PAYBACK PERIOD
Project L costs $65,000, its expected cash inflows are $14,000 per year for 11 years, and its WACC is 9%. What is the project's payback? Round your answer to two decimal places.
__ years
Calculation of payback period : | ||
Time | Amount | Cumulative |
- | (65,000.00) | (65,000.00) |
1.00 | 14,000.00 | (51,000.00) |
2.00 | 14,000.00 | (37,000.00) |
3.00 | 14,000.00 | (23,000.00) |
4.00 | 14,000.00 | (9,000.00) |
5.00 | 14,000.00 | 5,000.00 |
6.00 | 14,000.00 | 19,000.00 |
7.00 | 14,000.00 | 33,000.00 |
8.00 | 14,000.00 | 47,000.00 |
9.00 | 14,000.00 | 61,000.00 |
10.00 | 14,000.00 | 75,000.00 |
11.00 | 14,000.00 | 89,000.00 |
Payback Period= 4+9000/14000 | ||
Payback Period= 4.64 years |