Question

In: Accounting

Discuss why the amount actually spent on direct labor could differ from that was budgeted in...

Discuss why the amount actually spent on direct labor could differ from that was budgeted in the planning budget?

What assumption is implicitly made about cost behavior when all of the items in a budget are adjusted in proportion to a change in activity?

Explain in detail why the spending variance takes the difference between the Flexible budget and Actual results instead of Planning budget and Actual results.

Solutions

Expert Solution

. 1. The amount actually spent on direct labor could differ from that was budgeted in the planning budget:

The difference can be because of following reasons:

  • The activity level or total production is different than budgeted
  • The actual labor rate is different than budgeted
  • The actual labor hour used is different than the budgeted due to higher or lower labor efficiency

. 2. assumption implicitly made about cost behavior when all of the items in a budget are adjusted in proportion to a change in activity:

The assumptionimplcitely made is that there is no fixed cost. All costs are variable and varies directly with the level of activity.

. 3. why the spending variance takes the difference between the Flexible budget and Actual results instead of Planning budget and Actual results:

The variable costs like materials , direct labor etc vary directly with the level of activity. If the actual level of activity is higher than the planning budgeted level of activity, the actual variable costs will be higher, even though budgeted standards of material price and quantity or labor rate and efficiencies are achieved. But the variances when compared to planning budget will show unfavourable variance.

Similarly if the level of activity is lower than the planning budget, the variance will be favourable without any improvement in labor efficiency or rate and without favourable material price or quantity.

Thus, if spending variances are reported based on difference between actual and planning budget, the variance report will not give correct information .

Hence a flexible budget is prepared based on actual level of activity and the spending variances are reported based on difference between actual cost and flexible budget.

For example:

Material cost as per planning budget =$10,000

Activity level as per planning budget =1000 units of production

Budgeted material cost per unit=10000/1000=$10

If the actual activity level or production is 1200 unit

Actual material cost=$11,400

If we report variances based on planning budget, it will show (11400-10000)=$1,400 Unfavourable variance since the actual cost is higher than the planning budget.

But the actual material cost per unit was $(11400/1200)= $       9.50

Hence , the correct variance should be favourable

The correct information can be obtained if the actual cost is compared with the cost as per flexible budget.

Material cost per unit as per planning budget=$10

Material cost as per flexible budget =$10*1200=$12000

Actual cost =$11400

Material cost variance=(12000-11400)=$600 (Favourable)


Related Solutions

The manufacturing overhead budget at Franklyn Corporation is based on budgeted direct labor-hours. The direct labor...
The manufacturing overhead budget at Franklyn Corporation is based on budgeted direct labor-hours. The direct labor budget indicates that 2,600 direct labor-hours will be required in January. The variable overhead rate is $7 per direct labor-hour. The company's budgeted fixed manufacturing overhead is $43,100 per month, which includes depreciation of $3,660. All other fixed manufacturing overhead costs represent current cash flows. The January cash disbursements for manufacturing overhead on the manufacturing overhead budget should be: Multiple Choice $61,300 $18,200 $57,640...
At the beginning of the period, the Assembly Department budgeted direct labor of $110,000, direct materials...
At the beginning of the period, the Assembly Department budgeted direct labor of $110,000, direct materials of $170,000, and fixed factory overhead of $28,000 for 8,000 hours of production. The department actually completed 10,000 hours of production. What is the appropriate total budget for the department, assuming it uses flexible budgeting? a. $288,000 b. $305,000 c. $350,000 d. $378,000 Budgeted sales for the month are a. $3,180,000 b. $5,820,000 c. $1,800,000 d. $8,500,000 The dollar amount of  Material C used in...
At the beginning of the period, the Cutting Department budgeted direct labor of $132,000, direct materials...
At the beginning of the period, the Cutting Department budgeted direct labor of $132,000, direct materials of $152,000 and fixed factory overhead of $10,300 for 7,400 hours of production. The department actually completed 10,700 hours of production. What is the appropriate total budget for the department, assuming it uses flexible budgeting? Round hourly rates to two decimal places. Round interim calculations to two decimal places. Round your final answer to the nearest dollar. a.$298,893 b.$294,300 c.$420,966 d.$425,542 If $501,000 of...
What was the amount of Direct Materials and Direct labor used in May?
Woodcarving company incurred the following costs during May : Conversion cost $ 479,500 Prime cost $ 406250 Manufacturing overhead $321500
What is the total amount to be budgeted in pounds for direct materials to be purchased...
What is the total amount to be budgeted in pounds for direct materials to be purchased for the month? 38,280 37,680 38,880 40,200
Direct Materials, Direct Labor, and Reports budgeted and actual costs for variable and fixed factory overhead...
Direct Materials, Direct Labor, and Reports budgeted and actual costs for variable and fixed factory overhead along with the related controllable and volume variances.Factory Overhead Cost Variance Analysis Mackinaw Inc. processes a base chemical into plastic. A detailed estimate of what a product should cost.Standard costs and actual costs for direct materials, direct labor, and factory overhead incurred for the manufacture of 7,200 units of product were as follows: Standard Costs Actual Costs Direct materials 9,400 lb. at $5.20 9,300...
Direct Materials and Direct Labor Variances At the beginning of June, Bezco Toy Company budgeted 15,000...
Direct Materials and Direct Labor Variances At the beginning of June, Bezco Toy Company budgeted 15,000 toy action figures to be manufactured in June at standard direct materials and direct labor costs as follows: Direct materials $15,750 Direct labor 12,600 Total $28,350 The standard materials price is $0.7 per pound. The standard direct labor rate is $14 per hour. At the end of June, the actual direct materials and direct labor costs were as follows: Actual direct materials $14,600 Actual...
Direct Materials and Direct Labor Variances At the beginning of June, Kimber Toy Company budgeted 22,000...
Direct Materials and Direct Labor Variances At the beginning of June, Kimber Toy Company budgeted 22,000 toy action figures to be manufactured in June at standard direct materials and direct labor costs as follows: Direct materials $46,200 Direct labor 23,100 Total $69,300 The standard materials price is $0.60 per pound. The standard direct labor rate is $15.00 per hour. At the end of June, the actual direct materials and direct labor costs were as follows: Actual direct materials $43,300 Actual...
Direct Materials and Direct Labor Variances At the beginning of June, Kimber Toy Company budgeted 11,000...
Direct Materials and Direct Labor Variances At the beginning of June, Kimber Toy Company budgeted 11,000 toy action figures to be manufactured in June at standard direct materials and direct labor costs as follows: Direct materials $11,550 Direct labor 6,600 Total $18,150 The standard materials price is $0.70 per pound. The standard direct labor rate is $10.00 per hour. At the end of June, the actual direct materials and direct labor costs were as follows: Actual direct materials $10,700 Actual...
1. At the beginning of the period, the Fabricating Department budgeted direct labor of $85,100 and...
1. At the beginning of the period, the Fabricating Department budgeted direct labor of $85,100 and equipment depreciation of $27,000 for 3,700 hours of production. The department actually completed 4,900 hours of production. Determine the budget for the department, assuming that it uses flexible budgeting. $ 2. Pasadena Candle Inc. projected sales of 53,000 candles for January. The estimated January 1 inventory is 3,700 units, and the desired January 31 inventory is 6,000 units. Prepare a production budget report in...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT