In: Finance
(b) Company X is currently making its capital budgeting
decisions for the upcoming
year. Among the projects they are considering, are two equipment:
Equipment A
and equipment AA. Equipment A costs $50,000 but will produce
expected
after-tax cash inflows of $30,000 at the end of each of the next 2
years.
Equipment AA also costs $50,000 but will produce expected after tax
cash
inflows of $16,500 at the end of each of the next 4 years. Both
projects have a
12% cost of capital.Assume that these are Mutual excusive projects.
Using NPV,
Which project or projects should the company accept? [5]
(c) year CFX
0 (50,000)
1 20,850
2 20,850
3 20,850
4 20,850
It is now determined that the cost of capital for both projects is
14%.
Using IRR, should the Project be selected? [6]
(d) What are two (2) disadvantages of the Payback Period?
b
EquiPment A | |||
Discount rate | 12.000% | ||
Year | 0 | 1 | 2 |
Cash flow stream | -50000 | 30000 | 30000 |
Discounting factor | 1.000 | 1.120 | 1.254 |
Discounted cash flows project | -50000.000 | 26785.714 | 23915.816 |
NPV = Sum of discounted cash flows | |||
NPV Equitment A = | 701.53 | ||
Where | |||
Discounting factor = | (1 + discount rate)^(Corresponding period in years) | ||
Discounted Cashflow= | Cash flow stream/discounting factor |
Equipment AA | |||||
Discount rate | 12.000% | ||||
Year | 0 | 1 | 2 | 3 | 4 |
Cash flow stream | -50000 | 16500 | 16500 | 16500 | 16500 |
Discounting factor | 1.000 | 1.120 | 1.254 | 1.405 | 1.574 |
Discounted cash flows project | -50000.000 | 14732.143 | 13153.699 | 11744.374 | 10486.048 |
NPV = Sum of discounted cash flows | |||||
NPV Equipment AA = | 116.26 | ||||
Where | |||||
Discounting factor = | (1 + discount rate)^(Corresponding period in years) | ||||
Discounted Cashflow= | Cash flow stream/discounting factor |
Accept equipment A as it has higher NPV
c
Project | |||||
IRR is the rate at which NPV =0 | |||||
IRR | 24.14% | ||||
Year | 0 | 1 | 2 | 3 | 4 |
Cash flow stream | -50000.000 | 20850.000 | 20850.000 | 20850.000 | 20850.000 |
Discounting factor | 1.000 | 1.241 | 1.541 | 1.913 | 2.375 |
Discounted cash flows project | -50000.000 | 16795.107 | 13528.807 | 10897.735 | 8778.351 |
NPV = Sum of discounted cash flows | |||||
NPV Project = | 0.000 | ||||
Where | |||||
Discounting factor = | (1 + discount rate)^(Corresponding period in years) | ||||
Discounted Cashflow= | Cash flow stream/discounting factor |
Accept project as IRR is more than cost of capital of 14%
d
Doesnot take account of time value of money
Does not take account of cash flows after the payback period