Question

In: Finance

Q1: Carrefour is expecting its new center to generate the following cash flows: Years 0 1...

Q1: Carrefour is expecting its new center to generate the following cash flows:

Years

0

1

2

3

4

5

Initial
Investment

($35,000,000)

Net operating cash-flow

$6,000,000

$8,000,000

$16,000,000

$20,000,000

$30,000,000

a. Determine the payback for this new center. (1 mark)

b. Determine the net present value using a cost of capital of 15 percent. Should the project be accepted? (1 mark)

Answer:

Q2. What is the EAC of two projects: project A, which costs $150 and is expected to last two years, and project B, which costs $190 and is expected to last three years? The cost of capital is 12%. (1 mark)

Answer:

Q3. A company pays annual dividends of $10.40 with no possibility of it changing in the next several years. If the firm’s stock is currently selling at $80, what is the required rate of return? (1 mark)

Answer:

Q4. Stag corp has a capital structure which is based on 50% common stock, 20% preferred stock and 30% debt. The cost of common stock is 14%, the cost of preferred stock is 8% and the pre-tax cost of debt is 10%. The firm's tax rate is 40%. (1 mark)

  1. Calculate the WACC of the firm.
  2. The firm is considering a project that is equally as risky as the firm's current operations. This project has initial costs of $280,000 and annual cash inflows of $66,000, $320,000, and $133,000 over the next three years, respectively. What is the net present value of this project ?

Solutions

Expert Solution

1.a)

as

years Initial Investment Net Operating Cashi flow Cumulative cash
0 ($35,000,000)
1 $6,000,000 $6,000,000
2 $8,000,000 $14,000,000
3 $16,000,000 $30,000,000
4 $20,000,000 $50,000,000
5 $30,000,000 $80,000,000
Calculation of payback period
Year before full recovery+ unrecovered cost at start of year
Cash flow during year
3+(35,000,000-30,000,000)/16,000,000
3+5,000,000/16,000,000
3+0.3125

3.3125 years

Answer b).

years Initial Investment Net Operating Cashi flow Cost of capital@15%
0 ($35,000,000)
1 $6,000,000 0.86957 5217391.304
2 $8,000,000 1.16257 9300568
3 $16,000,000 2.28323 36531680
4 $20,000,000 2.85498 57099600
5 $30,000,000 3.35216 100564800
Total discounted cash flow 208714039.3
Cash outflow ($35,000,000)
NPV $173,714,039

As NPV is positive , we shoud accept the project.

Answer2)

EAC= Asset Price×Discount Rate

   1-(1+Discount rate)​ −n

Project A

EAC=

Project A
EAC 150*0.12/1-(1+0.12)-2
18/1-(1.12)-2
Nominator 18
denominator 1-1/1.2544
denominator 1.2544-1/1.2544
0.2544/1.2544
0.202806122
EAC 18/0.202806122
88.75471718
Project B
190*0.12/1-(1+0.12)-3
22.8/1-(1.12)-3
Nominator 22.8
denominator 1-1/1.402464
denominator 1.402464-1/1.402464
0.402464/1.402464
denominator 0.286969
EAC 22.8/0.286969
79.45109

ANSWER 3)

Cost of capital= Dividend paid/ selling price of stock

=10.40/80

= 0.135 or 13.5%

Answer 4):
Capital structure of the stag corp
= 50% common stock + 20% preferred stock + 30% debt

Cost of common stock(Ke)= 14%
Cost of preferred Stock(Kp)= 8%
Cost of debt(Kd)= 10%
Tax= 40%

Answer a) WACC

Ke*% of common stock + Kp* % of Preferred Stock + Kd(1-tax)*% of Debt


=14%*50%+ 8%*20% + (1-0.4)10%*30%
=7%+1.6%+(0.6)3
=7%+1.6%+1.8%
=10.4%

Answer B)

years Initial Investment Net Operating Cashi flow [email protected]%
0 ($280,000)
1 $66,000 0.9057971 59782.6087
2 $320,000 0.82046839 262549.8845
3 $133,000 0.74317781 98842.64919
Total discounted cash flow 421175.1424
Cash outflow ($280,000)
NPV $141,175

