In: Accounting
Q14-Q18 are based on this case: XTi Co. gathered the following actual results for the current month: Actual Units produced 1,200 Direct materials purchased 6,400 lbs. @ $11 per lb for $70,400; and used 5,800 lbs. Direct labor cost (2,150 hours @$22 per hour) $47,300 Manufacturing overhead costs incurred: $19,350 Variable and $9,650 Fixed overhead. The Static original budgeted production was 1,000 units. The Input standards were: Std Quantity x Std Price per input =Std Cost per Output U Direct materials 5 lbs./Output unit x $10/lb. Direct labor 2 hrs./Output unit x $20/hr. Variable manufacturing overhead 2 Direct labor hrs x $8 per hr = $16 per unit Fixed mfg. overhead [Budget $10,000] 2 Direct labor hrs x $5 per hr = $10 per unit |
Q14. What is the direct materials quantity variance? ____
A. $4400U B. 2000F C. 6400U D. 5800U E. None of these.
Q15. What is the direct labor efficiency variance? _____
A. $5000F B. 700F C. 4300U D. 2000F E. None of these.
Q16. What is the fixed overhead production volume variance? _____
A. $200F B. 350F C. 200U D. 2000F E. None of these.
Q17. What is the variable overhead controllable variance? _____
A. 2,000F B. $150U C. 2150U D. 4300U E. None of these.
Q18. What is the direct materials price variance? ____
A. $2000F B. 5800U C. 4400U D. 6400 U E. None of these.
Q19. What is the total overhead controllable variance? _____
A. $150U B. 2,000F C. 2200F D. 4300U E. None of these.
Q 20. What is the direct labor rate variance? _____
A. $4,800U B. 4,000U C. 4,300U D. 2,400U E. None of these.
A) Material Usage Variance = Std Price*(Std Qty for actual output - Actual Qty)
10*(5lbs per unit*1200units - 5800lbs)
10*200
2000(F) as actual is lower than budgeted
B) Labour Efficiency = Std Rate * (Std hrs for actual output - Actual Hrs)
20 * (2hrs*1200units - 2150hrs )
20* 250hrs
5000(F) as std hrs are more than actual.
C)Fixed overhead production volume variance = Applied Fixed Overhead – Budgeted Fixed Overhead
Where applied fixed overhead rate is $10 per unit
$10*1200units - $10000
2000(F)
D)Variable overhead variance = Std Rate* Actual Output - Actual Overhead
$16*1200 - 19350
$150(U) as Std overhead is lower than actual overhead.
E) Direct materials price variance = Actual Qty * (Std price - Actual Price)
5800lbs * ($10-$11)
$5800(U) as std price is lower than actual price for direct material.
F)Direct labor rate variance = Actual Hrs * (Std rate - Actual Rate)
2150 hrs * (20 - 22)
$4300(U) as actual rate per hr is higher