In: Accounting
Fine Clothing Company produces Jackets from leather, fabric, and synthetic materials in a single production department. The basic product is a standard jacket made from leather and lined with fabric. Fine Clothing has a good reputation in the market because the standard jacket is a high-quality item that has been produced for many years. Last year, the company decided to expand its product line and produce specialty jackets for special orders. These jackets differ from the standard in that they vary in size, contain both leather and synthetic materials, and are imprinted with the buyer's logo (the standard jacket is simply imprinted with the Fine Clothing name in small letters). The decision to use some synthetic materials in the jacket was made to hold down the materials cost. To reduce the labor costs per unit, most of the cutting and stitching on the specialty jackets is done by automated machines, which are used to a much lesser degree in the production of the standard jackets. Because of these changes in the design and production of the specialty jackets, Fine Clothing management believed that they would cost less to produce than the standard jackets. However, because they are specialty items, they were priced slightly higher; standards are priced at $30 and specialty jackets at $32. After reviewing last month's results of operations, Fine Clothing's president became concerned about the profitability of the two product lines because the standard jacket showed a loss while the specialty jacket showed a greater profit margin than expected. The president is wondering whether the company should drop the standard jacket and focus entirely on specialty items. Units and cost data for last month's operations as reported to the president are as follows:
Units produced | 10,000.00 | 2,500.00 |
Direct materials | ||
Leather (1 sq. yd. x $15.00; 112 sq. yd. x $15.00) | 15 | 7.5 |
Fabric (1 sq. yd. x $5.00; 1 sq. yd. x $5.00) | 5 | 5 |
Synthetic | 5 | |
Total materials | 20 | 17.5 |
Direct labor (1/2 hr. x $12.00, 1/4 hr. x $12.00) | 6 | 3 |
Manufacturing overhead (1/2 hr. x $8.98; 1/4 hr. x $8.98) | 4.49 | 2.25 |
Cost per unit | 30.49 | 22.75 |
Factory overhead is applied on the basis of direct labor hours. The
rate of $8.98 per direct labor hour was calculated by dividing the
total overhead ($50,500) by the direct labor hours (5,625). As
shown in the table, the cost of a standard jacket is $0.49 higher
than its $30 sales price; the specialty jacket has a cost of only
$22.75, for a gross profit per unit of $9.25. The problem with
these costs is that they do not accurately reflect the activities
involved in manufacturing each product. Determining the costs using
ABC should provide better product costing data to help gauge the
actual profitability of each product line. The manufacturing
overhead costs must be analyzed to determine the activities driving
the costs. Assume that the following costs and cost drivers have
been identified:
• The Purchasing Department's cost is $6,000. The major activity
driving these costs is the number of purchase orders processed.
During the month, the Purchasing Department prepared the following
number of purchase orders for the materials indicated:
Leather
20
Fabric
30
Synthetic Material
50
• The cost of receiving and inspecting materials is $7,500. These
costs are driven by the number of deliveries. During the month, the
following number of deliveries were made:
Leather
30
Fabric
40
Synthetic Material
80
• Production line setup cost is $10,000. Setup activities involve
changing the machines to produce the different types of jackets.
Each setup for production of the standard jackets requires one
hour; each setup for specialty jackets requires two hours. Standard
jackets are produced in batches of 200, and specialty jackets are
produced in batches of 25. During the last month, there were 50
setups for the standard item and 100 setups for the specialty
item.
• The cost of inspecting finished goods is $8,000. All jackets are
inspected to ensure that quality standards are met. However, the
final inspection of standard jackets takes very little time because
the employees identify and correct quality problems as they do the
hand cutting and stitching. A survey of the personnel responsible
for inspecting the final products showed that 150 hours were spent
on standard jackets and 250 hours on specialty jackets during the
month.
• Equipment-related costs are $6,000. Equipment-related costs
include repairs, depreciation, and utilities. Management has
determined that a logical basis for assigning these costs to
products is machine hours. A standard jacket requires 1/2 hour of
machine time, and a specialty jacket requires two hours. Thus,
during the last month, 5,000 hours of machine time relate to the
standard line and 5,000 hours relate to the specialty line.
• Plant-related costs are $13,000. These costs include property
taxes, insurance, administration, and others. For the purpose of
determining average unit costs, they are to be assigned to products
using machine hours.
a. Using activity-based costing concepts, what overhead costs
should be assigned to the two products?
b. What is the unit cost of each product using activity-based
costing concepts?
c. Reevaluate the president's concern about the profitability of
the two product lines.
d. Discuss the merits of activity-based management as it relates to
Fine Clothing's ABC cost system. Please do not state the obvious.
Use this example to identify the merits and compare it with the
traditional system. How your decision would be affected in either
case