Question

In: Statistics and Probability

If a firm uses a budgeting program for its projects, is an activity budget not needed?...

If a firm uses a budgeting program for its projects, is an activity budget not needed? If it is, then of what value is the program budget?

Solutions

Expert Solution

Activity budgeting is required to budget the project on the basis of task or activity.

Program budgeting is required to aggregate the income or expenditure at the project level.

The primary objective of program budgeting/top-down budgeting is to provide accurate aggregate budget as budget at individual level might not be accurate.

Budgeting is a very crucial part of any project management. Before the project is kicked off, a project sponsor and the financial support have to be clearly identified. A project can follow any methodology of implementation like waterfall or agile but budgeting is equally vital in both the methodologies. There are two major ways in which a project is budgeted. They are:
• Top Down Approach
• Bottom Up Approach

In the top down approach, the higher management develops a budget which is divided internally across various domains in the project. There is a fixed budget which has to be followed and the activities and improvements should have high ROI. Every activity which is being designed such as change of application system, consultant onboarding or outsourcing the work have to be taken considering the financial constraints. In case, the project requirements require pricing then the project budget is changed and increased. In the bottom up approach, every activity within the project and its associated costing are calculated and the summation of the same is considered as the project cost. It still has to be within the defined limits that the project sponsor provides. One major difference between both the approaches are the involvement of project sponsors and the project managers in the financial decision making. In the top down approach, the project managers do not have an active saying in the project budgeting while in bottom up approach the do.

If in case, the program uses a top down approach, the project sponsors would already have a ballpark figure identified for the project along with an additional buffer in case the costing is more than the forecasted prices. Typically, in most multinational companies, a budget is approved in a top down approach when the program manager presents the idea for kick starting the project. Once the project starts, the first activity for the project management team is to identify the actual costs that are involved in the project. All the project leads and managers would have to detail out the plans and give an approximate project estimate to the higher management. The costs are then compared with the ROI they provide. If the justification provided by the Project teams are valid, then projects budget is increased. Else, project sponsor would ask the team to reconsider the approach and complete the deployment within the fixed budgets.


Related Solutions

If a firm uses its WACC as the discount rate for all of the projects it...
If a firm uses its WACC as the discount rate for all of the projects it undertakes then the firm will tend to: I. reject some positive net present value projects. II. accept some negative net present value projects. III. favor high risk projects over low risk projects. IV. increase its overall level of risk over time. A. I and III only B. III and IV only C. I, II, and III only D. I, II, and IV only E....
Determine the budget for the department, assuming that it uses flexible budgeting.
At the beginning of the period, the Assembly Department budgeted direct labor of $120,000 and property tax of $16,000 for 5,000 hours of production. The department actually completed 5,600 hours of production. Determine the budget for the department, assuming that it uses flexible budgeting.
A firm is evaluating two projects for this year’s capital budget. Its WACC is 14%. Project...
A firm is evaluating two projects for this year’s capital budget. Its WACC is 14%. Project A costs $6,000 and its expected cash inflows would be $2,000 per year for 5 years. Project B costs $18,000 and its expected cash inflows would be $5,600 per year for 5 years. Calculate NPV and IRR for each project. Refer to problem 7. Calculate the MIRR and payback for each project. Refer to Problem 7. Calculate the discounted payback for each project. Refer...
A firm is evaluating two projects for this year’s capital budget. Its WACC is 14%. Project...
A firm is evaluating two projects for this year’s capital budget. Its WACC is 14%. Project A costs $6,000 and its expected cash inflows would be $2,000 per year for 5 years. Project B costs $18,000 and its expected cash inflows would be $5,600 per year for 5 years. Calculate NPV and IRR for each project. Refer to problem 7. Calculate the MIRR and payback for each project. Refer to Problem 7. Calculate the discounted payback for each project. Refer...
In capital budgeting: a. ​ If a firm accepts projects without regard for risk, then the...
In capital budgeting: a. ​ If a firm accepts projects without regard for risk, then the company can change its overall risk profile firm as perceived by investors. b. ​ Projects are thought to be incremental to the normal business of the firm. c. ​All of the above. d. ​ Risk is important and should be included in the analysis but often isn’t.
Activity-Based Flexible Budgeting Foy Company has a welding activity and wants to develop a flexible budget...
Activity-Based Flexible Budgeting Foy Company has a welding activity and wants to develop a flexible budget formula for the activity. The following resources are used by the activity: • Four welding units, with a lease cost of $15,000 per year per unit • Six welding employees each paid a salary of $60,000 per year (A total of 9,000 welding hours are supplied by the six workers.) • Welding supplies: $300 per job • Welding hours: 3 hours used per job...
"When a firm chooses to increases its capital budget, the less profitable projects it would choose...
"When a firm chooses to increases its capital budget, the less profitable projects it would choose rather than the ones picked out initially. "How do we rank projects; what are the models we use to decide which projects to initially choose? If the goal of management is to maximize shareholder wealth, how can a corporation excuse look at anything other than the bottom line?
which among these is plausible: 1. Zero based budgeting 2. Activity based budgeting 3. Rolling budget.
which among these is plausible: 1. Zero based budgeting 2. Activity based budgeting 3. Rolling budget.
Budget Variance Analysis Hertzler Corporation uses customers served as its measure of activity. During November, the...
Budget Variance Analysis Hertzler Corporation uses customers served as its measure of activity. During November, the company budgeted for 23,000 customers, but actually served 25,000 customers. The company uses the following revenue and cost formulas in its budgeting, where q is the number of customers served: Revenue: $7.25q Wages and salaries: $30,500 + $2.30q Supplies: $0.80q Insurance: $6,200 Miscellaneous: $8,750 + $0.30q The company reported the following actual results for November: Revenue $ 185,000 Wages $ 95,000 Supplies $ 19,500...
Activity Flexible Budgeting, Performance Report, Volume Variance Novo, Inc., wants to develop an activity flexible budget...
Activity Flexible Budgeting, Performance Report, Volume Variance Novo, Inc., wants to develop an activity flexible budget for the activity of moving materials. Novo uses eight forklifts to move materials from receiving to stores. The forklifts are also used to move materials from stores to the production area. The forklifts are obtained through an operating lease that costs $18,000 per year per forklift. Novo employs 25 forklift operators who receive an average salary of $50,000 per year, including benefits. Each move...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT