Question

In: Accounting

“Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the...

“Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the Koopers job by $3,000. It seems we’re either too high to get the job or too low to make any money on half the jobs we bid.”

Teledex Company manufactures products to customers’ specifications and operates a job order costing system. Manufacturing overhead cost is applied to jobs on the basis of direct labor cost. The following estimates were made at the beginning of the year:

Department
Fabricating Machining Assembly Total Plant
  Direct labor $ 218,000      $ 109,000      $ 327,000      $ 654,000   
  Manufacturing overhead $ 381,500      $ 436,000      $ 98,100      $ 915,600   

    

Jobs require varying amounts of work in the three departments. The Koopers job, for example,
would have required manufacturing costs in the three departments as follows:

Department
Fabricating Machining Assembly Total Plant
  Direct materials $ 4,800     $ 500      $ 3,200      $ 8,500   
  Direct labor $ 6,400     $ 800      $ 8,000      $ 15,200   
  Manufacturing overhead ?      ?        ?      ?
The company uses a plantwide overhead rate to apply manufacturing overhead cost to jobs.

    

Required:
1. Assuming use of a plantwide overhead rate:
a.

Compute the rate for the current year.

        

b.

Determine the amount of manufacturing overhead cost that would have been applied to
the Koopers job.

        

2.

Suppose that instead of using a plantwide overhead rate, the company had used a separate predetermined overhead rate in each department. Under these conditions:

     

a. Compute the rate for each department for the current year.

        

b.

Determine the amount of manufacturing overhead cost that would have been applied to
the Koopers job.

        

4.

Assume that it is customary in the industry to bid jobs at 150% of total manufacturing cost (direct materials, direct labor, and applied overhead).

a.

What was the company's bid price on the Koopers job if a plantwide overhead rate had been used to apply overhead cost?

        

b.

What would the bid price have been if departmental overhead rates had been used to apply overhead cost?

        

    
5.

At the end of the year, the company assembled the following actual cost data relating to all jobs worked on during the year.

      

Department

  
Cutting Machining Assembly Total plant
  Direct materials $ 208,000    $ 17,800    $ 132,000    $ 357,800   
  Direct labor 228,000    126,000    280,000    634,000   
  Manufacturing overhead $ 393,000    $ 478,000    $ 86,700    $ 957,700   
a.

Compute the underapplied or overapplied overhead for the year, assuming that a plantwide overhead rate is used.

        

b.

Compute the underapplied or overapplied overhead for the year, assuming that departmental overhead rates are used. (Enter overapplied overhead costs as negative amounts and underapplied overhead costs as positive amounts.)

        

Solutions

Expert Solution

Solution:

Plant wide Overhead Rate

- Plant-wide overhead rate means predetermined overhead rate of plant as a whole.

- Overheads are the indirect manufacturing costs incurred on the making of product. These costs are not directly traceable with the production volume because it incurred for a period or in lum sum amount.

- Generally, the overhead costs are apply to the production department on predetermined basis.

- Predetermined Overhead Rate is the rate which is used to apply manufacturing overhead to products or job orders.

- Normally, it is calculated at the beginning of the period.

- It is calculated by dividing the estimated factory overhead cost by an allocation base (or suitable basis).

- Allocation bases may be direct labor hours, direct labor costs, machine hours etc..

Plant wide Predetermined Overhead Rate = Estimated Manufacturing Overhead Cost for Plant / Estimated Allocation Base for Plant

Part 1(a) – Plant wide overhead rate for current year

Allocation Base is Direct Labor Cost

Total Estimated Direct Labor Cost for Plant = $654,000

Total Estimated Manufacturing Overhead for Plant = $915,600

Plant wide Overhead Rate = Total Estimated Manufacturing Overhead for Plant $915,600 / Total Estimated Direct Labor Cost for Plant $654,000 x 100

= 140% of direct labor cost

Part 1(b) – Applied Manufacturing Overhead Cost to the Koopers Job

Koopers Job

Direct Labor Cost

Applied Manufacturing Overhead @ 140% of Direct labor cost

Fabricating Dept

$6,400

$8,960

Machining Dept.

$800

$1,120

Assembly Dept.

$8,000

$11,200

Total Applied Manufacturing Overhead

$21,280

Part 2(a) – Departmental Overhead Rate for Current Year

Fabricating Department

Total Manufacturing Overhead

$381,500

175%

of Direct labor cost

Total Direct Labor Cost

218,000

Machining Department

Total Manufacturing Overhead

$436,000

400%

of Direct labor cost

Total Direct Labor Cost

109,000

Assembly Dept.

Total Manufacturing Overhead

$98,100

30%

of Direct Labor cost

Total Direct Labor Cost

327000

Part 2(b) – Applied Manufacturing Overhead to the Koopers Job

Direct Labor Cost

Departmental Overhead Rate

Applied Manufacturing Overhead

Fabricating Dept

$6,400

175%

$11,200

Machining Dept.

$800

400%

$3,200

Assembly Dept.

$8,000

30%

$2,400

Total Applied Manufacturing Overhead

$16,800

Part 4(a) – Bid Price if plant wide overhead rate is applied

Koopers Job

Direct Materials

$8,500

Direct Labor

$15,200

Applied Manufacturing Overhead (Refer Part 1(b)

$21,280

Total Manufacturing Cost

$44,980

Bid Price (150% of total manufacturing Cost)

$67,470

(44,980*150%)

Bid Price of Job = $67,470

Part 4(b) – Bid Price if departmental overhead rate is applied

Koopers Job

Direct Materials

$8,500

Direct Labor

$15,200

Applied Manufacturing Overhead (Refer Part 2(b)

$16,800

Total Manufacturing Cost

$40,500

Bid Price (150% of total manufacturing Cost)

$60,750

(40,500*150%)

Bid Price of Job = $60,750

Hope the above calculations, working and explanations are clear to you and help you in understanding the concept of question.... please rate my answer...in case any doubt, post a comment and I will try to resolve the doubt ASAP…thank you

Pls ask separate question for remaining parts.


Related Solutions

“Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the...
“Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the Koopers job by $3,000. It seems we’re either too high to get the job or too low to make any money on half the jobs we bid.” Teledex Company manufactures products to customers’ specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to...
Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the...
Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the Koopers job by $3,000. It seems we’re either too high to get the job or too low to make any money on half the jobs we bid.” Teledex Company manufactures products to customers’ specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to...
“Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the...
“Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the Koopers job by $3,000. It seems we’re either too high to get the job or too low to make any money on half the jobs we bid.” Teledex Company manufactures products to customers’ specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to...
“Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the...
“Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the Koopers job by $3,000. It seems we’re either too high to get the job or too low to make any money on half the jobs we bid.” Teledex Company manufactures products to customers’ specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to...
“Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the...
“Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the Koopers job by $2,000. It seems we’re either too high to get the job or too low to make any money on half the jobs we bid.” Teledex Company manufactures products to customers’ specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to...
“Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the...
“Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the Koopers job by $3,000. It seems we’re either too high to get the job or too low to make any money on half the jobs we bid.” Teledex Company manufactures products to customers’ specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to...
“Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the...
“Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the Koopers job by $2,000. It seems we’re either too high to get the job or too low to make any money on half the jobs we bid.” Teledex Company manufactures products to customers’ specifications and operates a job order costing system. Manufacturing overhead cost is applied to jobs on the basis of direct labor cost. The following estimates were made at the beginning of...
“Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the...
“Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the Koopers job by $2,000. It seems we’re either too high to get the job or too low to make any money on half the jobs we bid.” Teledex Company manufactures products to customers’ specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to...
“Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the...
“Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the Koopers job by $2,000. It seems we’re either too high to get the job or too low to make any money on half the jobs we bid.” Teledex Company manufactures products to customers’ specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to...
“Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the...
“Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the Koopers job by $2,000. It seems we’re either too high to get the job or too low to make any money on half the jobs we bid.” Teledex Company manufactures products to customers’ specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT