Question

In: Accounting

As of the end of June, the job cost sheets at Racing Wheels, Inc., show the...

As of the end of June, the job cost sheets at Racing Wheels, Inc., show the following total costs accumulated on three custom jobs. Job 102 Job 103 Job 104 Direct materials $ 17,000 $ 64,000 $ 57,000 Direct labor 13,000 29,500 45,000 Overhead 6,240 14,160 21,600 Job 102 was started in production in May and the following costs were assigned to it in May: direct materials, $10,000; direct labor, $3,100; and overhead, $1,488. Jobs 103 and 104 are started in June. Overhead cost is applied with a predetermined rate based on direct labor cost. Jobs 102 and 103 are finished in June, and Job 104 is expected to be finished in July. No raw materials are used indirectly in June. Using this information, answer the following questions. (Assume this company’s predetermined overhead rate did not change across these months). 1. What is the cost of the raw materials requisitioned in June for each of the three jobs? (Omit the "$" sign in your response.) Job 102 $ Job 103 $ Job 104 $ 2. How much direct labor cost is incurred during June for each of the three jobs? (Omit the "$" sign in your response.) Job 102 $ Job 103 $ Job 104 $ 3. What predetermined overhead rate is used during June? (Omit the "%" sign in your response.) Predetermined overhead rate % 4. How much total cost is transferred to finished goods during June? (Omit the "$" sign in your response.) Total transferred cost $

Solutions

Expert Solution

1) Calculation of cost of the raw materials requisitioned in June (Amount in $)

Job May (a) June (b = c-a) Total (c)
Job 102 10,000 7,000 17,000
Job 103 0 64,000 64,000
Job 104 0 57,000 57,000
Total 10,000 128,000 138,000

2) Calculation of labor cost for June (Amount in $)

Job May (a) June (b = c-a) Total (c)
Job 102 3,100 9,900 13,000
Job 103 0 29,500 29,500
Job 104 0 45,000 45,000
Total 3,100 84,400 87,500

3) Predetermined Overhead rate for the month will be equal to predetermined overhead rate for Job 102.

Predetermined Overhead rate = Estimated Overhead costs (Job 102)/Estimated Direct Labor (Job 102)

= $6,240/$13,000 = 0.48 or 48%

4) Calculation of cost transferred to Finished goods during june (Amt in $)

Job Direct Materials (A) Direct Labor (B) Applied Overhead (C = B*48%) Total Cost (A+B+C) Cost transferred to Finished Goods
102 17,000 13,000 6,240 36,240 36,240
103 64,000 29,500 14,160 107,660 107,660
104 57,000 45,000 21,600 123,600 0
Total 138,000 87,500 42,000 267,500 143,900

Only job 102 and 103 is completed in june hence only cost related to job 102 and 103 will be transferred to finished goods.


Related Solutions

As of the end of June, the job cost sheets at Racing Wheels, Inc., show the...
As of the end of June, the job cost sheets at Racing Wheels, Inc., show the following total costs accumulated on three custom jobs. Job 102 Job 103 Job 104 Direct materials $ 44,000 $ 54,000 $ 49,000 Direct labor 16,000 29,100 44,000 Overhead applied 5,440 9,894 14,960 Job 102 was started in production in May, and the following costs were assigned to it in May: direct materials, $10,000; direct labor, $3,300; and overhead, $1,122. Jobs 103 and 104 were...
As of the end of June, the job cost sheets at Racing Wheels, Inc., show the...
As of the end of June, the job cost sheets at Racing Wheels, Inc., show the following total costs accumulated on three custom jobs. Job 102 Job 103 Job 104 Direct materials $ 41,000 $ 51,000 $ 65,000 Direct labor 12,000 29,700 39,000 Overhead applied 5,400 13,365 17,550 Job 102 was started in production in May and the following costs were assigned to it in May: direct materials, $13,000; direct labor, $3,500; and overhead, $1,575. Jobs 103 and 104 were...
As of the end of June, the job cost sheets at Racing Wheels, Inc., show the...
As of the end of June, the job cost sheets at Racing Wheels, Inc., show the following total costs accumulated on three custom jobs. Job 102 Job 103 Job 104 Direct materials $ 43,000 $ 73,000 $ 53,000 Direct labor 11,000 28,600 43,000 Overhead applied 4,400 11,440 17,200 Job 102 was started in production in May and the following costs were assigned to it in May: direct materials, $13,000; direct labor, $4,000; and overhead, $1,600. Jobs 103 and 104 were...
As of the end of June, the job cost sheets at Racing Wheels, Inc., show the...
As of the end of June, the job cost sheets at Racing Wheels, Inc., show the following total costs accumulated on three custom jobs. Job 102 Job 103 Job 104 Direct materials $ 21,000 $ 55,000 $ 59,000 Direct labor 12,000 29,700 44,000 Overhead applied 4,560 11,286 16,720 Job 102 was started in production in May, and the following costs were assigned to it in May: direct materials, $8,000; direct labor, $3,300; and overhead, $1,254. Jobs 103 and 104 were...
As of the end of June, the job cost sheets at Racing Wheels, Inc., show the...
As of the end of June, the job cost sheets at Racing Wheels, Inc., show the following total costs accumulated on three custom jobs. Job 102 Job 103 Job 104 Direct materials $ 41,000 $ 56,000 $ 48,000 Direct labor 15,000 28,500 45,000 Overhead applied 6,300 11,970 18,900 Job 102 was started in production in May, and the following costs were assigned to it in May: direct materials, $9,000; direct labor, $3,600; and overhead, $1,512. Jobs 103 and 104 were...
As of the end of June, the job cost sheets at Racing Wheels, Inc., show the...
As of the end of June, the job cost sheets at Racing Wheels, Inc., show the following total costs accumulated on three custom jobs. Job 102 Job 103 Job 104 Direct materials $ 41,000 $ 56,000 $ 48,000 Direct labor 15,000 28,500 45,000 Overhead applied 6,300 11,970 18,900 Job 102 was started in production in May, and the following costs were assigned to it in May: direct materials, $9,000; direct labor, $3,600; and overhead, $1,512. Jobs 103 and 104 were...
As of the end of June, the job cost sheets at Racing Wheels, Inc., show the...
As of the end of June, the job cost sheets at Racing Wheels, Inc., show the following total costs accumulated on three custom jobs. Job 102 Job 103 Job 104   Direct materials $ 27,000 $ 56,000   $ 51,000     Direct labor 17,000 26,700   46,000   Overhead 6,800 10,680   18,400 Job 102 was started in production in May and the following costs were assigned to it in May: direct materials, $12,000; direct labor, $3,200; and overhead, $1,280. Jobs 103 and 104 are started...
As of the end of June, the job cost sheets at Racing Wheels, Inc., show the...
As of the end of June, the job cost sheets at Racing Wheels, Inc., show the following total costs accumulated on three custom jobs. Job 102 Job 103 Job 104 Direct materials $ 44,000 $ 54,000 $ 53,000 Direct labor 16,000 30,000 41,000 Overhead applied 5,280 9,900 13,530 Job 102 was started in production in May, and the following costs were assigned to it in May: direct materials, $11,000; direct labor, $3,400; and overhead, $1,122. Jobs 103 and 104 were...
At the end of June, the job cost sheets for Monson Manufacturing show the following total...
At the end of June, the job cost sheets for Monson Manufacturing show the following total costs accumulated on three custom jobs. Job 203 Job 204 Job 205 Direct materials $32,000 $47,000 $43,000 Direct labor 18,000 22,000 25,000 Overhead 26,100 31,900 36,250 Job 203 was started in production in May and the following costs were assigned to it in May: direct materials, $12,000; direct labor, $6,000; and overhead $8,700. Jobs 204 and 205 are started in June. Overhead cost is...
The daily cost of producing x high performance wheels for racing is given by the following...
The daily cost of producing x high performance wheels for racing is given by the following function, where no more than 100 wheelscan be produced each day. What production level will give the lowest average cost per wheel? What is the minimum average cost? C(x)=0.09x^3 - 4.5x^2 + 171x;(0,100] what production level will give the lowest average cost per wheel? x=_
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT