Question

In: Accounting

Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,750,000 in 2018...

Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,750,000 in 2018 for the mining site and spent an additional $750,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately four years, the company is required to restore the land to its original condition, including repaving of roads and replacing a greenbelt. The company has provided the following three cash flow possibilities for the restoration costs (FV of $1, PV of $1, FVA of $1, PVA of $1, FVAD of $1 and PVAD of $1) (Use appropriate factor(s) from the tables provided.):

                 Cash outflow Probability

1                450 000               15%

2                  550 000         45%

3              750 000                      40%

To aid extraction, Jackpot purchased some new equipment on July 1, 2018, for $150,000. After the copper is removed from this mine, the equipment will be sold for an estimated residual amount of $35,000. There will be no residual value for the copper mine. The credit-adjusted risk-free rate of interest is 12%.

The company expects to extract 11.5 million pounds of copper from the mine. Actual production was 3.1 million pounds in 2018 and 4.5 million pounds in 2019.

Required:

1. Compute depletion and depreciation on the mine and mining equipment for 2018 and 2019. The units-of-production method is used to calculate depreciation. (The expected format for rounding is presented in the appropriate rows of the table. Round your final answers to nearest whole dollar.)

Restoration costs

Cash outflow

probability

Probable restoration cost

Possibility 1

450 000

15%

67500

Possibility 2

550 000

45%

247500

Possibility 3

750 000

40%

300000

615 000

PV of 1$

n=

4

i=

12%

Present value of probable restoration costs                                       390 845

Mining site

1 750 000

Development costs

750 000

Restoration costs

390 845

  Total                                                              2 890 845


Depletion per pound

2018

2019

Depletion per Pound

?

0

Pounds extracted

?

?

Depletion expense

?

?


Depreciation expense (mining equipment)

2018

2019

Depreciation per pound

?

0

Pounds extracted

?

?

Depreciation expense

?

?

Solutions

Expert Solution

2018 2019
Depletion per pound                       0.25              0.25
Pounds extracted             3,100,000    4,500,000
Depletion expense                779,271    1,131,200
Mining equipment
2018 2019
Depreciation per Pound                       0.01              0.01
Pounds extracted             3,100,000    4,500,000
Depreciation Expesnes                   31,000          45,000

Workings:

Cost of Mining Site            2,890,845
Expected extraction          11,500,000
Depletion per pound                       0.25
Cost of Mining Equipment                150,000
Salvage Value                  35,000
Depreciable Value                115,000
Expected extraction          11,500,000
Depreciation per Pound                       0.01


Dear Student,

Best effort has been made to give quality and correct answer. But if you find any issues please comment your concern. I will definitely resolve your query.

Also please give your positive rating.


Related Solutions

Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,250,000 in 2018...
Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,250,000 in 2018 for the mining site and spent an additional $650,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately 4 years, the company is required to restore the land to its original condition, including repaving of roads and replacing a greenbelt. The company has provided the following three cash flow possibilities for the restoration costs: (FV of $1,...
Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,650,000 in 2018...
Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,650,000 in 2018 for the mining site and spent an additional $730,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately 4 years, the company is required to restore the land to its original condition, including repaving of roads and replacing a greenbelt. The company has provided the following three cash flow possibilities for the restoration costs: (FV of $1,...
Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,850,000 in 2018...
Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,850,000 in 2018 for the mining site and spent an additional $770,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately 4 years, the company is required to restore the land to its original condition, including repaving of roads and replacing a greenbelt. The company has provided the following three cash flow possibilities for the restoration costs: (FV of $1,...
Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,500,000 in 2018...
Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,500,000 in 2018 for the mining site and spent an additional $700,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately 4 years, the company is required to restore the land to its original condition, including repaving of roads and replacing a greenbelt. The company has provided the following three cash flow possibilities for the restoration costs: (FV of $1,...
Jackpot Mining Company operates a copper mine in central Montana. The company paid $2,000,000 in 2018...
Jackpot Mining Company operates a copper mine in central Montana. The company paid $2,000,000 in 2018 for the mining site and spent an additional $800,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately four years, the company is required to restore the land to its original condition, including repaving of roads and replacing a greenbelt. The company has provided the following three cash flow possibilities for the restoration costs (FV of $1,...
   Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,650,000 in...
   Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,650,000 in 2021 for the mining site and spent an additional $730,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately four years, the company is required to restore the land to its original condition, including repaving of roads and replacing a greenbelt. The company has provided the following three cash flow possibilities for the restoration costs: (FV of...
Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,250,000 in 2021...
Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,250,000 in 2021 for the mining site and spent an additional $650,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately four years, the company is required to restore the land to its original condition, including repaving of roads and replacing a greenbelt. The company has provided the following three cash flow possibilities for the restoration costs: (FV of $1,...
Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,700,000 in 2021...
Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,700,000 in 2021 for the mining site and spent an additional $740,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately four years, the company is required to restore the land to its original condition, including repaving of roads and replacing a greenbelt. The company has provided the following three cash flow possibilities for the restoration costs: (FV of $1,...
Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,250,000 in 2021...
Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,250,000 in 2021 for the mining site and spent an additional $650,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately four years, the company is required to restore the land to its original condition, including repaving of roads and replacing a greenbelt. The company has provided the following three cash flow possibilities for the restoration costs: (FV of $1,...
ackpot Mining Company operates a copper mine in central Montana. The company paid $1,550,000 in 2018...
ackpot Mining Company operates a copper mine in central Montana. The company paid $1,550,000 in 2018 for the mining site and spent an additional $710,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately four years, the company is required to restore the land to its original condition, including repaving of roads and replacing a greenbelt. The company has provided the following three cash flow possibilities for the restoration costs (FV of $1,...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT