In: Accounting
Problem 3-2A (Video) (Part Level Submission)
Rosenthal Company manufactures bowling balls through two
processes: Molding and Packaging. In the Molding Department, the
urethane, rubber, plastics, and other materials are molded into
bowling balls. In the Packaging Department, the balls are placed in
cartons and sent to the finished goods warehouse. All materials are
entered at the beginning of each process. Labor and manufacturing
overhead are incurred uniformly throughout each process. Production
and cost data for the Molding Department during June 2020 are
presented below.
Production Data |
June |
||
Beginning work in process units | 0 | ||
Units started into production | 25,740 | ||
Ending work in process units | 2,340 | ||
Percent complete—ending inventory | 40 | % |
Cost Data |
||
Materials | $231,660 | |
Labor | 62,712 | |
Overhead | 131,976 | |
Total | $426,348 |
Physical units | ||||||||
Units to be accounted for | ||||||||
Work in process,June 1 | 0 | |||||||
Started into production | 25,740 | |||||||
total units | 25,740 | |||||||
units accounted for | ||||||||
transferred out | 23,400 | |||||||
Work in process<june 30 | 2,340 | |||||||
Total units | 25,740 | |||||||
Materials | CC | |||||||
total Equivalent units | 25,740 | 24336 | ||||||
Materials | CC | Total | ||||||
units cost of production | 9.00 | 8.00 | 17.00 | |||||
Transferred out | 397800 | |||||||
Work in process june 30 | 28548 | |||||||
Production Cost Report | ||||||||
physical | Materials | CC | ||||||
Quantities | units | |||||||
units to be accounted for | ||||||||
work in process ,june 1 | 0 | |||||||
Started into production | 25,740 | |||||||
total units | 25740 | |||||||
units accounted for | ||||||||
Transferred out | 23,400 | 23,400 | 23,400 | |||||
Work in process,june 30 | 2,340 | 2,340 | 936 | |||||
total units | 25740 | 25740 | 24,336 | |||||
Costs | Materials | CC | total | |||||
unit costs | ||||||||
total costs | 231,660 | 194688 | 426,348 | |||||
Equivalent units | 25740 | 24,336 | ||||||
unit costs | 9 | 8 | 17 | |||||
Costs to be accounted for | ||||||||
work in process <june 1 | 0 | |||||||
Started into production | 426,348 | |||||||
total costs | 426348 | |||||||
Cost Reconcilation Schedule | ||||||||
costs accounted for | ||||||||
Transferred out | 397800 | |||||||
Work in process,jue 30 | ||||||||
Materials | 21060 | |||||||
CC | 7488 | 28548 | ||||||
total costs | 426348 | |||||||