In: Accounting
P3.2A (LO 3, 4), AP Rosenthal Company manufactures bowling balls through two processes: Molding and Packaging. In the Molding Department, the urethane, rubber, plastics, and other materials are molded into bowling balls. In the Packaging Department, the balls are placed in cartons and sent to the fi nished goods warehouse. All materials are entered at the beginning of each process. Labor and manufacturing overhead are incurred uniformly throughout each process. Production and cost data for the Molding Department during June 2020 are presented below. Journalize transactions. Complete four steps necessary to prepare a production cost report. Production Data June Beginning work in process units –0– Units started into production 22,000 Ending work in process units 2,000 Percent complete—ending inventory 40% Cost Data Materials $198,000 Labor 53,600 Overhead 112,800 Total $364,400
Instructions a. Prepare a schedule showing physical units of production. b. Determine the equivalent units of production for materials and conversion costs. c. Compute the unit costs of production. d. Determine the costs to be assigned to the units transferred out and in process for June. e. Prepare a production cost report for the Molding Department for the month of June.
a | |||||
Physical units | |||||
Units to be accounted for | |||||
Work in process, June 1 | 0 | ||||
Started into production | 22000 | ||||
Total units | 22000 | ||||
Units accounted for | |||||
Transferred out | 20000 | ||||
Work in process, June 30 | 2000 | ||||
Total units | 22000 | ||||
b | |||||
Materials | Conversion Costs | ||||
Equivalent units | 22000 | 20800 | |||
c | |||||
Materials | Conversion Costs | Total unit cost | |||
Unit costs | 9.00 | 8.00 | 17.00 | ||
d | |||||
Transferred out | 340000 | ||||
Work in process, June 30 | 24400 | ||||
e | |||||
ROSENTHAL COMPANY | |||||
Molding Department | |||||
Production Cost Report | |||||
For the Month Ended June 30, 2020 | |||||
Equivalent Units | |||||
Physical Units | Materials | Conversion Costs | |||
Units to be accounted for | |||||
Work in process, June 1 | 0 | ||||
Started into production | 22000 | ||||
Total units | 22000 | ||||
Units accounted for | |||||
Transferred out | 20000 | 20000 | 20000 | ||
Work in process, June 30 | 2000 | 2000 | 800 | ||
Total units | 22000 | 22000 | 20800 | ||
Costs | Materials | Conversion Costs | Total | ||
Unit costs: | |||||
Total costs | 198000 | 166400 | 364400 | ||
Equivalent units | 22000 | 20800 | |||
Unit costs | 9.00 | 8.00 | 17.00 | ||
Costs to be accounted for | |||||
Work in process, June 1 | 0 | ||||
Started into production | 364400 | ||||
Total costs | 364400 | ||||
Cost Reconciliation Schedule | |||||
Costs accounted for | |||||
Transferred out | 340000 | =20000*17 | |||
Work in process, June 30 | |||||
Materials | 18000 | =2000*9 | |||
Conversion costs | 6400 | 24400 | =800*8 | ||
Total costs | 364400 |