In: Finance
Machine A has an initial cost of $19,500 and a salvage value of $7500 (today's value) at the end of its 12 year life.
Machine B has an initial cost of $17,900 and a salvage value of $2300 (today's value) at the end of it's 6 year life.
Inflation is 3.9%
Don’t forget, we will need to increase the costs and salvage values by inflation for any transaction other than year 0.
The company uses a MARR rate of 14%
Benefits for machine A in year 1 are $5,250 and increase by 5.5% per year.
Benefits for machine B in year 1 are $5,400 and increase by 5.5% per year.
Costs for each machine start at $800 and increase with the inflation rate
A. Show the Cash flow table for these two machines over the project.
B. What is the NPW, the EUAW and the IRR for both of these machines?
Answer - A
Statement showing Cash flow table of Machine A
Amount ($)
Particulars | Working | Year 1 | Year 2 | Year 3 | Year 4 | Year 5 | Year 6 | Year 7 | Year 8 | Year 9 | Year 10 | Year 11 | Year 12 |
Benefits for Machine | Increase by 5.5% per year | 5,250 | 5,539 | 5,843 | 6,165 | 6,504 | 6,862 | 7,239 | 7,637 | 8,057 | 8,500 | 8,968 | 9,461 |
Cost for Machine | Increase by inflation rate of 3.9% per year | -800 | -831 | -864 | -897 | -932 | -969 | -1,006 | -1,046 | -1,086 | -1,129 | -1,173 | -1,219 |
Cash Flow | 4,450 | 4,708 | 4,980 | 5,267 | 5,572 | 5,893 | 6,232 | 6,591 | 6,971 | 7,371 | 7,795 | 8,242 |
Statement showing Cash flow table of Machine B
Amount ($)
Particulars | Working | Year 1 | Year 2 | Year 3 | Year 4 | Year 5 | Year 6 |
Benefits for Machine | Increase by 5.5% per year | 5,400 | 5,697 | 6,010 | 6,341 | 6,690 | 7,058 |
Cost for Machine | Increase by inflation rate of 3.9% per year | -800 | -831 | -864 | -897 | -932 | -969 |
Cash Flow | 4,600 | 4,866 | 5,147 | 5,444 | 5,757 | 6,089 |
Answer - B
Statement showing NPW of Machine A
Amount ($)
Year | Particulars | Notes / Working | Amount (A) | Discount Factor @ 14% (B) | Present Value (A * B) |
0 | Machine cost | Given | -19,500 | 1 | -19,500 |
1 | Cash Flow | Calculated above | 4,450 | 0.8772 | 3,904 |
2 | Cash Flow | Calculated above | 4,708 | 0.7695 | 3,622 |
3 | Cash Flow | Calculated above | 4,980 | 0.6750 | 3,361 |
4 | Cash Flow | Calculated above | 5,267 | 0.5921 | 3,119 |
5 | Cash Flow | Calculated above | 5,572 | 0.5194 | 2,894 |
6 | Cash Flow | Calculated above | 5,893 | 0.4556 | 2,685 |
7 | Cash Flow | Calculated above | 6,232 | 0.3996 | 2,491 |
8 | Cash Flow | Calculated above | 6,591 | 0.3506 | 2,311 |
9 | Cash Flow | Calculated above | 6,971 | 0.3075 | 2,144 |
10 | Cash Flow | Calculated above | 7,371 | 0.2697 | 1,988 |
11 | Cash Flow | Calculated above | 7,795 | 0.2366 | 1,844 |
12 | Cash Flow | Calculated above | 8,242 | 0.2076 | 1,711 |
12 | Salvage value | $7,500 * (1.039)12 | 11,870 | 0.2076 | 2,464 |
Net Present Worth | 15,036 |
Statement showing NPW of Machine B
Amount ($)
Year | Particulars | Notes / Working | Amount (A) | Discount Factor @ 14% (B) | Present Value (A * B) |
0 | Machine cost | Given | -17,900 | 1 | -17,900 |
1 | Cash Flow | Calculated above | 4,600 | 0.8772 | 4,035 |
2 | Cash Flow | Calculated above | 4,866 | 0.7695 | 3,744 |
3 | Cash Flow | Calculated above | 5,147 | 0.6750 | 3,474 |
4 | Cash Flow | Calculated above | 5,444 | 0.5921 | 3,223 |
5 | Cash Flow | Calculated above | 5,757 | 0.5194 | 2,990 |
6 | Cash Flow | Calculated above | 6,089 | 0.4556 | 2,774 |
6 | Salvage value | $2,300 * (1.039)6 | 2,893 | 0.4556 | 1,318 |
Net Present Worth | 3,659 |