Related Solutions

Q1: Carrefour is expecting its new center to generate the following cash flows: Years 0 1...
Q1: Carrefour is expecting its new center to generate the following cash flows: Years 0 1 2 3 4 5 Initial Investment ($35,000,000) Net operating cash-flow $6,000,000 $8,000,000 $16,000,000 $20,000,000 $30,000,000 a. Determine the payback for this new center. (1 mark) b. Determine the net present value using a cost of capital of 15 percent. Should the project be accepted?
Q1: Carrefour is expecting its new center to generate the following cash flows: Years 0 1...
Q1: Carrefour is expecting its new center to generate the following cash flows: Years 0 1 2 3 4 5 Initial Investment ($35,000,000) Net operating cash-flow $6,000,000 $8,000,000 $16,000,000 $20,000,000 $30,000,000 a. Determine the payback for this new center. (1 mark) b. Determine the net present value using a cost of capital of 15 percent. Should the project be accepted? (1 mark) Answer: Q2. What is the EAC of two projects: project A, which costs $150 and is expected to...
Assignment Questions Q1: Carrefour is expecting its new center to generate the following cash flows: Years...
Assignment Questions Q1: Carrefour is expecting its new center to generate the following cash flows: Years 0 1 2 3 4 5 Initial Investment ($35,000,000) Net operating cash-flow $6,000,000 $8,000,000 $16,000,000 $20,000,000 $30,000,000 a. Determine the payback for this new center. (1 mark) b. Determine the net present value using a cost of capital of 15 percent. Should the project be accepted? (1 mark) Q2. What is the EAC of two projects: project A, which costs $150 and is expected...
Q1.) A project has the following cash flows for years 0 through 2, respectively: -13,568, 9,415,...
Q1.) A project has the following cash flows for years 0 through 2, respectively: -13,568, 9,415, 9,983. What is the internal rate of return on this project? Q2.) GDebi Enterprises is thinking of building a chemical processing plant to produce 4-hydroxy-3-methoxybenzaldehyde. The firm estimates that the initial cost of the project will be $11.7 million, and the plant will produce cash inflows of $7.2 million for the next 5 years, after which time the project will terminate. In the 6th...
Q1/ A project has the following cash flows for years 0 through 3, respectively: -34,416, 15,926,...
Q1/ A project has the following cash flows for years 0 through 3, respectively: -34,416, 15,926, 21,329, 38,250. If the required return is 10.6 percent, what is the net present value of the project? Q2/ A project has the following cash flows for years 0 through 2, respectively: -11,062, 8,666, 8,313. What is the internal rate of return on this project? Q3/ A project has the following cash flows, for years 0 through 3 respectively: -27,084, 11,112, 8,232, 9,204. If...
1. Assume a corporation is expecting the following cash flows in the future: $-6 million in...
1. Assume a corporation is expecting the following cash flows in the future: $-6 million in year 1, $8 million in year 2, $19 million in year 3. After year 3, the cash flows are expected to grow at a rate of 4% forever. The discount rate is 8%, the firm has debt totaling $55 million, and 9 million shares outstanding. What should be the price per share for this company? 1a. As with most bonds, consider a bond with...
There are two projects with the following cash flows. Years: 0 1 2 3 4 5...
There are two projects with the following cash flows. Years: 0 1 2 3 4 5 Project 1: -210 125 125 175 175 -400 Project 2:  300 -95 -75 -125 -400 600 a. What are the NPVs of these two projects if market interest rate is 3%? b. With the interest rate of 6%, please modified these two projects to let them have only one IRR for each one of them. (That means the sign of cash flows of each project...
UBTECH Robotics is expected to generate the following free cash flows over the next five years....
UBTECH Robotics is expected to generate the following free cash flows over the next five years. After which, the free cash flows are expected to grow at the industry average of 3% per year. Using the discounted free cash flow model and the weighted average cost of capital of 11% UBTECH Robotics FCF Forecast ($ Millions) Year 1999, 2000, 2001, 2002, 2003, 2004 FCF (Amount in Millions)$55, $45, $89, $102, $84, $87 a. Estimate the enterprise value (V0) of UBTECH...
Hammer Inc wants to expand into Spain. They are expecting the following cash flows over the...
Hammer Inc wants to expand into Spain. They are expecting the following cash flows over the next five years. Exchange rates and discount rates are also given.   Year 1    Year 2 Year 3 Year 4 Year 5 Expected CF (Euros): 2 million 2.2 million 2.5 mil 3 mil 4 mil Exchange Rate (1 Euro): $1.40    $1.40 $1.30 $1.25 $1.20 Discount Rate 18% 18% 15%    15% 15% What is the value of the project?
Assume a corporation is expecting the following cash flows in the future: $-9 million in year...
Assume a corporation is expecting the following cash flows in the future: $-9 million in year 1, $11 million in year 2, $23 million in year 3. After year 3, the cash flows are expected to grow at a rate of 6% forever. The discount rate is 13%, the firm has debt totaling $47 million, and 8 million shares outstanding. What should be the price per share for this company?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT