In: Accounting
Direct materials: | 10 pounds × $3 per pound |
Direct labor: | 2.5 hours × $8 per hour |
Variable manufacturing overhead: | 2.5 hours × $2 per hour |
The following activity occurred during the month of June: | |
Materials purchased: | 125,000 pounds at $2.60 per pound |
Materials used: | 110,000 pounds |
Units produced: | 10,000 units |
Direct labor: | 24,000 hours at $7.50 per hour |
Actual variable manufacturing overhead: | $51,000 |
|
||||||||||||||||||
|
||||||||||||||||||
|
||||||||||||||||||
|
Answer 1
b) $8,000 favorable.
Explanation :
Actual labour hours worked = 24,000 hours
Standard labour hours allowerd for 10,000 units = 2.5 hours * 10,000 units = 25,000 hours
Standard Rate = $8 per hour
Direct labor efficiency variance = (Actual labour hours worked - Standard labour hours allowerd) * Standard Rate
= (24,000 hours - 25,000 hours) * $8 per hour = $8,000 favorable. (ie option b)
Explnation : Since actual labour hours worked is less than Standard labour hours allowerd , the direct labor efficiency variance calculated above is Favorable
Answer 2
a.) $12,000 favorable
Explanation :
Standard Labour Rate = $8 per hour
Actual Labour Rate = $7.50 per hour
Actual labour hours worked = 24,000 hours
Direct labor rate variance = (Actual Labour Rate - Standard Labour Rate ) * Actual labour hours worked
= ($7.50 per hour - $8 per hour) * 24,000 hours = $12,000 favorable (ie option a)
Explanation : Since actual labour rate is less than standard labour rate , the direct labor rate variance calculated above is favorable.