In: Finance
Project EvaluationDog Up! Franks is looking at a new sausage system with an installed cost of $375,000. This cost will be depreciated straight-line to zero over the project’s 5-year life, at the end of which the sausage system can be scrapped for $25,000. The sausage system will save the firm $95,000 per year in pretax operating costs, and the system requires an initial investment in net working capital of $15,000. If the tax rate is 24 percent and the discount rate is 10 percent, what is the NPV of this project? Chapter 6 question 8
INITIAL INVESTMENT: | |
Installed cost of new system | $ 3,75,000 |
Increase in NWC | $ 15,000 |
Initial cash outflow | $ 3,90,000 |
ANNUAL OCF: | |
Savings in operating costs | $ 95,000 |
Depreciation [375000/5] | $ 75,000 |
Incremental NOI | $ 20,000 |
Tax at 24% | $ 4,800 |
Incremental NOPAT | $ 15,200 |
Add: Depreciation | $ 75,000 |
Incremental OCF | $ 90,200 |
TERMINAL NON OPERATING CASH FLOWS: | |
After tax salvage value = 25000*(1-24%) = | $ 19,000 |
Release of NWC | $ 15,000 |
After tax terminal operating cash flow | $ 34,000 |
NPV: | |
PV of annual OCF = 90200*(1.1^5-1)/(0.1*1.1^5) = | $ 3,41,929 |
PV of terminal cash flow = 34000/1.1^5 = | $ 21,111 |
Total PV of cash inflows | $ 3,63,040 |
Less: Initial investment | $ 3,90,000 |
NPV | $ -26,960 |
The project should not be accepted as the NPV is negative. |