A mortgage service office has the following four activities involved in approving a loan application. Note that a working day is 8 hours and there are 60 minutes in one hour.
Activity | Time (minutes) |
A. Property survey | 20 |
B. Credit report | 15 |
C. Title search | 30 |
D. Final decision | 25 |
1. If each activity is performed by a different person, with four employees, what would be the maximum number of loan applications the office can process per day? And what is the office's direct labor utilization (DLU) ?
2. Activities B and C are combined together and assigned to two employees, while the other two employees are responsible for activities A and D respectively. What would be the maximum number of loan applications the office can process per day? And what is the office's direct labor utilization (DLU) ?
3. The office now has only three employees, activities B and C are combined together and assigned to one employee, while the other two employees are responsible for activities A and D respectively. Under this setting, what would be the maximum number of loan applications the office can process per day? And what is the office's direct labor utilization (DLU) ?
4. The office now has only three employees, activities A, B and C are combined together and assigned to two employees, while the other employee is responsible for the last activity D . Under this setting, what would be the maximum number of loan applications the office can process per day? And what is the office's direct labor utilization (DLU) ?
5. With three employees, every employee can perform any activity and more than one activity. Under this setting, What would be the maximum number of loan applications the office can process per day? And what is the office's direct labor utilization (DLU) ?
There are seven tasks in an assembly line, from which a product with a relative stable demand is produced. The time needed for each task (in minutes) and the relationships among tasks are in the graph below (note that activity C is linked to activity D). The assembly line operates 8 hours a day. The daily customer demand for the product is 100 units. Please design/balance this assembly line, so that supply and demand would be matched the most efficiently way possible.
1.
Activity | Processing Time (P) | Number of resources (N) |
Capacity per day = 8*60*N/P |
A. Property survey | 20 | 1 | 24 |
B. Credit report | 15 | 1 | 32 |
C. Title search | 30 | 1 | 16 |
D. Final decision | 25 | 1 | 19.2 |
Cycle time = Max(20, 15, 30, 25) = 30 minutes
Capacity = Min(24, 32, 16, 19.2) = 16 per day
DLU = Total direct labor content / (Cycle time * # workers) = 90 / (30*4) = 0.75 or 75%
2.
Activity | Processing Time (P) | Number of resources (N) |
Capacity per day = 8*60*N/P |
A | 20 | 1 | 24.00 |
B & C | 45 | 2 | 21.33 |
D | 25 | 1 | 19.20 |
Cycle time = Max(20, 45/2, 25) = 25 minutes
Capacity = Min(24, 21.33, 19.20) = 19.2 per day
DLU = Total direct labor content / (Cycle time * # workers) = 90 / (25*4) = 0.90 or 90%
3.
Activity | Processing Time (P) | Number of resources (N) |
Capacity per day = 8*60*N/P |
A | 20 | 1 | 24.00 |
B & C | 45 | 1 | 10.67 |
D | 25 | 1 | 19.20 |
Cycle time = Max(20, 45, 25) = 45 minutes
Capacity = Min(24, 10.67, 19.2) = 10.67 per day
DLU = Total direct labor content / (Cycle time * # workers) = 90 / (45*3) = 0.67 or 67%
4.
Activity | Processing Time (P) | Number of resources (N) |
Capacity per day = 8*60*N/P |
A, B, & C | 65 | 2 | 14.77 |
D | 25 | 1 | 19.20 |
Cycle time = Max(65/2, 25) = 65/2 = 32.5 minutes
Capacity = Min(14.77, 19.2) = 14.77 per day
DLU = Total direct labor content / (Cycle time * # workers) = 90 / (32.5*3) = 0.92 or 92%