Question

In: Statistics and Probability

Amusement Park ABC has an average of 230 customers per hour arriving at a ticket counter...

Amusement Park ABC has an average of 230 customers per hour arriving at a ticket counter where 8 employees are working. Each employee can serve an average of 30 customers per hour. The squared coefficient of variation for the inter-arrival times is 1.5 and 2 for the service times. a) On average, how many customers will be present at the ticket counter? b) On average, how long will a customer have to wait for an employee?

Solutions

Expert Solution


Related Solutions

A food store has an average of 220 customers arriving per hour during peak shopping hours....
A food store has an average of 220 customers arriving per hour during peak shopping hours. During these peak periods all eight checkout counters will be open and operating with a capacity of serving an average of 35 customers per hour per counter. All checkout counters are identical. A. What proportion of the time would all of the checkout counters and waiting lines be empty of customers? B. How long would customers wait in line on the average? C. How...
The number of customers arriving per hour at a certain automobile service facility is assumed to...
The number of customers arriving per hour at a certain automobile service facility is assumed to follow a Poisson distribution with mean λ=5. a) Compute the probability that more than 11 customers will arrive in a 2​-hour period. b) What is the mean number of arrivals during a 2​-hour ​period?
The number of customers arriving per hour at a certain automobile service facility is assumed to...
The number of customers arriving per hour at a certain automobile service facility is assumed to follow a Poisson distribution with mean λ=9. ​(a) Compute the probability that more than 16 customers will arrive in a 2-hour period.​ (b) What is the mean number of arrivals during a 2-hour period? ​(a) The probability that more than 16 customers will arrive is ​(Round to four decimal places as​ needed.) ​(b) The mean number of arrivals is ​(Type an integer or a...
Customers arrive at the rate of 100 per hour. The ticket seller averages 30 seconds per...
Customers arrive at the rate of 100 per hour. The ticket seller averages 30 seconds per customer. What is the average customer time in the system?
It is assumed that there is an average of 12 customers per hour at a service...
It is assumed that there is an average of 12 customers per hour at a service counter according to a Poisson process. a) How likely is it that 4 customers show up at this counter in the next 15 minutes? b) Given that 4 customers showed up at this counter in a given 15-minute period, what is the probability that there were at least 2 customers that showed up in the last 5 minutes of this period?
You are assessing the viability of operating an amusement park. The nominal revenues from ticket sales...
You are assessing the viability of operating an amusement park. The nominal revenues from ticket sales at the end of Year 1 will be $554176. They will increase by 4% per year in real terms. The only annual cost will be to lease the whole operation for $118845 per year. The leasing costs are nominal and will start at the end of Year 1. They will stay fixed in nominal terms. Assume the inflation rate is 5% and the real...
An amusement park has estimated the following demand equation for the average park guest Q=16-2P Where...
An amusement park has estimated the following demand equation for the average park guest Q=16-2P Where Q represents the number of rides per guest and P the price per ride. The total cost of providing rides to a guest is TC=2+0.5Q If a one-price policy is used, how much should it charge per ride if the park wishes to maximize its profit? What is the park's profit for each guest? If a two-part tariff policy is used, what admission fee...
An amusement park has estimated the following demand equation for the average park guest Q=16?2P Where...
An amusement park has estimated the following demand equation for the average park guest Q=16?2P Where Q represents the number of rides per guest and P the price per ride. The total cost of providing rides to a guest is TC=2+0.5Q If a one-price policy is used, how much should it charge per ride if the park wishes to maximize its profit? What is the park's profit for each guest? If a two-part tariff policy is used, what admission fee...
Customers are arriving to a shop according to Poisson process with mean 3.2 customers/hour. What is...
Customers are arriving to a shop according to Poisson process with mean 3.2 customers/hour. What is the probability that the next customer will arrive after 10 minutes but before 33 minutes?
A small auto parts store has a single counter with one employee. Customers arrive at the counter at the rate of 10 per hour according to a Poisson distribution.
 A small auto parts store has a single counter with one employee. Customers arrive at the counter at the rate of 10 per hour according to a Poisson distribution. The employee can handle 20 customers per hour and service times are exponentially distributed. Calculate (A) The probability that a customer finds an empty counter in the auto parts store (no customers waiting or being served) (B) The average number of customers waiting in the que at the auto parts store (i.e.,...
ADVERTISEMENT