In: Operations Management
Suppose that the annual demand will be 10000 units. The company operates 250 days/year, with two 8-hour shifts a day. Management believes that a capacity cushion of 15% is the best. Average lot site is 50 units and the standard processing time is 0.5 hours. Each lot requires 0.2 hours standard set up time. How many production line would be needed to compensate the demand?(15pts)
Total Demand = 10000 units
Batch Size = 50 units
No. of Batches = Total Demand / Batch size = 10000 / 50 = 200 batches
Set-up time per lot = 0.2 hours
Total Set-up time = No. of Batches * Set-up time per lot = 200 * 0.2 = 40 hours
Standard processing time per unit = 0.5 hours
Total processing time = Total Demand * Standard processing time per unit = 10000 * 0.5 = 5000
Total Time = 5000 + 40 = 5040 hours
Capacity cushion = 15%
Total time including capacity cushion = 5040 * 1.15 = 5,796 hours
Total Time available = Days per year * No. of shifts * Hours per shift = 250 * 2 * 8 = 4000
No. of processing lines = Total time including capacity cushion / Total Time available = 5796 / 4000 = 1.45 = 2 lines
Answer: 2 nos. production lines would be needed to compensate the demand.
-----------------------------------------------------------------------------------------------------------------------
In case of any doubt, please ask through the comment section before Upvote/downvote.
If you liked the answer, please give an upvote. This will be quite encouraging for me, thank-you!!!