In: Finance
A company is analyzing two mutually exclusive projects, S and L, with the following cash flows:
A company is analyzing two mutually exclusive projects, S and L, with the following cash flows:
The company's WACC is 9.5%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places. % |
Project S | -$1,000 | $882.50 | $250 | $15 | $5 |
Project L | -$1,000 | $5 | $260 | $420 | $769.95 |
The company's WACC is 9.5%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places.
%
Let’s compute NPV of both the projects.
NPV = PV of future cash inflow – Initial investment
Project S |
Project L |
|||||
Year |
Computation of PV Factor |
PV Factor @ 9.5 % (F) |
Cash Flow (CS) |
PV (CS x F) |
Cash Flow (CL) |
PV (CL x F) |
0 |
1/ (1+0.095)0 |
1 |
-$1000 |
-$1,000 |
-$1,000 |
-$1,000 |
1 |
1/ (1+0.095)1 |
0.913242009132420 |
882.5 |
805.93607 |
5 |
4.56621 |
2 |
1/ (1+0.095)2 |
0.834010967244219 |
250 |
208.50274 |
260 |
216.84285 |
3 |
1/ (1+0.095)3 |
0.761653851364584 |
15 |
11.42481 |
420 |
319.89462 |
4 |
1/ (1+0.095)4 |
0.695574293483638 |
5 |
3.47787 |
769.95 |
535.55743 |
NPVS |
$29.34149 |
NPVL |
$76.86111 |
NPV of Project S = $ 29.34
NPV of Project L = $ 76.86
Project L seems to be better as it has higher NPV and it adds higher value to the firm.
Computation of IRR of Project L using trial and error method:
Computation of NPV at discount rate of 11 %.
Year |
Computation of PV Factor |
PV Factor @ 11 % (F) |
Cash Flow (CL) |
PV (CL x F) |
0 |
1/ (1+0.11)0 |
1 |
-$1,000 |
-$1,000 |
1 |
1/ (1+0.11)1 |
0.900900900900901 |
5 |
4.50450 |
2 |
1/ (1+0.11)2 |
0.811622433244055 |
260 |
211.02183 |
3 |
1/ (1+0.11)3 |
0.731191381300950 |
420 |
307.10038 |
4 |
1/ (1+0.11)4 |
0.658730974145000 |
769.95 |
507.18991 |
NPV1 |
$29.81662 |
As NPV is positive let’s compute NPV at discount rate of 12 %
Year |
Computation of PV Factor |
PV Factor @ 12 % (F) |
Cash Flow (CL) |
PV (CL x F) |
0 |
1/ (1+0.12)0 |
1 |
-$1,000 |
-$1,000 |
1 |
1/ (1+0.12)1 |
0.89285714285714 |
5 |
4.46429 |
2 |
1/ (1+0.12)2 |
0.79719387755102 |
260 |
207.27041 |
3 |
1/ (1+0.12)3 |
0.71178024781341 |
420 |
298.94770 |
4 |
1/ (1+0.12)4 |
0.63551807840483 |
769.95 |
489.31714 |
NPV2 |
-$0.00046 |
IRR = R1 + [NPV1 x (R2 – R1)/ (NPV1 – NPV2)]
= 11 % + [$ 29.81662 x (12% - 11%)/ ($ 29.81662 – (-$ 0.00046))]
= 11 % + [($ 29.81662 x 1 %)/ ($ 29.81662 + $ 0.00046)]
= 11 % + ($ 0.2981662 / $ 29.81709)
= 11 % + 0.009999846
= 11 % + 0.999984573 % = 12.00 %
IRR of the better project, project L is 12 %