In: Accounting
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. It started only two jobs during March—Job P and Job Q. Job P was completed and sold by the end of March and Job Q was incomplete at the end of March. The company uses a plantwide predetermined overhead rate based on direct labor-hours. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March):
Estimated total fixed manufacturing overhead | $ | 11,000 | |
Estimated variable manufacturing overhead per direct labor-hour | $ | 1.20 | |
Estimated total direct labor-hours to be worked | 2,200 | ||
Total actual manufacturing overhead costs incurred | $ | 12,700 | |
Job P | Job Q | |||||
Direct materials | $ | 13,200 | $ | 8,200 | ||
Direct labor cost | $ | 16,900 | $ | 7,800 | ||
Actual direct labor-hours worked | 1,300 | 600 |
10. Calculate the cost of goods sold using the direct method.
11. Calculate the cost of goods manufactured using the indirect method.
12. Calculate the cost of goods sold using the indirect method.
13. How would you revise your answer to question 11 if the company had beginning work in process inventory of $8,200?
14. How would you revise your answer to question 12 if the company had beginning finished goods inventory of $12,200?
15. Assume that Job P includes 24 units that each sell for $2,600 and that the company’s selling and administrative expenses in March were $20,000. Prepare an absorption costing income statement for March.
Dear student, we cannot able to post solution more than four subparts of the question as per our policy.
Estimated total fixed manufacturing overhead | $ 11,000 | ||
Estimated total direct labor-hours to be worked | 2,200 | ||
Estimated fixed manufacturing overhead per direct labor-hour | $ 5.00 | ||
Add: Estimated variable manufacturing overhead per direct labor-hour | $ 1.20 | ||
Predetermined Overhead Rate | $ 6.20 | ||
Job P | Job Q | Total | |
Actual direct labor-hours worked | 1,300 | 600 | |
Predetermined Overhead Rate | $ 6.20 | $ 6.20 | |
Applied manufacturing overhead | $ 8,060 | $ 3,720 | $ 11,780 |
Total actual manufacturing overhead costs incurred | $ 12,700 | ||
Less: Total manufacturing overhead applied | $ 11,780 | ||
Underapplied of overhead applied | $ 920 |
Answer 10
Calculate the cost of goods sold using the direct method. | |||
Direct Material | $ 13,200 | ||
Direct labor cost | $ 16,900 | ||
Applied manufacturing overhead | $ 8,060 | ||
Unadjusted Cost of Good sold | $ 38,160 | ||
Add: Underapplied of overhead applied | $ 920 | ||
Adjusted Cost of Good sold | $ 39,080 |
Answer 11
Calculate the cost of goods manufactured using the indirect method. | |||
Beginning work-in progress | $ 0 | ||
Total direct materials (13200+8200) | $ 21,400 | ||
Total direct labor cost (16900+7800) | $ 24,700 | ||
Applied Manufacturing overhead | $ 11,780 | ||
Total manufacturing cost | $ 57,880 | ||
Total cost of work in progress | $ 57,880 | ||
Less: Ending work-in progress (Cost of Job Q = 8200+7800+3720) | $ 19,720 | ||
Cost of Good manufactured | $ 38,160 |
Answer 12
Calculate the cost of goods sold using the indirect method. | |||
Beginning Finished Goods Inventory | $ 0 | ||
Add: Cost of Goods Manufactured | $ 38,160 | ||
Cost of Goods available for sale | $ 38,160 | ||
Less: Ending Finished Goods Inventory | $ 0 | ||
Unadjusted Cost of good sold | $ 38,160 | ||
Add: underapplied overhead | $ 920 | ||
Adjusted Cost of Good sold | $ 39,080 |
Answer 13
How would you revise your answer to question 11 if the company had beginning work in process inventory of $8,200? | |||
Beginning work-in progress | $ 8,200 | ||
Total direct materials (13200+8200) | $ 21,400 | ||
Total direct labor cost (16900+7800) | $ 24,700 | ||
Applied Manufacturing overhead | $ 11,780 | ||
Total manufacturing cost | $ 57,880 | ||
Total cost of work in progress | $ 66,080 | ||
Less: Ending work-in progress (Cost of Job Q = 8200+7800+3720) | $ 19,720 | ||
Cost of Good manufactured | $ 46,360 |