Question

In: Finance

You discovered a project opportunity which costs 74,000$ today. The project generates 12,000$ in two years,...

You discovered a project opportunity which costs 74,000$ today. The project generates 12,000$ in two years, costs 4,000 in three years and then generates 30,000 for the next 5 years. What is the payback period of this project?

Solutions

Expert Solution

Payback period is the time taken to recover the costs of the the project. Below table summarizes the CFs

Year Opening Balance CF Closing Balance
1 $            74,000.00 $                                   -   74000-0 = $74,000.00
2 $            74,000.00 $                   12,000.00 74000-12000 = $62,000.00
3 $            62,000.00 $                    -4,000.00 62000-(-4000) = $66,000.00
4 $            66,000.00 $                   30,000.00 66000-30000= $36,000.00
5 $            36,000.00 $                   30,000.00 36000-30000 = $6,000.00
6 $              6,000.00 $                   30,000.00 6000- 30000= $-24,000.00

As the closing balance becomes negative at the end of year 6 it doesn't matter what the CFs are post this point. This is a big flaw of this method because if there is a big negative CF after this point, it is not considered in the decision making process.

Opening balance of year 1= Cost of the project or 74000
Opening balance = previous year's closing balance for all years after year 1
Closing balance = Opening balance - CF

The closing balance of year 5 was 6000 and the CF for year 6 was 30000 so the portion of year during which the 6000 is recovered is 6000/30000 = 0.2

So the payback period is 5.2 years

So the correct option is option 2


Related Solutions

You discovered a project opportunity which costs 74,000$ today. The project generates 12,000$ in two years,...
You discovered a project opportunity which costs 74,000$ today. The project generates 12,000$ in two years, costs 4,000 in three years and then generates 30,000 for the next 5 years. What is the payback period of this project?
You are planning to invest in a project which costs $40 million today. The project will...
You are planning to invest in a project which costs $40 million today. The project will produce returns of $4 million per year for five years and the scrap value will be $20 million. That is, you will receive $4 million at the end of the year, for each of the next five years, and you will receive $20 million at the end of the fifth year. Question (a) [2 marks] What is the net present value of the project...
You are considering two mutually exclusive projects, A and B. Project A costs $70,000 and generates...
You are considering two mutually exclusive projects, A and B. Project A costs $70,000 and generates cash flows of $10,000 for 10 years. Project B costs $80,000 and generates cash flows of $2,000 for six years and then cash flows of $28,000 for four years. Report rates in percentage form to two decimal places i.e. 10.03% not 10% At what discount rate would make you indifferent between choosing one project or another? What is the highest discount rate in which...
You are considering two mutually exclusive projects, A and B. Project A costs $70,000 and generates...
You are considering two mutually exclusive projects, A and B. Project A costs $70,000 and generates cash flows of $12,000 for 10 years. Project B costs $60,000 and generates cash flows of $2,000 for six years and then cash flows of $29,000 for four years. Which project would you accept if your discount rate was 10%? Which project would you accept if your discount rate was 5%?
You are considering a project that costs $500 to invest in today, and will pay you $100 next year, $50 in two years, and $100 in three years.
You are considering a project that costs $500 to invest in today, and will pay you $100 next year, $50 in two years, and $100 in three years. The cash inflow will grow at a constant rate of 3% per year after year 3, and you will receive cash inflows for 25 years (total including the first three CFs). Your discount rate is 14%. What is the NPV of the project? Also, what would the NPV be if the cash...
You are considering a project that costs $500 to invest in today, and will pay you $100 next year, $50 in two years, and $100 in three years.
  You are considering a project that costs $500 to invest in today, and will pay you $100 next year, $50 in two years, and $100 in three years. The cash inflow will grow at a constant rate of 3% per year after year 3, and you will receive cash inflows for 25 years (total including the first three CFs). Your discount rate is 14%. What is the NPV of the project? Also, what would the NPV be if the...
What is the EAC of two projects: project A, which costs $150 and is expected to last two years, and project B, which costs $190 and is expected to last three years?
  Q2. What is the EAC of two projects: project A, which costs $150 and is expected to last two years, and project B, which costs $190 and is expected to last three years? The cost of capital is 12%. (1 mark) Answer: Q3. A company pays annual dividends of $10.40 with no possibility of it changing in the next several years. If the firm’s stock is currently selling at $80, what is the required rate of return? (1 mark)...
1) Today you borrow 12,000 for 5 years. The bank lends you this money with an...
1) Today you borrow 12,000 for 5 years. The bank lends you this money with an interest rate of 7%. What would be the interest expense each year on this fully amortized loan? 2) You are in the leasing business and have 20,000 asset to lease. If you require a 12% return on your asset, and the lease term is 9 years, how much would the lease payment be at the beginning of each year?
You are evaluating a project that costs $61,000 today. The project has an inflow of $132,000...
You are evaluating a project that costs $61,000 today. The project has an inflow of $132,000 in one year and an outflow of $51,000 in two years. What are the IRRs for the project? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and enter your answers as a percent rounded to 2 decimal places, e.g., 32.16.)    IRR   Smallest %   Largest %    What discount rate results in the maximum NPV for this...
You are evaluating a project that costs $67,000 today. The project has an inflow of $144,000...
You are evaluating a project that costs $67,000 today. The project has an inflow of $144,000 in one year and an outflow of $57,000 in two years. What are the IRRs for the project? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and enter your answers as a percent rounded to 2 decimal places, e.g., 32.16.)    IRR   Smallest %   Largest % What discount rate results in the maximum NPV for this project?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT