In: Accounting
Becton Labs, Inc., produces various chemical compounds for industrial use. One compound, called Fludex, is prepared using an elaborate distilling process. The company has developed standard costs for one unit of Fludex, as follows: |
Standard Quantity |
Standard Price or Rate |
Standard Cost | ||||
Direct materials | 2.60 ounces | $ | 20.00 | per ounce | $ | 52.00 |
Direct labor | 0.60 hours | $ | 16.00 | per hour | 9.60 | |
Variable manufacturing overhead | 0.60 hours | $ | 4.50 | per hour | 2.70 | |
$ | 64.30 | |||||
During November, the following activity was recorded relative to production of Fludex: |
a. | Materials purchased, 13,000 ounces at a cost of $244,400. |
b. |
There was no beginning inventory of materials; however, at the end of the month, 3,300 ounces of material remained in ending inventory. |
c. |
The company employs 20 lab technicians to work on the production of Fludex. During November, they worked an average of 150 hours at an average rate of $14.00 per hour. |
d. |
Variable manufacturing overhead is assigned to Fludex on the basis of direct labor-hours. Variable manufacturing overhead costs during November totaled $6,500. |
e. |
During November, 3,600 good units of Fludex were produced . |
1. | For direct labor: |
a. |
Compute the rate and efficiency variances. (Input all amounts as positive values. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e, zero variance).) |
b. |
In the past, the 20 technicians employed in the production of Fludex consisted of 4 senior technicians and 16 assistants. During November, the company experimented with fewer senior technicians and more assistants in order to save costs. Would you recommend that the new labor mix be continued? |
|
2. |
Compute the variable overhead rate and efficiency variances. (Input all amounts as positive values. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e, zero variance).) |
1a)
Labor Rate/Price Variance
Labor Price Variance – It arises due to difference in actual rate paid from standard rate. It is calculated as below:
Labor Price Variance = Actual Time (Standard Rate per hour – Actual Rate per hour)
Here, actual time means time for which wage has been paid.
Direct Labor Rate/Price Variance |
||
Actual Hourly Rate |
$14.00 |
Per Hour |
Standard Hourly Rate |
$16.00 |
Per Hour |
Variance or Difference in Rate |
$2.00 |
Per Hour |
x Actual Labor Hours worked (20*150) |
3000 |
Hours |
Labor Rate Variance |
$6,000 |
Favorable |
Labor Quantity/Efficiency Variance
Labor Efficiency Variance – It arises due to variation in the working hours from the set standard.
Labor Quantity / Efficiency Variance |
||
Standard Hours Allowed for actual production: |
||
Actual Production |
3600 |
Units |
x Allowed Standard Hours Per Unit |
0.60 |
hours |
Total Standard Hours Allowed for actual production (SHAP) |
2,160 |
hours |
Actual Labor Hours Worked |
3,000 |
hours |
Variance or Difference in Hours |
840 |
hours |
x Standard Hourly Rate (SHR) |
$16.00 |
per hour |
Labor Efficiency Variance |
$13,440 |
Unfavorable |
Part 1(b) –
Total Labor Cost Variance |
||
Direct Labor Rate Variance (Refer above) |
$6,000 |
Favorable |
Direct Labor Efficiency Variance (Refer above) |
$13,440 |
Unfavorable |
Total Labor Cost Variance |
$7,440 |
Unfavorable |
The new labor mix would NOT BE RECOMMENDED.
The total labor cost variance is unfavorable. Hence the new labor mix would not be recommended since new labor mix will increase the labor cost.
Part 2 –
Variable Overhead Rate/Spending/Cost Variance |
||
Actual Hourly Variable Overhead Rate ($6,500 / 150*20) |
2.1667 |
Per Hour |
Standard Hourly Variable Overhead Rate |
4.50 |
Per Hour |
Variance or Difference in Rate |
2.33 |
Per Hour |
x Actual Hours Worked |
3000 |
Hours |
Variable Overhead Rate/Spending Variance |
$7,000 |
Favorable |
Variable Overhead Efficiency/Quantity Variance |
||
Standard Hours Allowed for actual production: |
||
Actual Production |
3,600 |
Square foot |
x Allowed Standard Hours Per Unit |
0.6 |
Hours |
Total Standard Hours Allowed for actual production (SHAP) |
2160 |
Hours |
Actual Hours Worked (AH) |
3000 |
Hours |
Variance or Difference in Hours |
840 |
hours |
x Standard Hourly Variable Overhead Rate |
$4.50 |
per hour |
Variable Overhead Efficiency Variance |
$3,780 |
Unfavorable |
Hope the above calculations, working and explanations are clear to you and help you in understanding the concept of question.... please rate my answer...in case any doubt, post a comment and I will try to resolve the doubt ASAP…thank you