Question

In: Accounting

ABC has estimated their overhead for the period will be $500,000. They use machine hours as...

ABC has estimated their overhead for the period will be $500,000. They use machine hours as an allocation base for each job and they estimate they will use 40,000 machine hours this year. What is their predetermined overhead rate for the year?

Question 1 options:

$12.50 per machine hour.

cannot be determined.

$2,000,000

$0.08 per machine hour.

Question 2 (1 point)

Assume ABC has a predetermined overhead rate of $15 per machine hour. Job #103 has used 100 direct labor hours and 50 machine hours. It's direct material costs are $1,600 and the cost of direct labor is $20 per hour. What is the total labor cost of Job #103?

Question 2 options:

$750

$4,350

$2,000

$3,600

Question 3 (1 point)

Assume ABC has a predetermined overhead rate of $15 per machine hour. Job #103 has used 100 direct labor hours and 50 machine hours. It's direct material costs are $1,600 and the cost of direct labor is $20 per hour. What is the total cost of Job #103?

Question 3 options:

$2,000

$3,600

$750

$4,350

Question 4 (1 point)

ABC had estimated $500,000 in overhead costs. At the end of the year, its actual overhead was $486,000. Its predetermined overhead rate was $15 per machine hour and it used 32,000 machine hours. What is the amount of Applied Overhead for the year?

Question 4 options:

$486,000

$480,000

$14,000

$500,000

Question 5 (1 point)

ABC had estimated $500,000 in overhead costs. At the end of the year, its actual overhead was $486,000. Its predetermined overhead rate was $15 per machine hour and it used 32,000 machine hours. What is the amount of Over-/Under- Applied Overhead for the year?

Question 5 options:

$6,000 Under applied

$14,000 Under applied

$20,000 Under applied

$14,000 Over applied

Solutions

Expert Solution

Question 1 :

Estimated overhead $500000
Machine hours 40000 hrs
Pre-determined OH rate $12.5 per machine hour

so option $12.5 per machine hour is correct.

Question 2 :

Pre-determined overhead rate (given)-$15 per machine hour.

Job #103 used 100 direct labour hours and 50 machine hours

Direct labour cost-$20 per hour

so Direct labour cost- ($20*100)=$2000. As the overhead does not specify the indirect labour. total labour cost will be $2000.

So $2000 is the correct answer.

Question 3 :

Total cost of the job #103 will be (direct material+ direct labour + overhead cost)

= ($1600+$2000+ overhead cost-($15*50))= $4350

So $4350 is the correct option.

Question 4 :

Estimated OH cost- $500000

Actual OH-$486000

Pre-determined OH rate- $15 per machine hr

ABC used 32000 machine hours. So Applied OH was ($15*32000)=$480000.

So $480000 is the correct option.

Question 5 :

Estimated OH cost- $500000

Actual OH-$486000

Applied Overhead was $480000

Applied OH was less than actual OH Hence it is under applied to the tune of ($486000-$480000)=$6000

So $6000 is the correct option.


Related Solutions

III. Manufacturing Overhead Costs estimated $       500,000 Direct Labor Hours estimated             50,000 Machine Hours estimated...
III. Manufacturing Overhead Costs estimated $       500,000 Direct Labor Hours estimated             50,000 Machine Hours estimated           250,000 Direct Labor Costs estimated $    1,000,000 Determine the Pre-determined Overhead rate based on the following: a Direct Labor Hours b Machine Hours c Direct Labor Cost
Estimated manufacturing overhead $ 500,000 Actual manufacturing overhead $ 550,000 Estimated direct labor hours 10,000 hours...
Estimated manufacturing overhead $ 500,000 Actual manufacturing overhead $ 550,000 Estimated direct labor hours 10,000 hours Actual direct labor hours 10,500 13. Calculate the predetermined overhead allocation rate using direct labor hours as the allocation base. 14. Determine the amount of overhead allocated during the year. Record the journal entry. 15. Determine the amount of underallocated or overallocated overhead. Record the journal entry to adjust Manufacturing Overhead.
Estimated variable manufacturing overhead $25 per machine hour Estimated fixed manufacturing overhead $67,100 Estimated machine-hours 6,100...
Estimated variable manufacturing overhead $25 per machine hour Estimated fixed manufacturing overhead $67,100 Estimated machine-hours 6,100 Actual manufacturing overhead $231,500 Actual machine-hours 6,250 The estimates of the manufacturing overhead and of machine-hours were made at the beginning of the year for the purpose of computing the company's predetermined overhead rate for the year. The applied manufacturing overhead for the year is:
ABC had an estimated factory overhead of $600,000 and an estimated direct labor hours of 100,000.
ABC had an estimated factory overhead of $600,000 and an estimated direct labor hours of 100,000. The company applies factory overhead, using direct labor hours as the cost driver.During the period, the company incurred $60,000 direct labor cost at a rate of $5 per hour.The actual factory overhead incurred is $80,000.Required:What is the predetermined overhead rate?What is the over- or under-applied factory overhead.Assuming that $50,000, $100,000, and $200,000 were balances found in Cost of Goods sold, Work-in-process, and finished goods,...
Budgeted overhead cost $1,050,000 Estimated machine hours 50,000 Estimated direct labor hours 10,000 Estimated direct materials...
Budgeted overhead cost $1,050,000 Estimated machine hours 50,000 Estimated direct labor hours 10,000 Estimated direct materials cost $1,500,000 Maverick’s inventory count, completed on December 31, 2016, revealed the following ending inventory balances: Raw Materials Inventory $250,000 Work in Process Inventory $626,000 Finished Goods Inventory $340,000 The company’s 2017 payroll data revealed the following actual payroll costs for the year: Job Title Number Employed Wage Rate per Hour Annual Salary per Employee Total Hours Worked per Employee President and CEO 1...
ABC is a job-order costing manufacturer that uses a plantwide overhead rate based on machine hours....
ABC is a job-order costing manufacturer that uses a plantwide overhead rate based on machine hours. Estimations for the year include $2,000,000 in overhead and 1,000,000 machine hours. ABC produced four products in March. Data are as follows: Product89 Product90 Product91 Product92 Balance, 3/1 $70,000     $20,000       $         0 $         0 Direct materials $30,000 $80,000 $100,000 15,000 Direct labor cost $25,000 $ 40,000 $60,000 $10,000 Actual machine hours – for month   1,000   2,000 3,000   500 By March 31, Jobs 89,...
1. Assume (1) actual machine-hours worked during the period of 54,000 hours, (2) manufacturing overhead applied...
1. Assume (1) actual machine-hours worked during the period of 54,000 hours, (2) manufacturing overhead applied to production during the period of $432,000, (3) estimated fixed manufacturing overhead of $331,800, and (4) estimated variable manufacturing overhead cost per machine-hour of $2.00. The estimated amount of the allocation base (machine-hours) is closest to: 2.Assume (1) actual machine-hours worked during the period of 54,000 hours, (2) estimated machine-hours to be worked during the coming period of 55,000 hours, (3) manufacturing overhead applied...
Data 4 Allocation base Machine-hours 5 Estimated manufacturing overhead cost $448,000 6 Estimated total amount of...
Data 4 Allocation base Machine-hours 5 Estimated manufacturing overhead cost $448,000 6 Estimated total amount of the allocation base 70,000 machine-hours 7 Actual manufacturing overhead cost $436,600 8 Actual total amount of the allocation base 77,000 Machine hours a) What is the predetermined overhead rate? (Round your answer to 2 decimal places.)        (b) By how much is the manufacturing overhead underapplied or overapplied? Either print or make a copy of your worksheet in your workbook before proceeding. You will...
Martinez Corporation applies overhead based upon machine-hours. Budgeted factory overhead was $362,000 and budgeted machine-hours were...
Martinez Corporation applies overhead based upon machine-hours. Budgeted factory overhead was $362,000 and budgeted machine-hours were 24,000. Actual factory overhead was $393,000 and actual machine-hours were 27,000. Before disposition of under/overapplied overhead, the cost of goods sold was $610,000 and ending inventories were as follows:             Direct materials                    $ 80,000             WIP                                        200,000             Finished goods                       270,000                   Total                               $550,000 Required: a.   Determine the budgeted factory overhead rate per machine-hour. b.   Compute the over/underapplied overhead. c.   Prepare the journal entry to dispose of the variance using the write-off to cost of...
Schulz Corporation applies overhead based upon machine-hours. Budgeted factory overhead was $266,400 and budgeted machine-hours were...
Schulz Corporation applies overhead based upon machine-hours. Budgeted factory overhead was $266,400 and budgeted machine-hours were 18,500. Actual factory overhead was $287,920 and actual machine-hours were 19,050. Before disposition of under/overapplied overhead, the cost of goods sold was $560,000 and ending inventories were as follows: Direct Materials: $60,000 WIP: 190,000 Finished Goods: 250,000 Total: $500,000 1) Determine the budgeted factor overhead rate per machine-hour. 2) Compute the over/underapplied overhead. 3) Select the journal entry to dispose of the variance using...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT