Question

In: Finance

Alberta’s previous NDP government legislated that all coal generation plants would be shutting down by 2030...

Alberta’s previous NDP government legislated that all coal generation plants would be shutting down by 2030 and that the province would be transitioning from coal generation electricity to more renewable energy generation and distribution. It also legislated that the Alberta electricity market would be moving from an energy only market to a capacity market by summer 2021

In order for TransAlta Hydro to become more competitive, efficient and be able to compete in the new market, they need to modernize their electricity producing facilities to be able to transition from coal-fire electricity generation to more renewable energy sources.

You are the project manager for a major retrofit project for TransAlta’s BigHorn Dam on the North Saskatchewan River near Edmonton. The baseline estimated budget is 10M and the initial timeline for the project with expected work completed percentages is as follows:

Month

1

2

3

4

5

6

7

8

9

Planned % completed

5%

13%

25%

35%

50%

65%

77%

90%

100%

The other available information is as follows:

  • By end of month #1, the project is behind 1% (only 4% has been completed) and the expected 5% costs has been used.
  • By end of month #2, unexpected very cold and wet weather put the project further behind another 2% overall (meaning that as of end of month 2, only 10% of the work has been completed) and an extra $10,000 had to be spent on area heaters and upgrades for a de-watering system needed to keep equipment and material dry. This is above and beyond the % planned for the month.
  • During month #3, the planned % of work for the month was achieved, however, the budget for the month was escalated and approved by 15%
  • Month 4 went as planned except for an additional cost of $15,000 to comply with future environmental legislation and inspections. This extra expense was approved
  • During month #5, only 2/3 of the planned percentage of work for the month was achieved and 90% of the budget for the month was used.
  • During month #6, extra measures to recover some ground resulted in a gain of 20% of work completed above and beyond the planned % of work for the month. Budget was escalated by 30% for the month
  • During month #7, an escalation of 10% for the moths’ budget was issued and approved. The % of work completed was as planned
  • During month #8, only 50% of the planned work was completed and 75% of the budgeted costs were spent
  • During month #9, 85% of the planned work for the month was completed and 85% of the planned budget for the month was spent.

Calculate EV analysis for each end-of-month based only on the available information up to that point (for example, on month 3, you would take into account all information up to and including end of month #3). Required for each month: BAC, BCWP, ACWP, CPI, ETC and EAC

Approximately, how much more time in months will it take to complete the project? Include up to 2 decimal points in your answer.

Solutions

Expert Solution

BCWP = % Complete (Actual) x Task Budget

BAC = Total Budget

ACWP = actual cost incurred till date

CPI = BCWP / ACWP = 1.33. This means the project has spent 33% less than it should have at this point in time.

ETC = (BAC – BCWP) / CPI

EAC = ACWP + ETC

EV Analysis:

Month BAC Additional Cost % Completion % Budget Utilised BCWP ACWP CPI ETC EAC
1    10.00                -   4% 5%      0.40      0.50     0.80    12.00    12.50
2    10.00            0.01 10% 13%      1.00      1.31     0.76    11.79    13.10
3    10.00                -   25% 26.80%      2.50      2.68     0.93      8.04    10.72
4    10.00            0.02 35% 36.80%      3.50      3.70     0.95      6.86    10.56
5    10.00                -   45% 50.30%      4.50      5.03     0.89      6.15    11.18
6    10.00                -   63% 69.80%      6.30      6.98     0.90      4.10    11.08
7    10.00                -   75% 83.00%      7.50      8.30     0.90      2.77    11.07
8    10.00                -   82% 92.75%      8.15      9.28     0.88      2.11    11.38
9    10.00                -   90% 101.25%      9.00    10.13     0.89     1.13    11.25

It can be seen from the data that only 90% work has been completed, whereas budget has been overutilised by 1.25%. It will take 1.13 months more to complete the remaining 10% task.


Related Solutions

Outside of health reasons and government mandates, why are some businesses shutting down temporarily during this...
Outside of health reasons and government mandates, why are some businesses shutting down temporarily during this pandemic? (Please use economic concepts covered in this course.)
If the U.S. directed airstrikes against Iran, shutting down Iranian oil exports, how would this impact...
If the U.S. directed airstrikes against Iran, shutting down Iranian oil exports, how would this impact the following items and explain? a) Would the world demand curve for crude oil: Shift to the right, shift to the left, or stay the same b) World supply curve for crude oil: Shift to the right, shift to the left, or stay the same c) U.S. demand curve for crude oil: Shift to the right, shift to the left, or stay the same...
ALL ARE MULTIPLE CHOICE In his breeding experiments, Mendel first crossed true-breeding _____ generation plants to...
ALL ARE MULTIPLE CHOICE In his breeding experiments, Mendel first crossed true-breeding _____ generation plants to produce the _____ generation, which were then allowed to self-pollinate to generate the _____ offspring. F ... P1 ... P2 P1 ... P2 ... P3 P ... F1 ... F2 P1 ... P2 ... F F1 ... F2 ... F3 Two organisms with genotype AaBbCcDdEE mate. These loci are all independent. What fraction of the offspring will have the same genotype as the parents?...
Today's Global Economy is very top-down driven with the government making all the decisions and regulations...
Today's Global Economy is very top-down driven with the government making all the decisions and regulations as it relates to doing business globally. What are some advantages and disadvantages to this approach? Is there another approach that might work better? Ask an interesting, thoughtful question pertaining to the topic Provide extensive additional information on the topic Explain, define, or analyze the topic in detail Share an applicable personal experience need 400 own words
What would happen if all the plants died? Few people care about the impact of vegetation...
What would happen if all the plants died? Few people care about the impact of vegetation other than for consumption. Discuss the impact photosynthesizing plants have on our lives.
How would a cut in government expenditures leading to a decrease in budget deficit (keeping all...
How would a cut in government expenditures leading to a decrease in budget deficit (keeping all the other factors constant) affect bond prices? Explain and show with the help of a well-labeled demand and supply diagram for bonds. Please also state the impact of this change in bond prices on interest rates.Immersive Reader
Should the U.S. rely more on government funding for health care for all citizens? What would...
Should the U.S. rely more on government funding for health care for all citizens? What would the advantages and disadvantages be of such a system?  
Here is a variable: Some people support a government-backed health insurance plan that would cover all...
Here is a variable: Some people support a government-backed health insurance plan that would cover all citizens, whereas others oppose such a plan. This variable has two values: “support government plan” and “oppose government plan.” Let's say that one explanation, the “income explanation,” suggests this hypothesis: In a comparison of individuals, those who have low incomes will be more likely to support a government plan than will those who have high incomes. A rival explanation, the “age explanation,” suggests this...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT