In: Finance
Alberta’s previous NDP government legislated that all coal generation plants would be shutting down by 2030 and that the province would be transitioning from coal generation electricity to more renewable energy generation and distribution. It also legislated that the Alberta electricity market would be moving from an energy only market to a capacity market by summer 2021
In order for TransAlta Hydro to become more competitive, efficient and be able to compete in the new market, they need to modernize their electricity producing facilities to be able to transition from coal-fire electricity generation to more renewable energy sources.
You are the project manager for a major retrofit project for TransAlta’s BigHorn Dam on the North Saskatchewan River near Edmonton. The baseline estimated budget is 10M and the initial timeline for the project with expected work completed percentages is as follows:
Month |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
Planned % completed |
5% |
13% |
25% |
35% |
50% |
65% |
77% |
90% |
100% |
The other available information is as follows:
Calculate EV analysis for each end-of-month based only on the available information up to that point (for example, on month 3, you would take into account all information up to and including end of month #3). Required for each month: BAC, BCWP, ACWP, CPI, ETC and EAC
Approximately, how much more time in months will it take to complete the project? Include up to 2 decimal points in your answer.
BCWP = % Complete (Actual) x Task Budget
BAC = Total Budget
ACWP = actual cost incurred till date
CPI = BCWP / ACWP = 1.33. This means the project has spent 33% less than it should have at this point in time.
ETC = (BAC – BCWP) / CPI
EAC = ACWP + ETC
EV Analysis:
Month | BAC | Additional Cost | % Completion | % Budget Utilised | BCWP | ACWP | CPI | ETC | EAC |
1 | 10.00 | - | 4% | 5% | 0.40 | 0.50 | 0.80 | 12.00 | 12.50 |
2 | 10.00 | 0.01 | 10% | 13% | 1.00 | 1.31 | 0.76 | 11.79 | 13.10 |
3 | 10.00 | - | 25% | 26.80% | 2.50 | 2.68 | 0.93 | 8.04 | 10.72 |
4 | 10.00 | 0.02 | 35% | 36.80% | 3.50 | 3.70 | 0.95 | 6.86 | 10.56 |
5 | 10.00 | - | 45% | 50.30% | 4.50 | 5.03 | 0.89 | 6.15 | 11.18 |
6 | 10.00 | - | 63% | 69.80% | 6.30 | 6.98 | 0.90 | 4.10 | 11.08 |
7 | 10.00 | - | 75% | 83.00% | 7.50 | 8.30 | 0.90 | 2.77 | 11.07 |
8 | 10.00 | - | 82% | 92.75% | 8.15 | 9.28 | 0.88 | 2.11 | 11.38 |
9 | 10.00 | - | 90% | 101.25% | 9.00 | 10.13 | 0.89 | 1.13 | 11.25 |
It can be seen from the data that only 90% work has been completed, whereas budget has been overutilised by 1.25%. It will take 1.13 months more to complete the remaining 10% task.