You have been appointed project manager for a company critical project. After a detailed WBS analysis...

You have been appointed project manager for a company critical project. After a detailed WBS analysis you have identified 15 key activities that make up the project. The following table details for each activity its duration and its preceding activities.

Activity

Preceding

Activity

Duration

Days

A

-

8

B

-

6

C

A

5

D

A

9

E

B

5

F

B

12

G

D,E

4

H

C

5

I

H

12

J

G,F

7

K

J

10

L

J

6

M

G,F

5

N

M

7

O

I,K

3

Senior Management has asked you to produce a comprehensive project plan. As part of this plan complete a CPM (critical path method) analysis of the above project. In your analysis produce a network diagram, define and identify the critical activities. In addition, calculate: Earliest Start, Latest Start, Earliest Finish, and Latest Finish, and slack for each activity.

Why are slack times important information for the project manager?

Solutions

Expert Solution

PLEASE LIKE THIS ANSWER, IT HELPS ME A LOT. THANK YOU!!!

Critical path, Total float, Free float, Independent float

A - 8
B - 6
C A 5
D A 9
E B 5
F B 12
G D,E 4
H C 5
I H 12
J G,H 7
K J 10
L J 6
M G,F 5
N M 7
O I,K 3

Solution:

Activity Immediate Predecessors Duration
A - 8
B - 6
C A 5
D A 9
E B 5
F B 12
G D,E 4
H C 5
I H 12
J G,H 7
K J 10
L J 6
M G,F 5
N M 7
O I,K 3

Edge and it's preceded and succeeded node

Edge Node1 → Node2
A 1→2
B 1→3
C 2→4
D 2→5
E 3→5
F 3→6
H 4→8
G 5→7
M 6→11
d 7→6
J 7→9
d 8→7
I 8→10
K 9→10
L 9→12
O 10→12
N 11→12

The network diagram for the project, along with activity time, is

Forward Pass Method
E1=0

E2=E1+t1,2 [t1,2=A=8]=0+8=8

E3=E1+t1,3 [t1,3=B=6]=0+6=6

E4=E2+t2,4 [t2,4=C=5]=8+5=13

E5=Max{Ei+ti,5}[i=2,3]

=Max{E2+t2,5;E3+t3,5}

=Max{8+9;6+5}

=Max{17;11}

=17

E6=Max{Ei+ti,6}[i=3,7]

=Max{E3+t3,6;E7+t7,6}

=Max{6+12;21+0}

=Max{18;21}

=21

E7=Max{Ei+ti,7}[i=5,8]

=Max{E5+t5,7;E8+t8,7}

=Max{17+4;18+0}

=Max{21;18}

=21

E8=E4+t4,8 [t4,8=H=5]=13+5=18

E9=E7+t7,9 [t7,9=J=7]=21+7=28

E10=Max{Ei+ti,10}[i=8,9]

=Max{E8+t8,10;E9+t9,10}

=Max{18+12;28+10}

=Max{30;38}

=38

E11=E6+t6,11 [t6,11=M=5]=21+5=26

E12=Max{Ei+ti,12}[i=9,10,11]

=Max{E9+t9,12;E10+t10,12;E11+t11,12}

=Max{28+6;38+3;26+7}

=Max{34;41;33}

=41


Backward Pass Method
L12=E12=41

L11=L12-t11,12 [t11,12=N=7]=41-7=34

L10=L12-t10,12 [t10,12=O=3]=41-3=38

L9=Min{Lj-t9,j}[j=12,10]

=Min{L12-t9,12;L10-t9,10}

=Min{41-6;38-10}

=Min{35;28}

=28

L8=Min{Lj-t8,j}[j=10,7]

=Min{L10-t8,10;L7-t8,7}

=Min{38-12;21-0}

=Min{26;21}

=21

L7=Min{Lj-t7,j}[j=9,6]

=Min{L9-t7,9;L6-t7,6}

=Min{28-7;29-0}

=Min{21;29}

=21

L6=L11-t6,11 [t6,11=M=5]=34-5=29

L5=L7-t5,7 [t5,7=G=4]=21-4=17

L4=L8-t4,8 [t4,8=H=5]=21-5=16

L3=Min{Lj-t3,j}[j=6,5]

=Min{L6-t3,6;L5-t3,5}

=Min{29-12;17-5}

=Min{17;12}

=12

L2=Min{Lj-t2,j}[j=5,4]

=Min{L5-t2,5;L4-t2,4}

=Min{17-9;16-5}

=Min{8;11}

=8

L1=Min{Lj-t1,j}[j=3,2]

=Min{L3-t1,3;L2-t1,2}

=Min{12-6;8-8}

=Min{6;0}

=0

(b) The critical path in the network diagram has been shown. This has been done by double lines by joining all those events where E-values and L-values are equal.
The critical path of the project is : 1-2-5-7-9-10-12 and critical activities are A,D,G,J,K,O

The total project time is 41
The network diagram for the project, along with E-values and L-values, is

For each non-critical activity, the total float, free float and independent float calculations are shown in Table


Activity
(i,j)
(1)

Duration
(tij)
(2)
Earliest time
Start
(Ei)
(3)


(Ej)
(4)


(Li)
(5)
Latest time
Finish
(Lj)
(6)
Earliest time
Finish
(Ei+tij)
(7)=(3)+(2)
Latest time
Start
(Lj-tij)
(8)=(6)-(2)

Total Float
(Lj-tij)-Ei
(9)=(8)-(3)

Free Float
(Ej-Ei)-tij
(10)=((4)-(3))-(2)

Independent Float
(Ej-Li)-tij
(11)=((4)-(5))-(2)
1-3 6 0 6 0 12 6 6 6 0 0
2-4 5 8 13 8 16 13 11 3 0 0
3-5 5 6 17 12 17 11 12 6 6 0
3-6 12 6 21 12 29 18 17 11 3 -3
4-8 5 13 18 16 21 18 16 3 0 -3
6-11 5 21 26 29 34 26 29 8 0 -8
7-6 0 21 21 21 29 21 29 8 0 0
8-7 0 18 21 21 21 18 21 3 3 0
8-10 12 18 38 21 38 30 26 8 8 5
9-12 6 28 41 28 41 34 35 7 7 7
11-12 7 26 41 34 41 33 34 8 8 0

PLEASE LIKE THIS ANSWER, IT HELPS ME A LOT. THANK YOU!!!


Related Solutions

Suppose that you have been appointed the project manager for a project to develop an online...
Suppose that you have been appointed the project manager for a project to develop an online booking system for a multi-doctor medical practice that will replace an existing desktop system. The key functionality that is required is as follows: Patient registration Patient login Book first available appointment with any doctor Book an appointment at a time of the patient’s choosing with a doctor of their choice. What development methodologies should you consider? How would you stage the work for each...
Suppose that you have been appointed the project manager for a project to develop an online...
Suppose that you have been appointed the project manager for a project to develop an online booking system for a multi-doctor medical practice that will replace an existing desktop system. The key functionality that is required is as follows: Patient registration Patient login Book first available appointment with any doctor Book an appointment at a time of the patient’s choosing with a doctor of their choice. a. What development methodologies should you consider? How would you stage the work for...
You have been appointed as the Project Manager for a New Product Launch Project by your...
You have been appointed as the Project Manager for a New Product Launch Project by your company. You must prepare a set of documents for the project kick-off meeting coming up next month. Task 1: Prepare a Project Charter for the New Product Launch Project (according to the choice of your product as explained above). Please use the Project Charter template given below Name of the Project Background [Why is the project being undertaken? Describe an opportunity or problem that...
Question 1 Suppose that you have been appointed the project manager for a project to develop...
Question 1 Suppose that you have been appointed the project manager for a project to develop an online booking system for a multi-doctor medical practice that will replace an existing desktop system. The key functionality that is required is as follows: • Patient registration • Patient login • Book first available appointment with any doctor • Book an appointment at a time of the patient’s choosing with a doctor of their choice. What development methodologies should you consider? How would...
You have been appointed as a project manager for a large bank in Dubai. The board...
You have been appointed as a project manager for a large bank in Dubai. The board of directors can’t decide how to analyse the project stakeholders. They ask you to compare the Salience Model to the Stakeholder Rating Model. You must refer to the example of stakeholders in your comparison.
You have been appointed as the Software Quality Assurance Manager for a project that enables students...
You have been appointed as the Software Quality Assurance Manager for a project that enables students to access their results on their android phones. As the person responsible for the overall quality aspects, its your interest to ensure that strong quality assurance practices are put in place to forestall any software failure by the end-users. i. It is important that you conduct requirements validation as part of your quality assurance practices in this project. Could you explain in your own...
Assume you have just been appointed a project manager for building a female hostel at the...
Assume you have just been appointed a project manager for building a female hostel at the University Campus area. Prepare the procurement plan to be submitted to the management
Assume that you have been appointed as Marketing Manager for a company in your region. In...
Assume that you have been appointed as Marketing Manager for a company in your region. In the past, many of their new products were unsuccessful. The senior management team now wants to focus on proper idea generation for their new products and also wants to select profitable market segments correctly. i) How would you select profitable market segment(s) for this company? Justify your answer. ii) Discuss your strategies on how to generate proper ideas for this company’s new products.
In this case,I have been appointed the project manager of a large firm glass making company...
In this case,I have been appointed the project manager of a large firm glass making company that distributes nationally. Identify some of the positive and negative risks associated with this project, and then rank these risks based on their level of priorities. Discuss how each of these risks can affect the project team. Using the key processes of project risk management, propose risk-response plans to the identified risks, and identify how each team member can play a role in these...
You have been appointed as the Human Resource Manager of Milynn Deeds Insurance Company. For you...
You have been appointed as the Human Resource Manager of Milynn Deeds Insurance Company. For you to properly define the duties, responsibilities and accountabilities of a job, it is crucial to conduct a job analysis. Discuss the uses of job analysis information.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT