In: Accounting
The Windam Restaurant Group manufactures the bags of frozen French fries used at its franchised restaurants. Last? week, Windam purchased and used 98,000 pounds of potatoes at a price of $0.85 per pound. During the? week, 2,100 direct labor hours were incurred in the plant at a rate of $12.45 per hour. The standard price per pound of potatoes is $1.00?, and the standard direct labor rate is $12.15 per hour. Standards indicate that for the number of bags of frozen fries? produced, the factory should have used 95,000 pounds of potatoes and 2,000 hours of direct labor.
1. |
Determine the direct material price and quantity variances. Be sure to label each variance as favorable or unfavorable. |
2. |
Think of a plausible explanation for the variances found in Requirement 1. |
3. |
Determine the direct labor rate and efficiency variances. Be sure to label each variance as favorable or unfavorable. |
4. |
Could the explanation for the labor variances be tied to the material? variances? Explain. |
1. Material price variance = (Standard rate - actual rate )× actual quantity used
= ($1 - $0.85) × 98000
= $ 14700 Favourable
Material quantity variance = ( Standard Qty - actual qty used ) × standard rate per unit
= ( 95000 - 98000 ) × $1
= $3000 unfavourable
Total material cost variance = (95000× 1) - (98000×0.85)
= $ 11700 favourable
2. The plausible reasons might be as follows :
~ Since the actual rate per unit of potatoes was less than the standard set, it resulted in a favourable variance of $14700.
~ But the quantity used was more than the set standard quantity allotted. Therefore the quantity variance was unfavourable by $3000
~ Thus, an overall favourable profit to the organisation was $11400 as reflected by the total material cost variance.
3. Direct labor rate variance = ( Std. Rate - actual rate) × actual hrs worked
= ($12.15 - $12.45) × 2100 hrs
= $ 630 Unfavourable
Labor efficiency variance = (Std. Hrs - Actual hrs )× std rate per hour
= (2000 - 2100) × $12.15
= $1215 unfavourable
So, total labour cost variance = (2000×12.15) - (2100×12.45)
= $1845 unfavourable
4 . The plausible reasons for the same are as follows:
~ Since both the actual hours taken to complete the work and the rate per hour were more than the set standarts, therefore it resulted in an overall unfavourable variance .