In: Finance
Caradoc Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $430,000 is estimated to result in $170,000 in annual pre-tax cost savings. The press falls into Class 8 for CCA purposes (CCA rate of 20% per year), and it will have a salvage value at the end of the project of $57,000. The press also requires an initial investment in spare parts inventory of $40,000, along with an additional $5,100 in inventory for each succeeding year of the project. If the shop’s tax rate is 35% and its discount rate is 9%.
Calculate the NPV of this project. (Do not round your intermediate calculations. Round the final answer to 2 decimal places. Omit $ sign in your response.)
NPV $
Should the company buy and install the machine press?
Yes
No
Depreciation Schedule | |||
Year | Opening Balance | Depreciation | Closing Balance |
A | B | C = B*20% | D = B-C |
1 | 430000 | 86000 | 344000 |
2 | 344000 | 68800 | 275200 |
3 | 275200 | 55040 | 220160 |
4 | 220160 | 44032 | 176128 |
Calculation of NPV of the Project | |||||
Particulars | 0 | 1 | 2 | 3 | 4 |
Initial Investment | |||||
Cost of Equipment (A) | -430000 | ||||
Operating Cash Flows | |||||
Annual Pre tax cost savigs (B) | 170000 | 170000 | 170000 | 170000 | |
Depreciation (C ) | 86000 | 68800 | 55040 | 44032 | |
Profit Before Tax (D = B-C) | 84000 | 101200 | 114960 | 125968 | |
Tax @35% (E = D*35%) | 29400 | 35420 | 40236 | 44088.8 | |
Profit After Tax (F = D-E) | 54600 | 65780 | 74724 | 81879.2 | |
Add back Depreciation (G = C) | 86000 | 68800 | 55040 | 44032 | |
Net Operating Cash flows (H = F+G) | 140600 | 134580 | 129764 | 125911.2 | |
Working Capital Investment | |||||
Net Working Capital (I) | -40000 | -5100 | -5100 | -5100 | 55300 |
Terminal Value | |||||
Salvage Value (J) | 57000 | ||||
Unclaimed CCA (K) | 176128 | ||||
Loss on sale (L = J-K) | -119128 | ||||
Tax @35% (M = L*35%) | -41694.8 | ||||
After tax loss (N = L-M) | -77433.2 | ||||
Add back unclaimed CCA (O = K) | 176128 | ||||
Net Salvage Value (P = N+O) | 98694.8 | ||||
Total Cash Flows (Q = A+H+I+P) | -470000 | 135500 | 129480 | 124664 | 279906 |
Discount Factor @9% (R) 1/(1+9%)^n n=0,1,2,3,4 |
1 | 0.917431193 | 0.841679993 | 0.77218348 | 0.708425 |
Discounted Cash Flows (V = T*U) | -470000 | 124311.9266 | 108980.7255 | 96263.48136 | 198292.5 |
NPV of the Project | 57848.60062 | ||||
Therefore, NPV of the Project is $57,848.60 | |||||
Company should buy and install the machine press since the NPV is positive |