Question

In: Finance

The current WACC is 16% and you calculated that a newly proposed project that is of...

The current WACC is 16% and you calculated that a newly proposed project that is of similar risk to an average project the firm undertakes (with an upfront investment in Year 0 followed by cash inflows in subsequent years) has an NPV of $266,000. The IRR of this project is:

-16%

-lower than 16%

-higher than 16%

Solutions

Expert Solution

Hello there,

Let us first understand the significance of the terms WACC and IRR.

Weighted Average Cost of Capital ("WACC") represent the average after tax cost of company 's source of capital. Source of capital includes here prefered stock, debts, common stock, bonds and other long term debts. The WACC represent the average rate at which the company's capital is arranged or how much amount of interest is paid on capital financed by the company.

Internal Rate of Return ("IRR"), represent the discount rate at which the Net Present Value ("NPV") of all cash flows in capital budgeting equals to zero.

Therefore it is required to be understood that where the WACC rate is higher than IRR, the preject need not to be accepted as, the borrowing cost is more than the rate of return and vice versa. That is the relationship between IRR and WACC is that if the NPV is more than 0, than IRR is higher than WACC and vice versa.

in the given case, since the WACC is 16% and NPV of the project is $266,000 it means that IRR is much more than WACC, thats why NPV is higher than 0.

Therefore in the given case, the IRR rate is higher than 16%.


Related Solutions

WACC should be calculated based on:
WACC should be calculated based on:
If you earn the WACC on a project, (IRR = WACC) or NPV = 0, what...
If you earn the WACC on a project, (IRR = WACC) or NPV = 0, what have you accomplished for your shareholders? 1A. A semiannual bond pays a 4.5 % coupon for the next 27 years. If investors want a 7.3% return, what are they willing to pay for the bond?
You have just calculated your firm's WACC. Your boss has asked you to do an NPV...
You have just calculated your firm's WACC. Your boss has asked you to do an NPV analysis of a potential new project, but you realise that the project is riskier than the firm's other projects. What should you do? Select one: a. Reject the project. b. Conduct the NPV analysis using the WACC as the discount rate. c. Conduct the NPV analysis using an appropriate discount rate, which will be higher than the firm's WACC. d. Conduct the NPV analysis...
As a newly appointed project manager, you are about to commence a cutting edge I.T. project...
As a newly appointed project manager, you are about to commence a cutting edge I.T. project within your organisation. It is the first time your organisation has undertaken a project like this in-house. How do you decide whether to use a predictive or adaptive approach? Briefly explain some of the characteristics common across all project life cycles. Which project lifecycle do you choose and why?
11. You are evaluating a proposed project for your company. The project is expected to generate...
11. You are evaluating a proposed project for your company. The project is expected to generate the following end-of-year cash flows: You have been told you should evaluate this project with an interest rate of 8.00%. A) What is the NPV? B) what is the Internal Rate of Return (IRR) C) Based on the information above: Your group leader has now told you that the risk of the project was understated before. As a result, she tells you to recalculate...
11. You are evaluating a proposed project for your company. The project is expected to generate...
11. You are evaluating a proposed project for your company. The project is expected to generate the following end-of-year cash flows: Please solve for below cash flows: 0------- -$3000 1--------- $300 2----------$300 3---------- $600 4---------- $600 5----------- $800 6----------- $800 7------------$800 8----------- $700 You have been told you should evaluate this project with an interest rate of 8.00%. A) What is the NPV? B) what is the Internal Rate of Return (IRR) C) Based on the information above: Your group...
The weighted average cost of capital (WACC) is calculated as the weighted average of cost of...
The weighted average cost of capital (WACC) is calculated as the weighted average of cost of component capital, including debt, preferred stock and common equity. In general, debt is less expensive than equity because it is less risky to the investors. Some managers may intend to increase the usage of debt, therefore increase the weight on debt (Wd). Do you think by increasing the weight on debt (Wd) will reduce the WACC infinitely? What are the benefits and costs of...
Project the Tax amount for the FY2020 using the tax % average calculated You are an...
Project the Tax amount for the FY2020 using the tax % average calculated You are an intern with an equity research organization. You have been given the task to project the values of certain income statement and balance sheet items for the next year (FY2020) for ABC Ltd (Your current time=0 is FY ending 2019). You have collected information about the historical income statement and balance sheet items. The historical information is provided in Table 1. Table 1 PARTICULARS (All...
the Weighted Average Cost of Capital (WACC) for a firm can be calculated or found through...
the Weighted Average Cost of Capital (WACC) for a firm can be calculated or found through research. Select two firms in the same industry. The industry may be that in which you currently work or it may be an industry in which you are interested. Calculate or find the WACC for the two firms. How do the WACCs compare? Are the WACCs what you would expect? What causes the differences between the two firms' WACCs?
You have been asked to calculate the WACC for a new project and you have decided...
You have been asked to calculate the WACC for a new project and you have decided to use the pure play method. You determine the capital structure is 75% equity and 25% debt (i.e., E/(D+E) = 0.75). To get the cost of debt for the project you plan to use an annual bond with the following characteristics: Price is $1,000, Coupon rate is 5%, face value is $1,000 and it has 10 years to maturity. To get the cost of...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT