Question

In: Finance

A firm is considering a $12,000 risky project. The expected cash flows are $3,000 in year...

A firm is considering a $12,000 risky project. The expected cash flows are $3,000 in year 1, $5,000 in year 2, and $7,000 in year 3. The firm's cost of capital is 11%, but the financial manager uses a hurdle rate of 9% for less-risky projects and 13% for riskier projects. Should the firm invest in this riskier project?

No, the NPV is -$578.05

No, the NPV is -$120.85

Yes, the NPV is $578.05

Yes, the NPV is $120.85

Yes, the NPV is $365.98

Solutions

Expert Solution

The correct answer is option A i.e. No, the NPV is -$578.05

Year Cashflow PV @13%
0 $              -12,000 $              -12,000
1 $                  3,000 $                  2,655
2 $                  5,000 $                  3,916
3 $                  7,000 $                  4,851
$              -578.05

Thumbs Up Please! Thank You


Related Solutions

firm is considering a project with the following expected cash flows: Year Cash Flow 0 -P350...
firm is considering a project with the following expected cash flows: Year Cash Flow 0 -P350 million 1 100 million 2 185 million 3 112.5 million 4 350 million The project’s WACC is 10 percent. What is the project’s discounted payback? a. 3.15 years b. 4.09 years c. 1.62 years d. 3.09 years The lolo Corporation has been presented with an investment opportunity that will yield end-of-year cash flows of $30,000 per year in Years 1 through 4, $35,000 per...
19) A firm is considering a project that is expected to generate annual cash flows of...
19) A firm is considering a project that is expected to generate annual cash flows of $24,000 for 15 years. The project requires an initial investment of $247,103.44. The cost of capital is 8.13%. What is the IRR of the project?
1.Projected Total Cash Flows Firm A is considering a project which will initially require $12,000 for...
1.Projected Total Cash Flows Firm A is considering a project which will initially require $12,000 for new equipment. The equipment will be depreciated straight line to a zero book value over the three year life of project In addition, the project will require an investment of $30,000 in net working capital which will be recovered at the end of the project Annual sales are $45,000 with cost of $32,400.The tax rate is 34% What is the net present value of...
Gio's Restaurants is considering a project with the following expected cash​ flows: Year Project Cash Flow​...
Gio's Restaurants is considering a project with the following expected cash​ flows: Year Project Cash Flow​ (millions) 0 ​$(180​) 1 80 2 75 3 80 4 95 If the​ project's appropriate discount rate is 12 ​percent, what is the​ project's discounted payback​ period? The​ project's discounted payback period is ___ years.
A company is considering a project with the following expected cash flows: Year 0: -$685,000 Year...
A company is considering a project with the following expected cash flows: Year 0: -$685,000 Year 1: $305,000 Year 2: $305,000 Year 3: $305,000 The company requires a 15% return on investment. Compute the NPV for the project.
A firm is considering investing in a project with the following cash flows: Year 1 2...
A firm is considering investing in a project with the following cash flows: Year 1 2 3 4 5 6 7 8 Cash flow (OMR) 1,000 1,500 2,000 1,750 1,500 1,000 1,000 500 The initial investment is OMR 7,250. The firm has a required rate of return of 8 per cent. Calculate: The payback period;    The discounted payback; The net present value.   
A firm is considering an investment project with the following cash flows: Year 0 = -$110,000...
A firm is considering an investment project with the following cash flows: Year 0 = -$110,000 (initial costs); Year 1= $40,000; Year 2 =$90,000; and Year 3 = $30,000; and Year 4 = $60,000. The company has a 10% cost of capital. What is the project’s discounted payback? 1.67 years 1.86 years 1.99 years 2.08 years A firm is considering an investment project with the following cash flows: Year 0 = -$110,000 (initial costs); Year 1= $40,000; Year 2 =$90,000;...
A project has the following cash flows : Year Cash Flows 0 −$12,000 1 5,290 2...
A project has the following cash flows : Year Cash Flows 0 −$12,000 1 5,290 2 7,630 3 5,040 4 −1,580 Assuming the appropriate interest rate is 10 percent, what is the MIRR for this project using the discounting approach? 19.21% 15.23% 13.96% 11.63% 17.77%
A company is considering a project that has the following cash flows: Co 3,000, C, +500,...
A company is considering a project that has the following cash flows: Co 3,000, C, +500, = +1,500, and C3 = +5,000, with a risk-adjusted discount rate of 15%. Calculate the Net Present Value (NPV), Internal Rate of Return (IRR), Profitability Index, and the Payback of this project. If you were the manager of the firm, will you accept or reject the project based on the calculation results above?
A project has expected cash flows of $55 next year (year 1). These cash flows will...
A project has expected cash flows of $55 next year (year 1). These cash flows will grow at 6% per year through year 6. Growth from year 6 to 7 will be -2%, and this negative growth will continue in perpetuity. Assume a discount rate of 8%. What is the present value today (year 0) of these cash flows? DO BY HAND
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT