In: Accounting
The following data for the Safety Company pertain to the production of 3,000 clay pigeons during July:
Standard variable-overhead cost was $5.00 per pound of clay.
The actual variable-overhead cost was $11,340.
Standard variable-overhead cost allowed for units produced was $12,000.
Variable-overhead efficiency variance was $340 unfavorable.
_____ is the variable-overhead rate variance.
Group of answer choices
$800 unfavorable
$1,000 favorable
$800 favorable
$560 unfavorable
Correct answer----------$1,000 Favorable
Working
| Variable Overhead Rate Variance | ||||||
| ( | Standard Rate | - | Actual Rate | ) | x | Actual pounds |
| ( | $ 5.00 | - | $ 4.59 | ) | x | 2468 |
| $ 1,000.00 | ||||||
| Variance | $ 1,000.00 | Favourable-F | ||||
Working to calculate actual rate
| Variable Overhead Efficiency Variance | ||||||
| ( | Standard pounds | - | Actual pounds | ) | x | Standard Rate |
| ( | 2400 | - | 2468 | ) | x | $ 5.00 |
| $ (340.00) | ||||||
| Variance | $ 340.00 | Unfavourable-U | ||||