In: Finance
A firm is evaluating two projects for this year’s capital budget. Its WACC is 14%. Project A costs $6,000 and its expected cash inflows would be $2,000 per year for 5 years. Project B costs $18,000 and its expected cash inflows would be $5,600 per year for 5 years. Calculate NPV and IRR for each project.
Refer to problem 7. Calculate the MIRR and payback for each project.
Refer to Problem 7. Calculate the discounted payback for each project.
Refer to Problem 7. If the projects were mutually exclusive, which one would you recommend? If the projects were independent, which one(s) would you recommend? Explain.
PROJECT A:
NPV = Present value of cash inflows - present value of cash outflows
NPV = -6000 + 2000 / ( 1 + 0.14)1 + 2000 / ( 1 + 0.14)2 + 2000 / ( 1 + 0.14)3 + 2000 / ( 1 + 0.14)4 + 2000 / ( 1 + 0.14)5
NPV = -6000 + 1754.386 + 1538.935 + 1349.943 + 1184.161 + 1038.737
NPV = $866.162
IRR is the rate of return that makes NPV equal to 0
NPV = -6000 + 2000 / ( 1 + R)1 + 2000 / ( 1 + R)2 + 2000 / ( 1 + R)3 + 2000 / ( 1 + R)4 + 2000 / ( 1 + R)5
Using trial and error method, i.e, after trying various values for R, let try R as 19.86
NPV = -6000 + 2000 / ( 1 + 0.1986)1 + 2000 / ( 1 + 0.1986)2 + 2000 / ( 1 + 0.1986)3 + 2000 / ( 1 + 0.1986)4 + 2000 / ( 1 + 0.1986)5
NPV = 0
Therefore IRR is 19.86%
Future value of year 1 cash flow = 2000 ( 1 + 0.14)4 = 3,377.92
Future value of year 2 cash flow = 2000 ( 1 + 0.14)3 = 2,963.088
Future value of year 3 cash flow = 2000 ( 1 + 0.14)2 = 2,599.2
Future value of year 4 cash flow = 2000 ( 1 + 0.14)1 = 2,280
Future value of year 5 cash flow = 2000 ( 1 + 0.14)0 = 2000
Total future value = 2000 + 2,280 + 2,599.2 + 2,963.088 + 3,377.92 = 13,220.208
MIRR = ( ?13,220.208 / 6000)1/5 - 1
MIRR = 1.1712 - 1
MIRR = 0.1712 or 17.12%
Payback period = 6000 / 2000
Payback period = 3 years
Cumulative cash flow for year 0 = -6000
Cumulative cash flow for year 1 = -6000 + 1754.386 = -4,245.614
Cumulative cash flow for year 2 = -4,245.614 + 1538.935 = -2,706.679
Cumulative cash flow for year 3 = -2,706.679 + 1349.943 = -1,356.736
Cumulative cash flow for year 4 = -1,356.736 + 1184.161 = -172.575
Cumulative cash flow for year 5 = -172.575 + 1038.737 = 866.162
172.575 / 1038.737 = 0.166
Discounted payback period = 4 + 0.166 = 4.166 years
PROJECT B:
NPV = Present value of cash inflows - present value of cash outflows
NPV = -18000 + 5600 / ( 1 + 0.14)1 + 5600 / ( 1 + 0.14)2 + 5600 / ( 1 + 0.14)3 + 5600 / ( 1 + 0.14)4 + 5600 / ( 1 + 0.14)5
NPV = -6000 + 4912.281 + 4309.018 + 3779.84 + 3315.65 + 2908.465
NPV = $1225.254
IRR is the rate of return that makes NPV equal to 0
NPV = -18000 + 5600 / ( 1 + R)1 + 5600 / ( 1 + R)2 + 5600 / ( 1 + R)3 + 5600 / ( 1 + R)4 + 5600 / ( 1 + R)5
Using trial and error method, i.e, after trying various values for R, let try R as 16.8
NPV = -18000 + 5600 / ( 1 + 0.168)1 + 5600 / ( 1 + 0.168)2 + 5600 / ( 1 + 0.168)3 + 5600 / ( 1 + 0.168)4 + 5600 / ( 1 + 0.168)5
NPV = 0
Therefore IRR is 16.8%
Future value of year 1 cash flow = 5600 ( 1 + 0.14)4 = 9,458.177
Future value of year 2 cash flow = 5600 ( 1 + 0.14)3 = 8,296.646
Future value of year 3 cash flow = 5600 ( 1 + 0.14)2 = 7,277.76
Future value of year 4 cash flow = 5600 ( 1 + 0.14)1 = 6,384
Future value of year 5 cash flow = 5600 ( 1 + 0.14)0 = 5600
Total future value = 5600 + 6,384 + 7,277.76 + 8,296.646 + 9,458.177 = 37,016.583
MIRR = ( ?37,016.583 / 18000)1/5 - 1
MIRR = 1.1551 - 1
MIRR = 0.1551 or 15.51%
Payback period = 18000 / 5600
Payback period = 3.21 years
Cumulative cash flow for year 0 = -18000
Cumulative cash flow for year 1 = -18000 + 4912.281 = -13,087.719
Cumulative cash flow for year 2 = -13,087.719 + 4309.018 = -8,778.539
Cumulative cash flow for year 3 = -8,778.539 + 3779.84 = -4,998.699
Cumulative cash flow for year 4 = -4,998.699 + 3315.65 = -1,683.049
Cumulative cash flow for year 5 = -1,683.049 + 2908.465 = 1,225.416
1,683.049 / 2908.465 = 0.579
Discounted payback period = 4 + 0.579 = 4.579 years
If the projects were mutually exclusive, we always go by the NPV rule. Project B has a higher NPV, therefore project B should be accepted.
If the projects were independent, both projects should be accepted as both projects has positive NPV, IRR and MIRR greater tha cost of capital.