Question

In: Accounting

Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the...

Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the Koopers job by $3,000. It seems we’re either too high to get the job or too low to make any money on half the jobs we bid.”

Teledex Company manufactures products to customers’ specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to jobs. The following estimates were made at the beginning of the year:

Department
Fabricating Machining Assembly Total Plant
Manufacturing overhead $ 381,500 $ 436,000 $ 98,100 $ 915,600
Direct labor $ 218,000 $ 109,000 $ 327,000 $ 654,000

Jobs require varying amounts of work in the three departments. The Koopers job, for example, would have required manufacturing costs in the three departments as follows:

Department
Fabricating Machining Assembly Total Plant
Direct materials $ 4,800 $ 500 $ 3,200 $ 8,500
Direct labor $ 6,400 $ 800 $ 8,000 $ 15,200
Manufacturing overhead ? ? ? ?

Required:

1. Using the company's plantwide approach:

a. Compute the plantwide predetermined rate for the current year.

b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job.

2. Suppose that instead of using a plantwide predetermined overhead rate, the company had used departmental predetermined overhead rates based on direct labor cost. Under these conditions:

a.Compute the predetermined overhead rate for each department for the current year.

b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job.

4. Assume that it is customary in the industry to bid jobs at 150% of total manufacturing cost (direct materials, direct labor, and applied overhead).

a.What was the company’s bid price on the Koopers job using a plantwide predetermined overhead rate?

b.What would the bid price have been if departmental predetermined overhead rates had been used to apply overhead cost?

Solutions

Expert Solution

1.

a. Plant-wide predetermined overhead rate = Estimated manufacturing overhead / Estimated direct labor cost

Plant-wide predetermined overhead rate = $915,600 / $654,000 = 140%

b. Manufacturing overhead cost applied to Koopers Job = $15,200*140% = $21,280

2.

a. Departmental predetermined overhead rate:

Fabricating = $381,500/$218,000 = 175%

Machining = $436,000/$109,000 = 400%

Assembly = $98,100/$327,000 = 30%

b.

Applied manufacturing overhead
Fabricating ($6,400*175%) $11,200
Machining ($800*400%) 3,200
Assembly ($8,000*30%) 2,400
Total applied manufacturing overhead $16,800

4.

a.

Koopers Job
Direct material $8,500
Direct labor 15,200
Applied manufacturing overhead ($15,200*140%) 21,280
Total manufacturing cost $44,980
Bid price ($44,980*150%) $67,470

b.

Koopers Job
Direct material $8,500
Direct labor 15,200
Applied manufacturing overhead 16,800
Total manufacturing cost $40,500
Bid price ($40,500*150%) $60,750

Related Solutions

“Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the...
“Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the Koopers job by $3,000. It seems we’re either too high to get the job or too low to make any money on half the jobs we bid.” Teledex Company manufactures products to customers’ specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to...
“Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the...
“Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the Koopers job by $3,000. It seems we’re either too high to get the job or too low to make any money on half the jobs we bid.” Teledex Company manufactures products to customers’ specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to...
“Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the...
“Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the Koopers job by $3,000. It seems we’re either too high to get the job or too low to make any money on half the jobs we bid.” Teledex Company manufactures products to customers’ specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to...
“Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the...
“Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the Koopers job by $2,000. It seems we’re either too high to get the job or too low to make any money on half the jobs we bid.” Teledex Company manufactures products to customers’ specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to...
“Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the...
“Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the Koopers job by $3,000. It seems we’re either too high to get the job or too low to make any money on half the jobs we bid.” Teledex Company manufactures products to customers’ specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to...
“Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the...
“Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the Koopers job by $2,000. It seems we’re either too high to get the job or too low to make any money on half the jobs we bid.” Teledex Company manufactures products to customers’ specifications and operates a job order costing system. Manufacturing overhead cost is applied to jobs on the basis of direct labor cost. The following estimates were made at the beginning of...
“Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the...
“Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the Koopers job by $2,000. It seems we’re either too high to get the job or too low to make any money on half the jobs we bid.” Teledex Company manufactures products to customers’ specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to...
“Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the...
“Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the Koopers job by $2,000. It seems we’re either too high to get the job or too low to make any money on half the jobs we bid.” Teledex Company manufactures products to customers’ specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to...
“Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the...
“Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the Koopers job by $2,000. It seems we’re either too high to get the job or too low to make any money on half the jobs we bid.” Teledex Company manufactures products to customers’ specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to...
“Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the...
“Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the Koopers job by $3,000. It seems we’re either too high to get the job or too low to make any money on half the jobs we bid.” Teledex Company manufactures products to customers’ specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT