Question

In: Accounting

Petral Ltd. Manufactures 2 products, W and Z using the same factory and facilities. Details provided...

Petral Ltd. Manufactures 2 products, W and Z using the same factory and facilities. Details provided below:

Product Line Vol of Production Material (direct) cost per unit Direct labour per unit Machine time per unit Labour cost per unit
W 600 $6 0.75hr 0.5hr $4
Z 7100 $18 1.25hrs 1.75hrs $10

Production overhead is comprised of the following costs:

Description of cost Amount

Factory overhead related to machine activity- $42,725

Set-up costs- $8,725

Cost of handling materials- $11,725

Administration costs for spare parts- $12,725

The firm uses a plant-wide overhead rate based on Machine hours of $5.97 per machine hour.

However, an investigation of the activities (in addition to machine hours) that drive costs at the product-line level revealed the following relationships:

Product line # of set ups # of times material was handled # of spare parts
W 2 3 3
Z 9 13 5

Required:

1) Verify the firm's plant-wide rate of $5.97 per machine hour. Show all relevant calculations.

2) Compute all appropriate overhead rates using activity based costing. Round off all individual overhead rates to two decimal places. Show all relevant calculations.

3) Apply (1) and (2) to 2 product lines: that is, calculate the amount of overhead that should be allocated to Product-lines W and Z under the plant-wide rate and ABC rates. Show all relevant calculations.

4) Compare the overhead allocations to product lines W and Z. Clearly explain the differences in allocated costs with respect to each product line: your explanation should first provide a theoretical explanation for the differences, and second, explain these differences by referring back to the case facts provided. This part requires a narration that explains any figures calculated to highlight differences in allocated amounts: students cannot just provide calculations without providing a detailed explanation. Please ensure that the answer is written in full sentences and using paragraphs. An answer with key words only, which are not developed into a reasoned argument, is not acceptable for second-year assignments.

Solutions

Expert Solution

Answer 1

Plantwide rate = Total Overheads/ Total Machine Hours

Total Overheads= 42725+8725+11725+12725= 75,900

Total Machine Hours = 600*.5+ 7100*1.75= 12,725

Plantwide rate per machine hr = 75,900/12,725= 5.964 per machine hr.So it is verified

2. Overhead Rates using Activity based costing

Set up rate= Set up Cost/No of set ups = 8,725/11 = 793.18 per set up

Material Handling rate= cost of handling material/ no of times materail handled= 11,725/16=732.81 each time

Spare part handling= cost/ no of spare parts=12,725/8 =1590.6 per part

Machine rate= Machine overheads/machine hrs= 42,725/12,725= 3.36 per hr

3. Overhead Cost calculations for product W and Z using Activity based costing

Cost for each product line = cost Material Handling + admn cost for spares + overheads for machine activity

Overhead cost per unit cost= Total cost as per above/ volume of production

W=( 2*793.18+3*732.81+3*1590.6+600*.5*3.36)/600

= $13542.59/600= $15.97 per unit

Z = ( 9*793.18+13*732.81+5*1590.6+7100*1.75*3.36)/7100

= $66366.15/7100= $9.34 per unit

4.Comparing costs calculated in part 1 based on machine hrs and and under Activity based costing is different. In both these cases costs under ABC is more. It means that product line is under costed based on machine hrs . It is better to use ABC costing to have more effective costs as compared to traditional method of costing.


Related Solutions

) Kofi Brokeman Ltd manufactures four products using the same machinery. The following details relate to...
) Kofi Brokeman Ltd manufactures four products using the same machinery. The following details relate to its cost and sales per unit of each product: Fandango FanChoco Fanice Choco Malt GHȼ GHȼ GHȼ GHȼ Selling price 28 30 45 42 Direct material 5 6 8 6 Direct labour 4 4 8 8 Variable overhead 3 3 6 6 Fixed overhead* 8 8 16 16 Profit 8 9 7 6 Labour hours 0.25 0.25 0.50 0.50 Machine hours 4 3 4...
Sunshine Co. Ltd. is a manufacturing company. It manufactures 2 products, known as ‘A’ and ‘Z’....
Sunshine Co. Ltd. is a manufacturing company. It manufactures 2 products, known as ‘A’ and ‘Z’. The following information is given for the year 2017: - The standard direct materials and direct labour used for each product is as follows: ‘A’ ‘Z’ Material 1 10 units 8 units Material 2 5 units 9 units Direct Labour 10 hours 15 hours Standard direct materials and direct labour costs: ($) Material 1 8.20 per unit Material 2 17.00 per unit Direct Labour...
Firm Z manufactures 3 products using the same machine. At the weekly market demand for the...
Firm Z manufactures 3 products using the same machine. At the weekly market demand for the product (see below), the firm is limited in terms of machine capacity - 450 hours per week. Product Machine hours required per unit of product Maximum demand in units Contribution margin per unit A 3 hours machinery hours, maximum demand in units 100, Contribution margin £9 B 2 hours machinery hours, maximum demand in units 100, contribution margin £7 C 1 hour machinery hours,...
a) Kofi Brokeman Ltd manufactures four products using the same machinery. The following details relate to its cost and sales per unit of each product:
a) Kofi Brokeman Ltd manufactures four products using the same machinery. The following details relate to its cost and sales per unit of each product:                                                                    Fandango       FanChoco      Fanice     Choco Malt                                                                       GHȼ                GHȼ               GHȼ         GHȼ   Selling price                                                  28                   30                  45                42 Direct material                                               5                     6                    8                   6 Direct labour                                                  4                     4                    8                   8 Variable overhead                                          3                     3                    6                   6 Fixed overhead*                                             8                     8                   16                 16 Profit                                                               8                     9                    7                   6 Labour hours                                                 0.25                 0.25              0.50             0.50 Machine hours                                                 4                     3                   4                   ...
PDR Co. manufactures 4 products using the same machinery. The following details relate to its 4...
PDR Co. manufactures 4 products using the same machinery. The following details relate to its 4 products. Product A Product B Product C Product D $ per unit $ per unit $ per unit $ per unit Selling price 28 30 45 42 Direct material 5 6 8 6 Direct labor 4 4 8 8 Variable overhead 3 3 6 6 Fixed overhead * 8 8 16 16 Profit 8 9 7 6 Labour hrs.per unit 1 1 2 2...
Halbert plc manufactures and sells three products that use the same production facilities. In the plan...
Halbert plc manufactures and sells three products that use the same production facilities. In the plan for 2011, the details of each product were:- Product                                                                      K                     L                      M                                                                                     £                     £                     £ Selling price per unit                                               70                    45                    30 Variable costs per unit                                            35                    25                    12 Apportioned fixed costs per unit                            20                    10                   10 Profit per unit                                                            15                    10                     8 Estimated sales – units                                   15 000           20 000           20 000 Estimated...
DFH plc manufactures and sells three products that use the same production facilities. The annual budget...
DFH plc manufactures and sells three products that use the same production facilities. The annual budget has just been prepared and the projected sales, selling prices, manufacturing costs and expenses resulted in the following projections of the profit that would be generated in 2014. Product D Product F Product H TOTAL Sales – units 1000 1500 2000 £ £ £ £ Sales 60 000 150 000 80 000 290 000 Variable costs of production 24 000 72 000 38 000...
There are two companies, A and B, which have facilities to produce the same products. A's...
There are two companies, A and B, which have facilities to produce the same products. A's operating income is 15% and B's operating income is 25%. In general, company B can be considered a profitable company with higher internal efficiency. But if actual B is not better at internal competencies, explain how the above operating profit could have been achieved. (Hint: B may have been using the equipment for a longer period of time.)
A company manufactures four products using the same plant and processes. The following information relates to...
A company manufactures four products using the same plant and processes. The following information relates to a production period: - Product Volume Material costs per unit Direct labour time per unit Machine time per unit Labour cost per unit A 1,100 £7 30 minutes 15 minutes £5 B 2,000 £7 30 minutes 15 minutes £5 C 1,500 £16 120 minutes 60 minutes £9 D 3,950 £19 90 minutes 90 minutes £9 Total production overhead recorded by the cost accounting system...
A company manufactures three products using the same production process. The costs incurred up to the...
A company manufactures three products using the same production process. The costs incurred up to the slit-off point are $200,000. These costs are allocated to the products on the basis of their sales value at the slit-off point. The number of units produced, the selling prices per unit of the three products at the split-off point and after further processing, and the additional processing costs are as follows: Product Number of Units Produced Selling Price at Split-Off Selling price after...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT