Question

In: Finance

Exotic Rentals has four independent projects under consideration, each with a required rate of return of...

Exotic Rentals has four independent projects under consideration, each with a required rate of return of 14%. The total projects budget is $800,000. A table showing the investments and projected free cash flows follow:

Project/Year Maserati Lamborghini Ferrari BMW i8 Coupe
0 (investment) $150,380 $221,320 $286,550 $175,500
1 $40,000 $85,000 $100,000 $52,000
2 $80,000 $110,000 $125,000 $90,000
3 $60,000 $110,000 $125,000 $90,000
4 $60,000 $92,000 $125,000 $70,000
5 $95,000 $125,000 $150,000 $135,000

No additional cash flows are expected from any of the five projects after year 5. The year 5 cash flow includes rentals and auction of the exotic vehicles into the secondary car market.

1- Which of the 4 projects has the highest IRR? The correct answer was determined using an Excel spreadsheet. Take answer to at least two decimal positions.

a) Ferrari

b) BMW i8 Coupe

c) Maserati

d) Lamborghini

2- Continuing with Exotic Rentals, the company has sufficient capital budget to fund three out of the four projects. Assuming that they do, what three projects should the firm select? Use highest NPV's to determine the projects to select.

a) BMW i8 Coupe, Maserati, Lamborghini

b) Ferrara, BMW i8 Coupe, Maserati

c) Lamborghini, Ferrari, BMW i8 Coupe

d) Maserati, Lamborghini, Ferrari

3- Continuing with Exotic Rentals, what is the combined NPV of these two projects: BMW i8 Coupe and Maserati

a) $448,464

b) $325,800

c) $509,182

d) $384,759

e) $183,302

4- Continuing with Exotic Rentals, what is the combined IRR of these two projects: Lamborghini and Ferrari?

a) 32.94%

b) 33.24%

c) 30.92%

d) 66.47%

e) 35.55%

5- Concluding Exotic Rentals, firm management is considering a loan to supplement the $800,000 set aside for the vehicles. The size of the loan would be approximately $34,000 and the interest rate would be 11.25%. Should Exotic Rentals take out the loan and fund all four projects? Base you decision only on the financial aspects of the deal.

a) No

b) Insufficient information to make a decision

c) Yes

Solutions

Expert Solution

Use IRR function in EXCEL to find the IRR

=IRR(Year0 to Year5 cashflows)

Use NPV function in EXCEL

=NPV(rate,Year1 to year5 cashflows)-Year0 cashflow

rate=14%

required return 14%
Maserati Lamborghini Ferrari BMW i8 Coupe
Year0 -150380 -221320 -286550 -175500
Year1 40000 85000 100000 52000
Year2 80000 110000 125000 90000
Year3 60000 110000 125000 90000
Year4 60000 92000 125000 70000
Year5 95000 125000 150000 135000
NPV 71628.25 131522.17 133639.51 111673.94
IRR 30.51% 35.55% 30.92% 35.05%

1. Lamborghini will have higher IRR

2. Option C is correct

Lamborghini, Ferrari, BMW i8 Coupe have higher NPV's

3. Combined NPV of BMW i8 Coupe and Maserati=71628.15+111673.94=183302.19

Option e is correct

4. Combined Lamborghini and Ferrari IRR=35.55%+30.92%=66.47%

option d is correct

5. Option c, Yes.

They can fund beacuse the interest rate is lower than both cost of capital of 14% and IRR5's of all the projects.


Related Solutions

A project under consideration has an internal rate of return of 13% and a beta of...
A project under consideration has an internal rate of return of 13% and a beta of 0.8. The risk-free rate is 3%, and the expected rate of return on the market portfolio is 13%. a. What is the required rate of return on the project? (Do not round intermediate calculations. Enter your answer as a whole percent.) b. Should the project be accepted? c. What is the required rate of return on the project if its beta is 1.80? (Do...
A project under consideration has an internal rate of return of 13% and a beta of...
A project under consideration has an internal rate of return of 13% and a beta of 0.5. The risk-free rate is 3%, and the expected rate of return on the market portfolio is 13%. a-1. Calculate the required return.   Required return %   a-2. Should the project be accepted? Yes No b-1. Calculate the required return if its beta is 1.5.   Required return %   b-2. Should the project be accepted? Yes No
A project under consideration has an internal rate of return of 13% and a beta of...
A project under consideration has an internal rate of return of 13% and a beta of 0.4. The risk-free rate is 3%, and the expected rate of return on the market portfolio is 13%. a. What is the required rate of return on the project? (Do not round intermediate calculations. Enter your answer as a whole percent.) b. Should the project be accepted? Yes No c. What is the required rate of return on the project if its beta is...
There are two projects under consideration by the Rainbow factory. Each of the projects will require...
There are two projects under consideration by the Rainbow factory. Each of the projects will require an initial investment of $34,000 and is expected to generate the following cash flows: First Year Second Year Third Year Total Alpha Project $32,500   $22,000     $5,500   $60,000 Beta Project 8,000   23,000     28,000   59,000 (Click here to see present value and future value tables) A. If the discount rate is 10%, compute the NPV of each project. Round your present value factor to three decimal...
You are considering two independent projects. The required rate of return is 13.75 percent for Project...
You are considering two independent projects. The required rate of return is 13.75 percent for Project A and 14.25 percent for Project B. Project A has an initial cost of $51,400 and cash inflows of $21,400, $24,900, and $22,200 for Years 1 to 3, respectively. Project B has an initial cost of $38,300 and cash inflows of $23,000 a year for 2 years. Which project(s), if either, should you accept? Accept both A and B Reject both A and B...
University Hospital has four capital projects under consideration with the following investments and projected cash flows....
University Hospital has four capital projects under consideration with the following investments and projected cash flows. What is their optimal capital budget allocation if their corporate cost of capital is 12%? Year 0 1 2 3 4 5 Project A        (600,000)                                 50,000                    90,000        150,000        200,000        250,000 B        (400,000)                                 80,000                  100,000        100,000        100,000        100,000 C        (700,000)                              100,000                  220,000        250,000        250,000        250,000 D       ...
Optimization of Capital Budgets University Hospital has four capital projects under consideration with the following investments...
Optimization of Capital Budgets University Hospital has four capital projects under consideration with the following investments and projected cash flows. What is their optimal capital budget allocation if their corporate cost of capital is 12%? Year 0 1 2 3 4 5 Project A        (600,000)                                  50,000                     90,000         150,000         200,000         250,000 B        (400,000)                                  80,000                   100,000         100,000         100,000         100,000 C        (700,000)                               100,000                   220,000         250,000         250,000...
You are considering two independent projects that have differing requirements. Project A has a required return...
You are considering two independent projects that have differing requirements. Project A has a required return of 12 percent compared to Project B's required return of 13.5 percent. Project A costs $75,000 and has cash flows of $21,000, $49,000, and $12,000 for Years 1 to 3, respectively. Project B has an initial cost of $70,000 and cash flows of $15,000, $18,000, and $41,000 for Years 1 to 3, respectively. Based on the NPV, you should:
A company has a required rate of return of 15% for five potential projects. The company...
A company has a required rate of return of 15% for five potential projects. The company has a maximum of $500,000 available for investment and cannot raise any capital. Details about the five projects are as follows: Project Initial Outlay Net Present Value at 15% Internal Rate of Return 1 $500,000 $125,000 23% 2   250,000 75,000 17% 3   150,000 25,000 35% 4   100,000 50,000 25% 5   150,000 50,000 25% The company should choose which of the following projects? a. Project...
5. You are considering two independent projects. The required return for both projects is 13 percent....
5. You are considering two independent projects. The required return for both projects is 13 percent. Project A has an initial cost of $145,000 and cash inflows of $62,000, $53,000, and $70,000 for Years 1 to 3, respectively. Project B has an initial cost of $95,000 and cash inflows of $40,000, $44,000, and $35,000 for Years 1 to 3, respectively. Given this information, which one of the following statements is correct based on the NPV and IRR methods of analysis?...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT