In: Accounting
ABC, Inc. purchased for $3,800,000 a mine estimated to contain 2.5 million tons of ore. When the ore is completely extracted, it was expected that the land would be worth $200,000. A building and equipment costing $1,800,000 were constructed on the mine site, and they will be completely used up and have no salvage value when the ore is exhausted. During the first year, 750,000 tons of ore were mined, and $300,000 was spent for labor and other operating costs.
Compute the total cost per ton of ore mined in the first year, by completing the following schedule:
Item |
Base |
Tons |
Per Ton |
Cost of mine | 3,800,000 | ||
Total Ore in tonnes | 2,500,000 | ||
Scrap value | 200,000 | ||
Building and equip | 1,800,000 | ||
Output year 1 | 750,000 | ||
Labour and operating cost | 300,000 | ||
Mine cost / Ton | 1.440 | ||
Build and equip /Ton | 0.720 | ||
Labour/Ton | 2.50 | ||
Item | Base | Tons | Per Ton |
Mine cost / Ton | 3,600,000.000 | 2,500,000 | 1.44 |
Build and equip /Ton | 1,800,000.000 | 2,500,000 | 0.72 |
Labour/Ton | 300,000.000 | 750,000 | 0.4 |
Total cost per ton | 2.56 | ||