Question

In: Accounting

Performance Report Based on Budgeted and Actual Levels of Production Bowling Company budgeted the following amounts:...

Performance Report Based on Budgeted and Actual Levels of Production

Bowling Company budgeted the following amounts:

Variable costs of production:
     Direct materials 3 pounds @ $0.60 per pound
     Direct labor 0.5 hr. @ $16.00 per hour
     VOH 0.5 hr. @ $2.20
FOH:
     Materials handling $6,200
     Depreciation $2,600

At the end of the year, Bowling had the following actual costs for production of 3,800 units:

Direct materials $6,800
Direct labor 30,500
VOH 4,200
FOH:
     Materials handling 6,300
     Depreciation $2,600

Required:

1. Calculate the budgeted amounts for each cost category listed above for the 4,000 budgeted units.
$

2. Prepare a performance report using a budget based on expected production of 4,000 units. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number and if there is no entries enter "0" then select for "Not applicable".

Bowling Company
Performance Report
Actual Budgeted Variance
Units produced
Direct materials $ $ $
Direct labor
Variable overhead
Fixed overhead:
Materials handling
Depreciation
Total $ $ $

3. Prepare a performance report using a budget based on the actual level of production of 3,800 units. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number and if there is no entries enter "0" then select for "Not applicable".

Bowling Company
Performance Report
Actual Budgeted Variance
Units produced
Direct materials $ $ $
Direct labor
Variable overhead
Fixed overhead:
Materials handling
Depreciation
Total $ $ $

Solutions

Expert Solution

1) Budgeted amounts for each cost category for 4,000 budgeted units.

Particulars Workings Budgeted Amount
Productions 4000 units
Variable Cost
Direct Materials 4000*3*0.60 7200
Direct labour 4000*0.5*16 32000
VOH 4000*0.5*2.2 4400
FOH
Materials handling 6200
Depreciation 2600

2)

Bowling Company

Performance Report

Actual Budgeted Variance
Units produced 3800 4000 -200
Direct material 6800 7200 -400  
Direct labour 30500 32000 -1500
Variable OH 4200 4400 -200
Fixed OH :
Materials Handling 6300 6200 100
Depreciation 2600 2600 0
Total 50400 52400 -2000

3)

Bowling Company

Performance Report

Actual Budgeted Variance
Units produced 3800 3800 0
Direct material 6800 3800*3*0.60 = 6840 -40  
Direct labour 30500 3800*0.5*16 = 30400 100
Variable OH 4200 3800*0.5*2.2 = 4180 20
Fixed OH :
Materials Handling 6300 6200 100
Depreciation 2600 2600 0
Total 50400 50220 180

