In: Finance
Short Answer questions: Consider two mutually exclusive projects X and Y with identical initial outlays of $600,000 and useful lives of 5 years. Project X is expected to produce an after-tax cash flow of $180,000 each year. Project Y is expected to generate a single after-tax net cash flow of $1,015,000 in year 5. The discount rate is 14 percent.
Calculate Net Present Value for each project
Calculate IRR for each project
What should you decide based on the two projects
show work
Project X | ||||||
Discount rate | 14.000% | |||||
Year | 0 | 1 | 2 | 3 | 4 | 5 |
Cash flow stream | -600000 | 180000 | 180000 | 180000 | 180000 | 180000 |
Discounting factor | 1.000 | 1.140 | 1.300 | 1.482 | 1.689 | 1.925 |
Discounted cash flows project | -600000.000 | 157894.737 | 138504.155 | 121494.873 | 106574.450 | 93486.360 |
NPV = Sum of discounted cash flows | ||||||
NPV Project X = | 17954.57 | |||||
Where | ||||||
Discounting factor = | (1 + discount rate)^(Corresponding period in years) | |||||
Discounted Cashflow= | Cash flow stream/discounting factor |
Project Y | ||||||
Discount rate | 14.000% | |||||
Year | 0 | 1 | 2 | 3 | 4 | 5 |
Cash flow stream | -600000 | 0 | 0 | 0 | 0 | 1015000 |
Discounting factor | 1.000 | 1.140 | 1.300 | 1.482 | 1.689 | 1.925 |
Discounted cash flows project | -600000.000 | 0.000 | 0.000 | 0.000 | 0.000 | 527159.194 |
NPV = Sum of discounted cash flows | ||||||
NPV Project Y = | -72840.81 | |||||
Where | ||||||
Discounting factor = | (1 + discount rate)^(Corresponding period in years) | |||||
Discounted Cashflow= | Cash flow stream/discounting factor |
Project X | ||||||
IRR is the rate at which NPV =0 | ||||||
IRR | 15.24% | |||||
Year | 0 | 1 | 2 | 3 | 4 | 5 |
Cash flow stream | -600000.000 | 180000.000 | 180000.000 | 180000.000 | 180000.000 | 180000.000 |
Discounting factor | 1.000 | 1.152 | 1.328 | 1.530 | 1.764 | 2.032 |
Discounted cash flows project | -600000.000 | 156198.155 | 135543.686 | 117620.410 | 102067.172 | 88570.577 |
NPV = Sum of discounted cash flows | ||||||
NPV Project X = | 0.000 | |||||
Where | ||||||
Discounting factor = | (1 + discount rate)^(Corresponding period in years) | |||||
Discounted Cashflow= | Cash flow stream/discounting factor | |||||
IRR= | 15.24% |
Project Y | ||||||
IRR is the rate at which NPV =0 | ||||||
IRR | 11.09% | |||||
Year | 0 | 1 | 2 | 3 | 4 | 5 |
Cash flow stream | -600000.000 | 0.000 | 0.000 | 0.000 | 0.000 | 1015000.000 |
Discounting factor | 1.000 | 1.111 | 1.234 | 1.371 | 1.523 | 1.692 |
Discounted cash flows project | -600000.000 | 0.000 | 0.000 | 0.000 | 0.000 | 600000.000 |
NPV = Sum of discounted cash flows | ||||||
NPV Project Y = | 0.000 | |||||
Where | ||||||
Discounting factor = | (1 + discount rate)^(Corresponding period in years) | |||||
Discounted Cashflow= | Cash flow stream/discounting factor | |||||
IRR= | 11.09% |
Accept project X as it has positive NPV and IRR greater than discount rate