QualSupport Corporation manufactures seats for automobiles,
vans, trucks, and various recreational vehicles. The company has a
number of plants around
the world, including the Denver Cover Plant, which makes seat
covers. Ted Vosilo is the plant manager of the Denver Cover Plant
but also serves as the
regional production manager for the company. His budget as the
regional manager is charged to the Denver Cover Plant. Vosilo has
just heard that QualSupport has received a bid from an outside
vendor to supply the equivalent of the entire annual output of the
Denver Cover Plant for $35 million. Vosilo was astonished at the
low outside bid because the budget for the Denver Cover Plant’s
operating costs for the upcoming year was set at $52 million. If
this bid is accepted, the Denver Cover Plant will be
closed down.
The budget for Denver Cover’s operating costs for the coming year is presented below.
Denver Cover Plant
Annual Budget for Operating Costs
Materials $ 14,000,000
Labor:
Direct $ 13,100,000
Supervision 900,000
Indirect plant 4,000,000 18,000,000
Overhead:
Depreciation—equipment 3,200,000
Depreciation—building 7,000,000
Pension expense 5,000,000
Plant manager and staff 800,000
Corporate expenses* 4,000,000 20,000,000
Total budgeted costs $52,000,000
*Fixed corporate expenses allocated to plants and other operating units based on total budgeted wage and salary costs.
a. Due to Denver Cover’s commitment to using high-quality fabrics in all of its products, the Purchasing Department was instructed to place blanket purchase orders with major suppliers to ensure the receipt of sufficient materials for the coming year. If these orders are canceled as a consequence of the plant closing, termination charges would amount to 20% of the cost of direct materials.
b. Approximately 400 plant employees will lose their jobs if the plant is closed. This includes all of the direct laborers and supervisors as well as the plumbers, electricians, and other skilled workers classified as indirect plant workers. Some would be able to find new jobs while many others would have difficulty. All employees would have difficulty matching Denver Cover’s base pay of $18.80 per hour, which is the highest in the area. A clause in Denver Cover’s contract with the union may help some employees; the company must provide employment assistance to its former employees for 12 months after a plant closing. The estimated cost to administer this service would be $1.5 million for the year.
c. Some employees would probably choose early retirement because Qual Support has an excellent pension plan. In fact, $3 million of the annual pension expense would continue whether Denver Cover is open or not.
d. Vosilo and his staff would not be affected by the closing of Denver Cover. They would still be responsible for administering three other area plants.
e. If the Denver Cover Plant were closed, the company would realize about $3.2 million salvage value for the equipment and building. If the plant remains open, there are no plans to make any significant investments in new equipment or buildings. The old equipment is adequate and should last indefinitely.
Required:
2. QualSupport Corporation plans to prepare a financial analysis that will be used in deciding whether or not to close the Denver Cover Plant. Management has asked you to identify:
a. The annual budgeted costs that are relevant to the decision regarding closing the plant.
Materials $
Labor:
Direct $
Supervision
Indirect plant
Differential pension cost
Total annual relevant costs $
b. The annual budgeted costs that are not relevant to the decision regarding closing the plant.
Depreciation—equipment $
Total annual continuing costs $
c. Any nonrecurring costs that would arise due to the closing of the plant.
Termination charges on canceled material orders $
Total nonrecurring costs $
3. Looking at the data you have prepared in (2) above,
a. Calculate the Net advantage (disadvantage) of closing the plant.
First year Other Years
$
Salvage value of equipment and building 3,200,000
Net advantage (disadvantage) of closing the plant
b. Should the plant be closed?
Yes___________
No ___________