In: Finance
Consider a project to supply your church with 55,000
gallons of hand sanitizer annually for church services. You
estimate that you will need an initial Gh¢4,200,000 in terms of
investment to get the project started. The project will last for 5
years.
The project will bring in annual cash flows of Gh¢1,375,000. It
also estimates a salvage value of Gh¢300,000 after dismantling
costs.
Your cost of capital is 13 percent. Assume no taxes or
depreciation.
Required:
What is the NPV of the sanitizer project? Should you pursue this
project?
b) Suppose you believe that there is a best case
scenario where initial investment could be 15% lower with salvage
value and revenue being 10% higher, what would be the NPV under
this scenario?
c) In the worst case scenario, you expect annual cash inflows to be
10% lower, salvage value to be 12% lower and initial investment to
be 10% higher. Calculate the NPV under this worst case scenario.
Would you still pursue the project?
d) You just received additional information that suggests that your
base case (answer to a), best case (b) and worst case (c) scenarios
have probabilities of 0.35, 0.35 and 0.30 respectively. What will
be the expected NPV
of the sanitizer project. What about the standard deviation of the
sanitizer project? Do you think the project is still viable?
a). Project NPV = sum of present value of cash flows discounted at the cost of capital
= -initial investment + Present Value (PV) of annual cash flows + PV of salvage value
= -4,200,000 + (1,375,000/13%)*(1 - (1+ 13%)^-5) + 300,000/(1+13%)^5 = 799,020.97
The project can be accepted since it has a positive NPV.
b). Best case scenario:
Initial investment = 4,200,000*(1-15%) = 3,570,000
Annual cash flow = 1,375,000*(1+10%) = 1,512,500
Salvage value = 300,000*(1+10%) = 330,000
NPV = -3,570,000 + (1,512,500/13%)*(1 - (1+ 13%)^-5) + 330,000/(1+13%)^5 = 1,928,923.06
c). Worst case scenario:
Initial investment = 4,200,000*(1+10%) = 4,620,000
Annual cash flow = 1,375,000*(1-10%) = 1,237,500
Salvage value = 300,000*(1-12%) = 264,000
NPV = -4,620,000 + (1,237,500/13%)*(1 - (1+ 13%)^-5) + 264,000/(1+13%)^5 = -124,137.69
d). Expected NPV = sum of [probability of each case*NPV of that case]
Standard deviation of the NPV = [sum of [probability*(NPV - expected NPV)^2]^0.5
Expected NPV = 917,539.10
Standard deviation = 829,733.44
The project can still be accepted as expected NPV is positive. Even if expected NPV deviates by 829,733.44, it will still have a positive NPV.