Question

In: Math

The daily cost of producing x high performance wheels for racing is given by the following...

The daily cost of producing x high performance wheels for racing is given by the following function, where no more than 100 wheelscan be produced each day. What production level will give the lowest average cost per wheel? What is the minimum average cost?

C(x)=0.09x^3 - 4.5x^2 + 171x;(0,100]

what production level will give the lowest average cost per wheel?
x=_

Solutions

Expert Solution

we have,

we know that average cost is given by,

Hence,

we can write,

equate it to 0 we can say that,

Hence we can say that x = 25 is the critical point of average cost function

we have to find the production level x that will give the minimum average cost given that x must be in a range of (0, 100] means it can not be 0 but it can be 100 or less than 100

we have,

Evaluate the average cost function at x = 25 and x = 100

we can write,

we can see that average cost is minimum at x = 25

Hence we can say that production level of x = 25 per wheel will give lowest average cost per wheel and minimum average cost is $114.75


Related Solutions

As of the end of June, the job cost sheets at Racing Wheels, Inc., show the...
As of the end of June, the job cost sheets at Racing Wheels, Inc., show the following total costs accumulated on three custom jobs. Job 102 Job 103 Job 104 Direct materials $ 44,000 $ 54,000 $ 49,000 Direct labor 16,000 29,100 44,000 Overhead applied 5,440 9,894 14,960 Job 102 was started in production in May, and the following costs were assigned to it in May: direct materials, $10,000; direct labor, $3,300; and overhead, $1,122. Jobs 103 and 104 were...
As of the end of June, the job cost sheets at Racing Wheels, Inc., show the...
As of the end of June, the job cost sheets at Racing Wheels, Inc., show the following total costs accumulated on three custom jobs. Job 102 Job 103 Job 104 Direct materials $ 41,000 $ 51,000 $ 65,000 Direct labor 12,000 29,700 39,000 Overhead applied 5,400 13,365 17,550 Job 102 was started in production in May and the following costs were assigned to it in May: direct materials, $13,000; direct labor, $3,500; and overhead, $1,575. Jobs 103 and 104 were...
As of the end of June, the job cost sheets at Racing Wheels, Inc., show the...
As of the end of June, the job cost sheets at Racing Wheels, Inc., show the following total costs accumulated on three custom jobs. Job 102 Job 103 Job 104 Direct materials $ 43,000 $ 73,000 $ 53,000 Direct labor 11,000 28,600 43,000 Overhead applied 4,400 11,440 17,200 Job 102 was started in production in May and the following costs were assigned to it in May: direct materials, $13,000; direct labor, $4,000; and overhead, $1,600. Jobs 103 and 104 were...
As of the end of June, the job cost sheets at Racing Wheels, Inc., show the...
As of the end of June, the job cost sheets at Racing Wheels, Inc., show the following total costs accumulated on three custom jobs. Job 102 Job 103 Job 104 Direct materials $ 21,000 $ 55,000 $ 59,000 Direct labor 12,000 29,700 44,000 Overhead applied 4,560 11,286 16,720 Job 102 was started in production in May, and the following costs were assigned to it in May: direct materials, $8,000; direct labor, $3,300; and overhead, $1,254. Jobs 103 and 104 were...
As of the end of June, the job cost sheets at Racing Wheels, Inc., show the...
As of the end of June, the job cost sheets at Racing Wheels, Inc., show the following total costs accumulated on three custom jobs. Job 102 Job 103 Job 104 Direct materials $ 41,000 $ 56,000 $ 48,000 Direct labor 15,000 28,500 45,000 Overhead applied 6,300 11,970 18,900 Job 102 was started in production in May, and the following costs were assigned to it in May: direct materials, $9,000; direct labor, $3,600; and overhead, $1,512. Jobs 103 and 104 were...
As of the end of June, the job cost sheets at Racing Wheels, Inc., show the...
As of the end of June, the job cost sheets at Racing Wheels, Inc., show the following total costs accumulated on three custom jobs. Job 102 Job 103 Job 104 Direct materials $ 41,000 $ 56,000 $ 48,000 Direct labor 15,000 28,500 45,000 Overhead applied 6,300 11,970 18,900 Job 102 was started in production in May, and the following costs were assigned to it in May: direct materials, $9,000; direct labor, $3,600; and overhead, $1,512. Jobs 103 and 104 were...
As of the end of June, the job cost sheets at Racing Wheels, Inc., show the...
As of the end of June, the job cost sheets at Racing Wheels, Inc., show the following total costs accumulated on three custom jobs. Job 102 Job 103 Job 104   Direct materials $ 27,000 $ 56,000   $ 51,000     Direct labor 17,000 26,700   46,000   Overhead 6,800 10,680   18,400 Job 102 was started in production in May and the following costs were assigned to it in May: direct materials, $12,000; direct labor, $3,200; and overhead, $1,280. Jobs 103 and 104 are started...
As of the end of June, the job cost sheets at Racing Wheels, Inc., show the...
As of the end of June, the job cost sheets at Racing Wheels, Inc., show the following total costs accumulated on three custom jobs. Job 102 Job 103 Job 104 Direct materials $ 17,000 $ 64,000 $ 57,000 Direct labor 13,000 29,500 45,000 Overhead 6,240 14,160 21,600 Job 102 was started in production in May and the following costs were assigned to it in May: direct materials, $10,000; direct labor, $3,100; and overhead, $1,488. Jobs 103 and 104 are started...
As of the end of June, the job cost sheets at Racing Wheels, Inc., show the...
As of the end of June, the job cost sheets at Racing Wheels, Inc., show the following total costs accumulated on three custom jobs. Job 102 Job 103 Job 104 Direct materials $ 44,000 $ 54,000 $ 53,000 Direct labor 16,000 30,000 41,000 Overhead applied 5,280 9,900 13,530 Job 102 was started in production in May, and the following costs were assigned to it in May: direct materials, $11,000; direct labor, $3,400; and overhead, $1,122. Jobs 103 and 104 were...
The cost of producing x units of a product is given by C(x)=700 + 90 x...
The cost of producing x units of a product is given by C(x)=700 + 90 x - 90 ln(x), where x>=1 Find the minimum average cost
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT