In: Accounting
“Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the Koopers job by $3,000. It seems we’re either too high to get the job or too low to make any money on half the jobs we bid.” |
Teledex Company manufactures products to customers’ specifications and operates a job order costing system. Manufacturing overhead cost is applied to jobs on the basis of direct labor cost. The following estimates were made at the beginning of the year:
|
Solution:
Plant wide Overhead Rate
- Plant-wide overhead rate means predetermined overhead rate of plant as a whole.
- Overheads are the indirect manufacturing costs incurred on the making of product. These costs are not directly traceable with the production volume because it incurred for a period or in lum sum amount.
- Generally, the overhead costs are apply to the production department on predetermined basis.
- Predetermined Overhead Rate is the rate which is used to apply manufacturing overhead to products or job orders.
- Normally, it is calculated at the beginning of the period.
- It is calculated by dividing the estimated factory overhead cost by an allocation base (or suitable basis).
- Allocation bases may be direct labor hours, direct labor costs, machine hours etc..
Plant wide Predetermined Overhead Rate = Estimated Manufacturing Overhead Cost for Plant / Estimated Allocation Base for Plant
Part 1(a) – Plant wide overhead rate for current year
Allocation Base is Direct Labor Cost
Total Estimated Direct Labor Cost for Plant = $654,000
Total Estimated Manufacturing Overhead for Plant = $915,600
Plant wide Overhead Rate = Total Estimated Manufacturing Overhead for Plant $915,600 / Total Estimated Direct Labor Cost for Plant $654,000 x 100
= 140% of direct labor cost
Part 1(b) – Applied Manufacturing Overhead Cost to the Koopers Job
Koopers Job |
Direct Labor Cost |
Applied Manufacturing Overhead @ 140% of Direct labor cost |
Fabricating Dept |
$6,400 |
$8,960 |
Machining Dept. |
$800 |
$1,120 |
Assembly Dept. |
$8,000 |
$11,200 |
Total Applied Manufacturing Overhead |
$21,280 |
Part 2(a) – Departmental Overhead Rate for Current Year
Fabricating Department |
|||
Total Manufacturing Overhead |
$381,500 |
175% |
of Direct labor cost |
Total Direct Labor Cost |
218,000 |
||
Machining Department |
|||
Total Manufacturing Overhead |
$436,000 |
400% |
of Direct labor cost |
Total Direct Labor Cost |
109,000 |
||
Assembly Dept. |
|||
Total Manufacturing Overhead |
$98,100 |
30% |
of Direct Labor cost |
Total Direct Labor Cost |
327000 |
Part 2(b) – Applied Manufacturing Overhead to the Koopers Job
Direct Labor Cost |
Departmental Overhead Rate |
Applied Manufacturing Overhead |
|
Fabricating Dept |
$6,400 |
175% |
$11,200 |
Machining Dept. |
$800 |
400% |
$3,200 |
Assembly Dept. |
$8,000 |
30% |
$2,400 |
Total Applied Manufacturing Overhead |
$16,800 |
Part 4(a) – Bid Price if plant wide overhead rate is applied
Koopers Job |
|
Direct Materials |
$8,500 |
Direct Labor |
$15,200 |
Applied Manufacturing Overhead (Refer Part 1(b) |
$21,280 |
Total Manufacturing Cost |
$44,980 |
Bid Price (150% of total manufacturing Cost) |
$67,470 (44,980*150%) |
Bid Price of Job = $67,470
Part 4(b) – Bid Price if departmental overhead rate is applied
Koopers Job |
|
Direct Materials |
$8,500 |
Direct Labor |
$15,200 |
Applied Manufacturing Overhead (Refer Part 2(b) |
$16,800 |
Total Manufacturing Cost |
$40,500 |
Bid Price (150% of total manufacturing Cost) |
$60,750 (40,500*150%) |
Bid Price of Job = $60,750
Hope the above calculations, working and explanations are clear to you and help you in understanding the concept of question.... please rate my answer...in case any doubt, post a comment and I will try to resolve the doubt ASAP…thank you
Pls ask separate question for remaining parts.