In: Finance
Questions:
Consider a project to supply your church with 55,000 gallons of hand sanitizer annually for church services. You estimate that you will need an initial Gh¢4,200,000 in terms of investment to get the project started. The project will last for 5 years.
The project will bring in annual cash flows of Gh¢1,375,000. It also estimates a salvage value of Gh¢300,000 after dismantling costs.
Your cost of capital is 13 percent. Assume no taxes or depreciation.
Required:
b) Suppose you believe that there is a best case scenario where initial investment could be 15% lower with salvage value and revenue being 10% higher, what would be the NPV under this scenario?
c) In the worst case scenario, you expect annual cash inflows to be 10% lower, salvage value to be 12% lower and initial investment to be 10% higher. Calculate the NPV under this worst case scenario. Would you still pursue the project?
d) You just received additional information that suggests that your base case (answer to a), best case (b) and worst case (c) scenarios have probabilities of 0.35, 0.35 and 0.30 respectively. What will be the expected NPV of the sanitizer project. What about the standard deviation of the sanitizer project? Do you think the project is still viable?
a. Base case | ||||||
Year | 0 | 1 | 2 | 3 | 4 | 5 |
1.Initial Investment | -4200000 | |||||
2.Net Salvage | 300000 | |||||
3.Annual Cash flows | 1375000 | 1375000 | 1375000 | 1375000 | 1375000 | |
4.Total annual FCFs(1+2+3) | -4200000 | 1375000 | 1375000 | 1375000 | 1375000 | 1675000 |
5.PV F at 13%(1/1.13^yr.n) | 1 | 0.88496 | 0.78315 | 0.69305 | 0.61332 | 0.54276 |
6.PV at 13%(4*5) | -4200000 | 1216814 | 1076827 | 952944 | 843313.3 | 909122.9 |
7.NPV (sum of Row 6)) | 799021 |
Yes. The project can be pursued as it returns POSITIVE NPV of its cash flows at 13% cost of capital. |
b. Best case | ||||||
Year | 0 | 1 | 2 | 3 | 4 | 5 |
1.Initial Investment | -3570000 | |||||
2.Net Salvage | 330000 | |||||
3.Annual Cash flows | 1512500 | 1512500 | 1512500 | 1512500 | 1512500 | |
4.Total annual FCFs(1+2+3) | -3570000 | 1512500 | 1512500 | 1512500 | 1512500 | 1842500 |
5.PV F at 13%(1/1.13^yr.n) | 1 | 0.88496 | 0.78315 | 0.69305 | 0.61332 | 0.54276 |
6.PV at 13%(4*5) | -3570000 | 1338496 | 1184509 | 1048238 | 927644.6 | 1000035 |
7.NPV (sum of Row 6)) | 1928923 |
c. Worst case | ||||||
Year | 0 | 1 | 2 | 3 | 4 | 5 |
1.Initial Investment | -4620000 | |||||
2.Net Salvage | 264000 | |||||
3.Annual Cash flows | 1237500 | 1237500 | 1237500 | 1237500 | 1237500 | |
4.Total annual FCFs(1+2+3) | -4620000 | 1237500 | 1237500 | 1237500 | 1237500 | 1501500 |
5.PV F at 13%(1/1.13^yr.n) | 1 | 0.88496 | 0.78315 | 0.69305 | 0.61332 | 0.54276 |
6.PV at 13%(4*5) | -4620000 | 1095133 | 969144 | 857649.6 | 758981.9 | 814954 |
7.NPV (sum of Row 6)) | -124138 |
d..Summary of NPVs | |
Base case | 799021 |
Best case | 1928923 |
Worst case | -124138 |
Expected NPV of the sanitizer project |
(0.35*799021)+(0.35*1928923)+(30%*-124138)= |
917539 |
Standard deviation of the sanitizer project= |
Sq. rt. Of (sum of Variances/No.of scenarios) |
ie. (((799021-917539)^2+(1928923-917539)^2+(-124138-917539)^2)/3)^(1/2)= |
841038.07 |
Coefficient of variation= |
Standard deviation/Expected NPV |
ie. 841038/917539= |
0.92 |
A coefficient of variation less than 1 is acceptable |
Hence the project is STILL VIABLE & Can be accepted. |