Related Solutions

Performance Report Based on Budgeted and Actual Levels of Production Bowling Company budgeted the following amounts:...
Performance Report Based on Budgeted and Actual Levels of Production Bowling Company budgeted the following amounts: Variable costs of production:      Direct materials 3 pounds @ $0.60 per pound      Direct labor 0.5 hr. @ $16.00 per hour      VOH 0.5 hr. @ $2.20 FOH:      Materials handling $6,200      Depreciation $2,600 At the end of the year, Bowling had the following actual costs for production of 3,800 units: Direct materials $6,800 Direct labor 30,500 VOH 4,200 FOH:      Materials handling 6,300      Depreciation $2,600 Required: 1....
Performance Report Based on Budgeted and Actual Levels of Production Bowling Company budgeted the following amounts:...
Performance Report Based on Budgeted and Actual Levels of Production Bowling Company budgeted the following amounts: Variable costs of production:      Direct materials 3 pounds @ $0.60 per pound      Direct labor 0.5 hr. @ $16.00 per hour      VOH 0.5 hr. @ $2.20 FOH:      Materials handling $6,200      Depreciation $2,600 At the end of the year, Bowling had the following actual costs for production of 3,800 units: Direct materials $6,800 Direct labor 30,500 VOH 4,200 FOH:      Materials handling 6,300      Depreciation $2,600 Required: 1....
Performance Report Based on Budgeted and Actual Levels of Production Bowling Company budgeted the following amounts:...
Performance Report Based on Budgeted and Actual Levels of Production Bowling Company budgeted the following amounts: Variable costs of production:      Direct materials 3 pounds @ $0.60 per pound      Direct labor 0.5 hr. @ $16.00 per hour      VOH 0.5 hr. @ $2.20 FOH:      Materials handling $6,200      Depreciation $2,600 At the end of the year, Bowling had the following actual costs for production of 3,800 units: Direct materials $6,800 Direct labor 30,500 VOH 4,200 FOH:      Materials handling 6,300      Depreciation $2,600 Required: 1....
Performance Report Based on Budgeted and Actual Levels of Production Bowling Company budgeted the following amounts:...
Performance Report Based on Budgeted and Actual Levels of Production Bowling Company budgeted the following amounts: Variable costs of production:      Direct materials 3 pounds @ $0.60 per pound      Direct labor 0.5 hr. @ $16.00 per hour      VOH 0.5 hr. @ $2.20 FOH:      Materials handling $6,200      Depreciation $2,600 At the end of the year, Bowling had the following actual costs for production of 3,800 units: Direct materials $6,800 Direct labor 30,500 VOH 4,200 FOH:      Materials handling 6,300      Depreciation $2,600 Required: 1....
Flexible Budget with Different Levels of Production Bowling Company budgeted the following amounts: Variable costs of...
Flexible Budget with Different Levels of Production Bowling Company budgeted the following amounts: Variable costs of production:      Direct materials 3 pounds @ $0.60 per pound      Direct labor 0.5 hr. @ $16.00 per hour      VOH 0.5 hr. @ $2.20 FOH:      Materials handling $6,200      Depreciation $2,600 Required: Prepare a flexible budget for 2,500 units, 3,000 units, and 3,500 units. Bowling Company Flexible Budget 2,500 units 3,000 units 3,500 units Direct materials $ $ $ Direct labor Variable overhead Fixed overhead: Materials handling...
The following amounts were selected from the production report of Chandelier Limited: Actual units in production...
The following amounts were selected from the production report of Chandelier Limited: Actual units in production 42 000 Equivalent units (materials) 42 000 Equivalent units (conversion cost) 39 000 Cost per equivalent unit (materials) R1.10 Cost per equivalent unit (conversion cost) R0.90 Chandelier Limited uses the weighted average method in preparing its production reports. Chandelier Limited's total production cost to be accounted for is: (2) a. R81 300 b. R84 000 c. R89 100 d. R72 900
The following data is given for the Stringer Company: Budgeted production 954 units Actual production 1,030...
The following data is given for the Stringer Company: Budgeted production 954 units Actual production 1,030 units Materials: Standard price per ounce $1.92 Standard ounces per completed unit 12 Actual ounces purchased and used in production 12,731 Actual price paid for materials $26,099 Labor: Standard hourly labor rate $14.49 per hour Standard hours allowed per completed unit 4.8 Actual labor hours worked 5,304.5 Actual total labor costs $80,894 Overhead: Actual and budgeted fixed overhead $1,031,000 Standard variable overhead rate $25.00...
Flexible Budget for Various Levels of Production Budgeted amounts for the year: Materials 2 leather strips...
Flexible Budget for Various Levels of Production Budgeted amounts for the year: Materials 2 leather strips @ $7.00 Labor 1.5 hr. @ $18.00 VOH 1.5 hr. @ $1.20 FOH $6,800 Required: 1. Prepare a flexible budget for 3,500, 4,000, and 4,500 units. Flexible Budget Variable Cost per Unit 3,500 units 4,000 units 4,500 units Direct materials $ $ $ $ Direct labor Variable overhead Fixed overhead Total $ $ $ 2. CONCEPTUAL CONNECTION Calculate the unit cost at 3,500, 4,000,...
The following data are given for Harry Company: Budgeted production 1,056 units Actual production   900 units...
The following data are given for Harry Company: Budgeted production 1,056 units Actual production   900 units Materials:     Standard price per ounce $1.758     Standard ounces per completed unit 11     Actual ounces purchased and used in production 10,197     Actual price paid for materials $20,904 Labor:     Standard hourly labor rate $14.09 per hour     Standard hours allowed per completed unit 4.4     Actual labor hours worked 4,635     Actual total labor costs $75,319 Overhead:     Actual and budgeted fixed overhead $1,054,000     Standard variable overhead rate $24.00 per...
The following data are given for Stringer Company: Budgeted production 959 units Actual production   1,063 units...
The following data are given for Stringer Company: Budgeted production 959 units Actual production   1,063 units Materials:     Standard price per ounce $1.9     Standard ounces per completed unit 10     Actual ounces purchased and used in production 10,949     Actual price paid for materials $22,445 Labor:     Standard hourly labor rate $14.96 per hour     Standard hours allowed per completed unit 4.6     Actual labor hours worked 5,474.45     Actual total labor costs $83,485 Overhead:     Actual and budgeted fixed overhead $1,186,000     Standard variable overhead rate $27.00 per...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT