In: Finance
Summer Tyme, Inc., is considering a new 3-year expansion project that requires an initial fixed asset investment of $2.97 million. The fixed asset will be depreciated straight-line to zero over its 3-year tax life, after which time it will have a market value of $231,000. The project requires an initial investment in net working capital of $330,000. The project is estimated to generate $2,640,000 in annual sales, with costs of $1,056,000. The tax rate is 33 percent and the required return on the project is 13 percent. |
Required: | |
(a) | What is the project's year 0 net cash flow? |
(Click to select) -3,630,000 -3,300,000 -3,135,000 -2,970,000 -3,465,000 |
(b) | What is the project's year 1 net cash flow? |
(Click to select) 1,249,182 1,387,980 1,318,581 1,457,379 1,526,778 |
(c) | What is the project's year 2 net cash flow? |
(Click to select) 1,457,379 1,526,778 1,318,581 1,249,182 1,387,980 |
(d) | What is the project's year 3 net cash flow? |
(Click to select) 1,966,388 1,685,475 1,779,113 2,060,025 1,872,750 |
(e) | What is the NPV? |
(Click to select) 1,302,982 313,203 307,233 328,863 -612,684 |
- Initial Fixed Investments =$2.97 million
Initial Investment in working capital = $330,000
a). Project's year 0 net cash flow = Initial Fixed Investments + Initial Investment in working capital
=$2,970,000 + $330,000
=$3,300,000
Hence, Option B. -$3,300,000
- Depreciation of Fixed Assets = Initial Fixed Investments/Assets life
=$2970,000/3years
= $990,000
Computing the Project's year Net Cash flow:-
Particular | Year 1 | Year 2 | Year 3 |
Annual Sales | 2640,000 | 2640,000 | 2640,000 |
Less: Costs | (1056,000) | (1056,000) | (1056,000) |
Less: Depreciation | (990,000) | (990,000) | (990,000) |
Income before Tax | 594,000 | 594,000 | 594,000 |
Less: Tax Rate@33% | (196,020) | (196,020) | (196,020) |
Net Income | 397,980 | 397,980 | 397,980 |
Add: Depreciation | 990,000 | 990,000 | 990,000` |
Cash Flow after tax | 1387,980 | 1387,980 | 1387,980 |
Add: Initial Net working capital | 0 | 0 | 330,000 |
Add: After tax salvage Value [$231,000*(1-0.33)] | 0 | 0 | 154,770 |
Net Cash flow of project | 1387,980 | 1387,980 | 1872,750 |
(b) Project's year 1 net cash flow = $1387,980
Hence, Option B
(c) Project's year 2 net cash flow = $1387,980
Hence, Option E
(d) Project's year 3 net cash flow = $1872,750
Hence, Option E
e). Calculating the NPV of the Project:-
Year | Net Cash Flows of Project ($) | PV Factor @13.00% | Present Value Net Cash Flows of Project ($) |
0 | (3,300,000.00) | 1.0000 | (3,300,000.00) |
1 | 1,387,980.00 | 0.8850 | 1,228,300.88 |
2 | 1,387,980.00 | 0.7831 | 1,086,991.93 |
3 | 1,872,750.00 | 0.6931 | 1,297,909.69 |
313,202.51 |
So, NPV of the Project is $313,202.51
Hence, Option B. $ 313,203
If you need any clarification, you can ask in comments.
If you like my answer, then please up-vote as it will be motivating