Question

In: Finance

Geary Machine Shop is considering a four-year project to improve its production efficiency. Buying a new...

Geary Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $768,000 is estimated to result in $256,000 in annual pretax cost savings. The press falls in the MACRS five-year class (MACRS Table), and it will have a salvage value at the end of the project of $112,000. The press also requires an initial investment in spare parts inventory of $32,000, along with an additional $4,800 in inventory for each succeeding year of the project.

  

Required :

If the shop's tax rate is 33 percent and its discount rate is 16 percent, what is the NPV for this project? (Do not round your intermediate calculations.)

Solutions

Expert Solution

0 1 2 3 4
Pretax cost savings $      2,56,000 $    2,56,000 $    2,56,000 $   2,56,000
Depreciation $      1,53,600 $    2,45,760 $    1,47,456 $       88,474
Incremental NOI $      1,02,400 $        10,240 $    1,08,544 $   1,67,526
Tax at 33% $         33,792 $          3,379 $        35,820 $       55,284
NOPAT $         68,608 $          6,861 $        72,724 $   1,12,243
Add: Depreciation $      1,53,600 $    2,45,760 $    1,47,456 $       88,474
Incremental OCF $      2,22,208 $    2,52,621 $    2,20,180 $   2,00,716
Capital expenditure $     7,68,000 $ -1,18,834 [See note below for after tax salvage value]
Change in NWC $         32,000 $            4,800 $          4,800 $          4,800 $     -46,400
FCF $   -8,00,000 $      2,17,408 $    2,47,821 $    2,15,380 $   3,65,951
PVIF at 16% 1 0.86207 0.74316 0.64066 0.55229
PV at 16% $   -8,00,000 $      1,87,421 $    1,84,171 $    1,37,985 $   2,02,111
NPV $       -88,312
After tax salvage value:
Salvage value at EOY 4 112000
Book value = 768000*17.28% = 132710
Loss on sale 20710
Tax shield on loss at 33% 6834
After tax salvage value = 112000+6834 = 118834

Related Solutions

Geary Machine Shop is considering a four-year project to improve its production efficiency. Buying a new...
Geary Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $1,132,800 is estimated to result in $377,600 in annual pretax cost savings. The press falls in the MACRS five-year class (MACRS Table), and it will have a salvage value at the end of the project of $165,200. The press also requires an initial investment in spare parts inventory of $47,200, along with an additional $7,080 in inventory for each succeeding year...
Geary Machine Shop is considering a four-year project to improve its production efficiency. Buying a new...
Geary Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $950,400 is estimated to result in $316,800 in annual pretax cost savings. The press falls in the MACRS five-year class (MACRS Table), and it will have a salvage value at the end of the project of $138,600. The press also requires an initial investment in spare parts inventory of $39,600, along with an additional $5,940 in inventory for each succeeding year...
Geary Machine Shop is considering a four-year project to improve its production efficiency. Buying a new...
Geary Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $566,400 is estimated to result in $188,800 in annual pretax cost savings. The press falls in the MACRS five-year class (MACRS Table), and it will have a salvage value at the end of the project of $82,600. The press also requires an initial investment in spare parts inventory of $23,600, along with an additional $3,540 in inventory for each succeeding year...
Geary Machine Shop is considering a four-year project to improve its production efficiency. Buying a new...
Geary Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $1,152,000 is estimated to result in $384,000 in annual pretax cost savings. The press falls in the MACRS five-year class (MACRS Table), and it will have a salvage value at the end of the project of $168,000. The press also requires an initial investment in spare parts inventory of $48,000, along with an additional $7,200 in inventory for each succeeding year...
Geary Machine Shop is considering a four-year project to improve its production efficiency. Buying a new...
Geary Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $969,600 is estimated to result in $323,200 in annual pretax cost savings. The press falls in the MACRS five-year class (MACRS Table), and it will have a salvage value at the end of the project of $141,400. The press also requires an initial investment in spare parts inventory of $40,400, along with an additional $6,060 in inventory for each succeeding year...
Geary Machine Shop is considering a four-year project to improve its production efficiency. Buying a new...
Geary Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $844,800 is estimated to result in $281,600 in annual pretax cost savings. The press falls in the MACRS five-year class (MACRS Table), and it will have a salvage value at the end of the project of $123,200. The press also requires an initial investment in spare parts inventory of $35,200, along with an additional $5,280 in inventory for each succeeding year...
Geary Machine Shop is considering a four-year project to improve its production efficiency. Buying a new...
Geary Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $547,200 is estimated to result in $182,400 in annual pretax cost savings. The press falls in the MACRS five-year class (MACRS Table), and it will have a salvage value at the end of the project of $79,800. The press also requires an initial investment in spare parts inventory of $22,800, along with an additional $3,420 in inventory for each succeeding year...
Geary Machine Shop is considering a four-year project to improve its production efficiency. Buying a new...
Geary Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $547,200 is estimated to result in $182,400 in annual pretax cost savings. The press falls in the MACRS five-year class (MACRS Table), and it will have a salvage value at the end of the project of $79,800. The press also requires an initial investment in spare parts inventory of $22,800, along with an additional $3,420 in inventory for each succeeding year...
Geary Machine Shop is considering a four-year project to improve its production efficiency. Buying a new...
Geary Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $1,094,400 is estimated to result in $364,800 in annual pretax cost savings. The press falls in the MACRS five-year class (MACRS Table), and it will have a salvage value at the end of the project of $159,600. The press also requires an initial investment in spare parts inventory of $45,600, along with an additional $6,840 in inventory for each succeeding year...
Geary Machine Shop is considering a four-year project to improve its production efficiency. Buying a new...
Geary Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $681,600 is estimated to result in $227,200 in annual pretax cost savings. The press falls in the MACRS five-year class (MACRS Table), and it will have a salvage value at the end of the project of $99,400. The press also requires an initial investment in spare parts inventory of $28,400, along with an additional $4,260 in inventory for each succeeding year...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT