In: Finance
FastTrack Bikes, Inc. is thinking of developing a new composite road bike. Development will take six years and the cost is $198,100 per year. Once in production, the bike is expected to make $301,477 per year for 10 years. The cash inflows begin at the end of year 7.
For parts a-c, assume the cost of capital is 9.9%.
a. Calculate the NPV of this investment opportunity. Should the company make the investment?
b. Calculate the IRR and use it to determine the maximum deviation allowable in the cost of capital estimate to leave the decision unchanged.
c. How long must development last to change the decision?
For parts d-f, assume the cost of capital is 14.6%.
d. Calculate the NPV of this investment opportunity. Should the company make the investment?
e. How much must this cost of capital estimate deviate to change the decision?
f. How long must development last to change the decision?
a. Calculate the NPV of this investment opportunity.
If the cost of capital is 9.9%, the NPV is $ ___ . (Round to the nearest dollar.)
Should the company make this investment? (Select the best choice below.)
A. Accept the investment because the NPV is equal to or less than zero ($0).
B. Reject the investment because the NPV is less than zero ($0).
C. Accept the investment because the NPV is equal to or greater than zero ($0).
D. Reject the investment because the NPV is equal to or greater than zero ($0).
b. Calculate the IRR and use it to determine the maximum deviation allowable in the cost of capital estimate to leave the decision unchanged.
The IRR is ___ %. (Round to two decimal places.)
If the cost of capital is 9.9%, the maximum deviation is ___ %. (Round to two decimal places.)
c. How long must development last to change the decision?
For the decision to change, development must last ___ years, or longer. (Round to two decimal places.)
d. Calculate the NPV of this investment opportunity. Should the company make the investment?
If the cost of capital is 14.6%, the NPV is $ ___ . (Round to the nearest dollar.)
Should the company make the investment? (Select the best choice below.)
A. Accept the investment because the NPV is equal to or greater than zero ($0)
B. Accept the investment because the NPV is equal to or less than zero ($0).
C. Reject the investment because the NPV is less than zero ($0).
D. Reject the investment because the NPV is equal to or greater than zero ($0).
e. How much must this cost of capital estimate deviate to change the decision?
The maximum deviation is __ %. (Round to two decimal places.)
f. How long must development last to change the decision?
For the decision to change, development must last no longer than __ years
a.NPV of this investment opportunity |
-(198100*4.36085)+(301477*(7.87051-4.36805))= |
192027 |
P/A,198100,6 yrs.,9.9%=4.36805 |
P/A,301477,16 yrs.,9.9%=7.87051 |
Yes. The company should make this invetsment as the NPV is POSITIVE. |
If the cost of capital is 9.9%, the NPV is $ 192027 |
C. Accept the investment because the NPV is equal to or greater than zero ($0). |
b.IRR |
Seting the NPV to 0,we get the IRR as, |
0=-(198100*(1-(1+r)^-6)/r))+(301477*((1-(1+r)^-16)/r)-(1-(1+r)^-6)/r))) |
Solving for r, |
IRR= 12.88% |
So, the maximum deviation allowable in the cost of capital estimate to leave the decision unchanged |
is |
12.88%-9.9%= |
2.98% |
or 3% |
The IRR is 12.88 % |
If the cost of capital is 9.9%, the maximum deviation is 2.98% |
d.NPV of this investment opportunity |
-(198100*3.82561)+(301477*(6.07450-3.82561))= |
-79865 |
P/A,198100,6 yrs.,14.6%=3.82561 |
P/A,301477,16 yrs.,14.6%=6.07540 |
No. The company should make this invetsment as the NPV is NEGATIVE. |
If the cost of capital is 14.6%, the NPV is $ -79865 |
C. Reject the investment because the NPV is less than zero ($0). |
b.IRR |
Seting the NPV to 0,we get the IRR as, |
0=-(198100*(1-(1+r)^-6)/r))+(301477*((1-(1+r)^-16)/r)-(1-(1+r)^-6)/r))) |
Solving for r, |
IRR= 12.88% |
So, the maximum deviation allowable in the cost of capital estimate to leave the decision unchanged |
is |
12.88%-14.6%= |
-1.72% |
or -2% |
The maximum deviation is -1.72% |