could produce 35 pieces/hour/worker. Write a function pieces_produced takes a number that represents a starting hour between 6am and 6pm, in twenty-four hour format (between 0 and 23), along with the number of workers and returns a number...
A manufacturing company measured the productivity of its workers and found that: between the hours of...
A manufacturing company measured the productivity of its workers and found that: between the hours of 6am and 10am they could produce 30 pieces/hour/worker between 10am and 2pm they could produce 40 pieces/hour/worker between 2pm and 6pm they could produce 35 pieces/hour/worker. Write a function pieces_produced takes a number that represents a starting hour between 6am and 6pm, in twenty-four hour format (between 0 and 23), along with the number of workers and returns a number that represents the total...
1. A manufacturing company measured the productivity of its workers and found that: • between the...
1. A manufacturing company measured the productivity of its workers and found that: • between the hours of 6am and 10am they could produce 30 pieces/hour/worker • between 10am and 2pm they could produce 40 pieces/hour/worker • between 2pm and 6pm they could produce 35 pieces/hour/worker. Write a function pieces_produced takes a number that represents a starting hour between 6am and 6pm, in twenty-four hour format (between 0 and 23), along with the number of workers and returns a number...
Firm ABC uses two inputs, blue workers and purple workers (measured in number of workers) to...
Firm ABC uses two inputs, blue workers and purple workers (measured in number of workers) to produce output. At Firm ABC’s current input bundle, the marginal product of blue workers is two times the marginal product of purple workers. The wage for a purple worker is one third of the wage for a blue worker. Is the firm currently minimizing its cost of production?
Berg Corporation is a service company that measures its output by the number of customers served....
Berg Corporation is a service company that measures its output by the number of customers served. The company has provided the following fixed and variable cost estimates that it uses for budgeting purposes. Fixed Element per Month Variable Element per Customer Served Revenue $ 4,200 Employee salaries and wages $ 58,800 $ 900 Travel expenses $ 700 Other expenses 33,300 When the company prepared its planning budget at the beginning of March, it assumed that 40 customers would have been...
A manufacturer wants to compare the number of defects on the day shift with the number...
A manufacturer wants to compare the number of defects on the day shift with the number on the evening shift. A sample of production from recent shifts showed the following defects: Day Shift​​: 6​ 9​ 8​ 7​ 10​ 8 Evening Shift: ​​9​ 11​ 8​ 12​ 10​ 13​ 15​ 10 The objective is to determine whether the mean number of defects on the night shift is greater than the mean number on the day shift at the 95% confidence level. a)...
A manufacturer wants to compare the number of defects on the day shift with the number...
A manufacturer wants to compare the number of defects on the day shift with the number on the evening shift. A sample of production from recent shifts showed the following defects: Day Shift 6 9 8 7 10 8 Evening Shift 9 11 8 12 10 13 15 10 The objective is to determine whether the mean number of defects on the night shift is greater than the mean number on the day shift at the 95% confidence level. a)...
A manufacturer wants to compare the number of defects on the day shift with the number...
A manufacturer wants to compare the number of defects on the day shift with the number on the evening shift. A sample of production from recent shifts showed the following defects: Day Shift 5 8 7 6 9 7 Evening Shift 8 10 7 11 9 12 14 9 The objective is to determine whether the mean number of defects on the night shift is greater than the mean number on the day shift at the 95% confidence level. State...
A manufacturer wants to compare the number of defects on the day shift with the number...
A manufacturer wants to compare the number of defects on the day shift with the number on the evening shift. A sample of production from recent shifts showed the following defects: Day Shift                     5          8          7          6          9          7 Evening Shift              8          10        7          11        9          12            14        9 The objective is to determine whether the mean number of defects on the night shift is greater than the mean number on the day shift at the 95% confidence level....
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT