In: Accounting
| You have been given the following list of variances for the Pennadi Company: | 
| Direct materials price variance | $ | 16,800 | U | 
| Direct materials quantity variance | 12,000 | U | |
| Direct labour rate variance | 16,270 | F | |
| Direct labour efficiency variance | 27,000 | U | |
| Variable overhead spending variance | 3,120 | U | |
| Variable overhead efficiency variance | 6,000 | U | |
| Fixed overhead budget variance | 5,000 | U | |
| Fixed overhead volume variance | 53,250 | F | |
| You have also been given the following information: | 
| Actual units produced | 25,000 | ||
| Budgeted units of production (normal volume) | 20,000 | ||
| Standard labour-hours for actual output | 12,500 | ||
| Standard material units for actual output | 400,000 | ||
| Actual direct labour costs | $ | 235,730 | |
| Actual cost of direct materials | $ | 496,800 | |
| 
 Overhead is applied using direct labour-hours. Variable overhead is applied at the rate of $10 per direct labour-hour. The materials purchase price was $0.828.(Attempt the following questions in the order listed.)  | 
| 6. | How many actual direct labour-hours were worked? | 
| 7. | What was the standard cost per unit of output produced, assuming that variable costing was used? | 
| 8. | Calculate the budgeted fixed overhead cost allocation rate. (Round your answer to 2 decimal places.) | 
| 9. | Calculate the actual, budgeted, and allocated fixed overhead costs. | 
| 10. | Calculate the underapplied or overapplied fixed overhead cost. | 
6) How many actual direct labours hours worked
Direct Lab rate var = (Std rate per labour hr - actual rate per labour hr)Actual direct labour hrs
16270 = (Std rate per lab hr*Actual lab hrs) - (Actual Rate per lab hr*Actual direct lab hrs)
16270 = (Std rate per lab hr*Actual lab hrs) - (Actual Direct lab cost)
16270 = (Std rate per lab hr*Actual lab hrs) - 235730(given)
(Std rate per lab hr*Actual lab hrs) = 16270+235730 = 252000
Now,
Direct Lab efficiency var = (Std Lab hrs -Actual lab hrs)*Std rate per Lab hr
-27000 = (Std Lab hrs*Std rate per lab hr) - (Actual lab hrs*Std rate per lab hr)
-27000 = (12500 * Std rate per lab hr) - 252000(calculated above)
(12500 * Std rate per lab hr) = -27000+252000= 225000
Std rate per lab hr = 225000/12500=18
So, Actual lab hrs = 252000/18 = 14000 hrs
7) Std Cost per unit of Product
First of all we need to claculate Std rate per Direct mat
Actual rate per direct mat = 0.828(given)
So, Actual Qty = Actual Direct mat cost / Actual rate per direct mat = 496800/0.828 = 600000
Now, Direct Mat price Var = (Std rate per direct mat - actual rate per direct mat) * Actual direct mat used
-16800 = (Std rate per direct mat * Actual direct mat used) - (Actual rate *Actual direct mat used)
-16800 = (Std rate per direct mat * 600000) - Actual direct mat cost( which is equal to 496800)
(Std rate per direct mat * 600000) = -16800+496800= 480000
Std rate per direct mat = 480000/600000 = 0.8
At this point of time, i realized something is wrong with the question as standard direct material units cant be 400000 because if std direct mat is 400000 then, Direct Mat qty Var = (400000-600000)0.8=160000 unfavourable but given in question 12000 unfavourtable, also variable OH efficiency var is not matching and i aslo think some information are missing, so please look into it