Question

In: Operations Management

Wilson Company had the following quality costs for 2014: Testing      $ 120,000 Rework           55,000 Training...

Wilson Company had the following quality costs for 2014:

Testing      $ 120,000
Rework           55,000
Training           90,000
Product liability insurance           70,000
Quality planning           86,000
Customer surveys           30,000
Re-inspection and retesting           35,000
Warranty repairs         100,000
Total quality costs         $ 586,000



Sales for 2014 were $2,000,000.

What is the amount of appraisal costs?

Solutions

Expert Solution

Cost of quality is a methodology that allows an organization to determine the extent to which its resources are used for activities that prevent poor quality. Quality-related activities that incur costs may be divided into prevention costs, appraisal costs, and internal and external failure costs.

Appraisal costs are associated with measuring and monitoring activities related to quality. These costs are associated with the suppliers’ and customers’ evaluation of purchased materials, processes, products, and services to ensure that they conform to specifications. They could include:

  • Verification—checking of incoming material, process setup, and products against agreed specifications
  • Quality audits—confirmation that the quality system is functioning correctly
  • Supplier rating—assessment and approval of suppliers of products and services

In the given example, following therefore should be included as part of Appraisal cost :

“ customer survey = 30,000”

Therefore, amount of appraisal cost will be $ 30,000

APPRISAL COST $30,000


Related Solutions

Schedule of Activity Costs Quality Control Activities Activity Cost Product testing $55,000 Assessing vendor quality 26,000...
Schedule of Activity Costs Quality Control Activities Activity Cost Product testing $55,000 Assessing vendor quality 26,000 Recalls 18,000 Rework 29,000 Scrap disposal 8,000 Product design 30,000 Training machine operators 46,000 Warranty work 12,000 Process audits 22,000 ​ From the provided schedule of activity costs, compute the percentage of non-value-added activities. Round to one decimal place. HTML EditorKeyboard Shortcuts
Below are the quality costs data for a company for 2014 & 2015 2014 2015 Prevention...
Below are the quality costs data for a company for 2014 & 2015 2014 2015 Prevention $90,000 $110,000 Appraisal $50,000 $62,000 Internal Faliure $40,000 $34,000 External Faliure $62,000 $60,000 Sales: $5,100,000 $5,350,000 A) whats the precentage change in the total quality index between 2014 & 2015 B) What is the percentage change in the precention quality index between 2014 & 2015 C) What is the percentage change in the internal faliure quality index between 2014 & 2015 ? D) Do...
Below are the quality costs data for a company for 2014 & 2015 2014 2015 Prevention...
Below are the quality costs data for a company for 2014 & 2015 2014 2015 Prevention $90,000 $110,000 Appraisal $50,000 $62,000 Internal Faliure $40,000 $34,000 External Faliure $62,000 $60,000 Sales: $5,100,000 $5,350,000 A) whats the precentage change in the total quality index between 2014 & 2015 B) What is the percentage change in the precention quality index between 2014 & 2015 C) What is the percentage change in the internal faliure quality index between 2014 & 2015 ? D) Do...
STATEMENT OF CASH FLOWS   W.C. Cycling had $55,000 in cash at year-end 2014 and $25,000 in...
STATEMENT OF CASH FLOWS   W.C. Cycling had $55,000 in cash at year-end 2014 and $25,000 in cash at year-end 2015. The firm invested in property, plant, and equipment totaling $250,000. Cash flow from financing activities totaled   $170,000. a.   What was the cash flow from operating activities? b.   If accruals increased by $25,000, receivables and inventories increased by $100,000, and depreciation and amortization totaled $10,000, what was the firm’s net income?
STATEMENT OF CASH FLOWS W.C. Cycling had $55,000 in cash at year-end 2014 and $25,000 in...
STATEMENT OF CASH FLOWS W.C. Cycling had $55,000 in cash at year-end 2014 and $25,000 in cash at year-end 2015. The firm invested in property, plant, and equipment totaling $250,000. Cash flow from financing activities totaled $170,000. a. What was the cash flow from operating activities? b. If accruals increased by $25,000, receivables and inventories increased by $100,000, and depreciation and amortization totaled $10,000, what was the firm’s net income?
Interim Quality Performance Report Davis, Inc., had the following quality costs for the years ended December...
Interim Quality Performance Report Davis, Inc., had the following quality costs for the years ended December 31, 20x4 and 20x5: 20x4 20x5 Prevention costs:     Quality audits $66,000        $99,000            Vendor certification 121,500        182,250        Appraisal costs:     Product acceptance $90,000        $135,000            Process acceptance 87,000        102,500        Internal failure costs:     Retesting $100,000        $94,000            Rework 200,000        170,000        External failure costs:     Recalls $145,000        $116,000            Warranty 315,000        318,000        At the end of 20x4, management decided to increase its investment in control costs by 50 percent for each category’s...
Interim Quality Performance Report Davis, Inc., had the following quality costs for the years ended December...
Interim Quality Performance Report Davis, Inc., had the following quality costs for the years ended December 31, 20x4 and 20x5: 20x4 20x5 Prevention costs:     Quality audits $60,000        $90,000            Vendor certification 127,500        191,250        Appraisal costs:     Product acceptance $84,000        $126,000            Process acceptance 93,000        115,000        Internal failure costs:     Retesting $98,000        $86,000            Rework 204,000        185,000        External failure costs:     Recalls $152,500        $122,000            Warranty 305,000        302,000        At the end of 20x4, management decided to increase its investment in control costs by 50 percent for each category’s...
Interim Quality Performance Report Davis, Inc., had the following quality costs for the years ended December...
Interim Quality Performance Report Davis, Inc., had the following quality costs for the years ended December 31, 20x4 and 20x5: 20x4 20x5 Prevention costs:     Quality audits $65,000        $97,500            Vendor certification 123,500        185,250        Appraisal costs:     Product acceptance $91,000        $136,500            Process acceptance 99,000        110,000        Internal failure costs:     Retesting $92,000        $96,000            Rework 204,000        173,000        External failure costs:     Recalls $140,000        $112,000            Warranty 325,000        294,000        At the end of 20x4, management decided to increase its investment in control costs by 50 percent for each category’s...
Cornerstone Exercise 14.2 (Algorithmic) Interim Quality Performance Report Davis, Inc., had the following quality costs for...
Cornerstone Exercise 14.2 (Algorithmic) Interim Quality Performance Report Davis, Inc., had the following quality costs for the years ended December 31, 2014 and 2015: 2014 2015 Prevention costs:     Quality audits $68,000        $102,000            Vendor certification 125,500        188,250        Appraisal costs:     Product acceptance $91,000        $136,500            Process acceptance 97,000        107,500        Internal failure costs:     Retesting $92,000        $82,000            Rework 173,000        214,000        External failure costs:     Recalls $127,500        $102,000            Warranty 315,000        318,000        At the end of 2014, management decided to increase its investment in control costs by 50...
X Company has the following information available for the year 2014: Quality engineering of products                         &nbsp
X Company has the following information available for the year 2014: Quality engineering of products                                 $20,000 Quality training of employees                                      $2,000 Net cost of scrap                                                        $30,000 Rework labor                                                               $4,500 Warranty repairs                                                      $100,000 Product recalls                                                         $200,000 Liability arising from defective products              $1,000,000 Maintenance of test equipment                                   $44,000 Quality improvement projects                                    $55,000 Setups for testing                                                          $3,000 Supplies used in testing                                                $5,500 Downtime caused by defects                                      $70,000 Disposal of defective products                                  $80,000 Sales revenue $5,000,000    Required: a. Prepare the quality cost report....