In: Finance
1. Investment Timing Option: Decision-Tree Analysis
The Karns Oil Company is deciding whether to drill for oil on a tract of land that the company owns. The company estimates the project would cost $5 million today. Karns estimates that, once drilled, the oil will generate positive net cash flows of $2.5 million a year at the end of each of the next 4 years. Although the company is fairly confident about its cash flow forecast, in 2 years it will have more information about the local geology and about the price of oil. Karns estimates that if it waits 2 years then the project would cost $7.5 million. Moreover, if it waits 2 years, then there is a 90% chance that the net cash flows would be $2.65 million a year for 4 years and a 10% chance that they would be $1.35 million a year for 4 years. Assume all cash flows are discounted at 10%.
a) If the company chooses to drill today, what is the project's
net present value? Negative value, if any, should be indicated by a
minus sign. Enter your answers in millions. For example, an answer
of $10,550,000 should be entered as 10.55. Do not round
intermediate calculations. Round your answer to two decimal
places.
$ million
b) Using decision-tree analysis, does it make sense to wait 2
years before deciding whether to drill?
-Select-Yes, it makes sense to wait two years to drill. OR No, it
makes sense to drill today.Item 2
2. Investment Timing Option: Option Analysis
The Karns Oil Company is deciding whether to drill for oil on a tract of land that the company owns. The company estimates the project would cost $8 million today. Karns estimates that, once drilled, the oil will generate positive net cash flows of $4 million a year at the end of each of the next 4 years. Although the company is fairly confident about its cash flow forecast, in 2 years it will have more information about the local geology and about the price of oil. Karns estimates that if it waits 2 years then the project would cost $9 million. Moreover, if it waits 2 years, then there is a 90% chance that the net cash flows would be $4.2 million a year for 4 years and a 10% chance that they would be $2.2 million a year for 4 years. Assume all cash flows are discounted at 10%. Use the Black-Scholes model to estimate the value of the option. Assume the variance of the project's rate of return is 0.111 and that the risk-free rate is 5%. Do not round intermediate calculations. Enter your answers in millions. For example, an answer of $10,550,000 should be entered as 10.55. Round your answer to three decimal places.
$ million
{I tried looking at other similar problems on here and replacing them with my numbers but i keep getting the wrong answer. Please help.}
1)
Project life: 4 Years
Discounted Rate : 10%
Initial outlay = $5 million
Net cash inflows = $2.5 million
a)
Year | Cash flows | PV of cash flows (in $ million) |
1 | 2.5/(1+0.1)^1 | 2.27 |
2 | 2.5/(1+0.1)^2 | 2.07 |
3 | 2.5/(1+0.1)^3 | 1.88 |
4 | 2.5/(1+0.1)^4 | 1.71 |
Total | 7.92 |
NPV = -5.00 + 7.92 = $2.92 millions
b)
10% Probability (Low) | ||
Year | Cash flows | PV of cash flows (in $ million) |
1 | 1.35/(1+0.1)^1 | 1.23 |
2 | 1.35/(1+0.1)^2 | 1.12 |
3 | 1.35/(1+0.1)^3 | 1.01 |
4 | 1.35/(1+0.1)^4 | 0.92 |
Total | 4.28 |
90% Probability (High) | ||
Year | Cash flows | PV of cash flows (in $ million) |
1 | 2.65/(1+0.1)^1 | 2.41 |
2 | 2.65/(1+0.1)^2 | 2.19 |
3 | 2.65/(1+0.1)^3 | 1.99 |
4 | 2.65/(1+0.1)^4 | 1.81 |
Total | 8.40 |
10% Probability Cash Flows Scenario = (-5.00+4,28) = -$0.72 million
90% Probability Cash Flows Scenario = (-5.00+8.40) = $3.40 million
Expected NPV = 0.1 x (-0.72) + 0.9 x (3.40) = $2.99 million
If the cash flows are only $1.35 million, the NPV of the project is negative and, thus, would not be undertaken. The value of the option of waiting for two years is evaluated as 0.1 x (0) + 0.9 x (3.4) = $3.06 million.
Since the NPV of waiting two years is more than going ahead and commencing the project today, hence it makes to wait two years to drill
2)
Option 1 (100% probability)
C0 = Cost in Year 0 = $8.00 million
CF = Cash Flow per year = $4.00 million for Years 1, 2, 3, 4
DR = Discount Rate = 10%
Year | Cash flows | PV of cash flows (in $ million) |
1 | 4.00/(1+0.1)^1 | 3.64 |
2 | 4.00/(1+0.1)^2 | 3.31 |
3 | 4.00/(1+0.1)^3 | 3.01 |
4 | 4.00/(1+0.1)^4 | 2.73 |
Total | 12.68 |
NPV = -8.00+12.68 = $4.68 million
Option 2 (wait 2 years with 90% Probability)
C0 = Cost in Year 0 = $9.00 million
CF = Cash Flow per year = $4.20 million for Years 1, 2, 3, 4
DR = Discount Rate = 10%
Year | Cash flows | PV of cash flows (in $ million) |
1 | 4.20/(1+0.1)^1 | 3.82 |
2 | 4.20/(1+0.1)^2 | 3.47 |
3 | 4.20/(1+0.1)^3 | 3.16 |
4 | 4.20/(1+0.1)^4 | 2.87 |
Total | 13.31 |
NPV = -9.00+13.31 = $4.31 millions and with 90% probability the revised NPV is $3.88 million
Option 2 (wait 2 years with 10% probability)
C0 = Cost in Year 0 = $9.00 million
CF = Cash Flow per year = $2.20 million for Years 1, 2, 3, 4
DR = Discount Rate = 10%
Year | Cash flows | PV of cash flows (in million) |
1 | 2.20/(1+0.1)^1 | 2.00 |
2 | 2.20/(1+0.1)^2 | 1.82 |
3 | 2.20/(1+0.1)^3 | 1.65 |
4 | 2.20/(1+0.1)^4 | 1.50 |
Total | 6.97 |
NPV = -9.00+6.97 = -$2.03 millions and with 10% probability the revised NPV is -$0.20 million
Option 2 NPV = $3.88 - $0.20 = $3.68 million
Black-Scholes Model:
Spot Price = Option 1 = $4.68
Strike Price = Option 2 = $3.68
t = Time to Expiration = 2 years between Option 1 and Option 2
v = Volatility = Variance of the project's rate of return = 11.10%
r = Risk Free Interest Rate = 5%
Use the Black-Sholes caculator at https://goodcalculators.com/black-scholes-calculator/
Call Price = Value of the Option = $1.35 million