Question

In: Operations Management

XYZ hotel uses approximately 200 towels daily. It operates 250 days a year. Assuming, lead time...

XYZ hotel uses approximately 200 towels daily. It operates 250 days a year. Assuming, lead time is normally distributed with a mean of 2 days and a standard deviation of 0.5 day. The management desires 90 percent service level. Annual carrying costs is $0.8 per towel, and ordering costs is $20. Given the production rate for the towel = 600 towels per day.

  1. Determine the optimal order quantity?
  2. Determine Safety Stock?
  3. The sales people have recently told the top management that they could expect $200 improvement in profit if the service level were increased to 99%. Is it worthwhile for XYZ hotel to make this change?

Solutions

Expert Solution

Solution:

Given,

D = 50000 Towels

S = $20

H = $0.8

L = 2 days

= 0.5 days

Hence,

a: EOQ

b: Safety Stock:

Z = 1.64 for 90% service level.

c: New service level

If we increase the service level to 99% the new Z will be,

Z = 2.58

Hence, new safety stick will be,

There will be no significant change in the total costs associated and hence this new service level is desired to ensure lower changes in stockouts and meeting more demand.


Related Solutions

Sam's Cat Hotel operates 52 weeks per? year, 5 days per? week, and uses a continuous...
Sam's Cat Hotel operates 52 weeks per? year, 5 days per? week, and uses a continuous review inventory system. It purchases kitty litter for ?$11.50 per bag. The following information is available about these bags. Refer to the standard normal table LOADING... for? z-values. Demand ?= 80 ?bags/week Order cost? = ?$58?/order Annual holding cost? = 30 percent of cost Desired ?cycle-service levelequals90 percent Lead time? = 2 ?week(s) ?(10 working? days) Standard deviation of weekly demand? = 16 bags...
Suppose that the annual demand will be 10000 units. The company operates 250 days/year, with two...
Suppose that the annual demand will be 10000 units. The company operates 250 days/year, with two 8-hour shifts a day. Management believes that a capacity cushion of 15% is the best. Average lot site is 50 units and the standard processing time is 0.5 hours. Each lot requires 0.2 hours standard set up time. How many production line would be needed to compensate the demand?(15pts)
Sam's Cat Hotel operates 52 weeks per year, 7 days per week
Sam's Cat Hotel operates 52 weeks per year, 7 days per week, and uses a continuous review inventory system. It purchases kitty litter for $10.75 per bag. The following information is available about these bags. Refer to the standard normal table for z-values. >Demand 95 bags/week >Order cost $56/order >Annual holding cost = 30 percent of cost >Desired cycle-service level = 99 percent >Lead time = 4 week(s) (28 working days) >Standard deviation of weekly demand = 20 bags >Current on-hand inventory is 325 bags, with no...
A Kathmandu based solar panel manufacturing company that operates 250 days per year requires 50,000 solar...
A Kathmandu based solar panel manufacturing company that operates 250 days per year requires 50,000 solar cells on an annual basis to assemble their panels. The annual holding cost per solar cell is Rs. 50. They are currently manufacturing the solar cells and have a production rate of 1000 cells per day. The cost to setup the machinery to begin a production batch costs the company Rs. 10,000 per setup. The company has discovered another solar cell manufacturer in China...
An office uses 1,000 photocopies per working day and there are 200 working days per year....
An office uses 1,000 photocopies per working day and there are 200 working days per year. Brand A copier costs $3,000 and will produce a total of one million copies before it wears out. Brand B’s copier costs $5,000 and will produce 2 million copies over its life. Maintenance and materials cost 3 cents per copy with either machine, and neither machine will have any salvage value. The required return is 10 percent per year. Which machine should the company...
One company operates 300 days per year. The economic order quantity (EOQ) is 250 units. Annual demand is 5000 units.
One company operates 300 days per year. The economic order quantity (EOQ) is 250 units. Annual demand is 5000 units. The expected time between orders will be: 15 days20 days1.2 days16.6 daysNone of the above
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT